Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080)

The Proposed Project 

Vancouver Fraser Port Authority (the Permit Holder) proposes to carry out physical activities related to the approved Area IV Site Preparation 24 hours a day, 7 days a week, excluding Statutory Holidays  for approximately 16 weeks, concluding on February 28, 2021. This would require an amendment to condition 18 of the approved project permit (PER No. 17-080) which states:  

All general construction and physical activities related to the Project shall be conducted from Monday to Saturday between the hours of 7:00 am and 8:00 pm. No construction and physical activities shall occur during Sundays or holidays. These hours shall not be modified without prior approval from VFPA. 

The scope of the amendment in relation to the delivery and placement of sand from dredged material (pumped to the site from a vessel in the Fraser River via supply pipeline), is being requested to ensure the dredging vessel can run 24 hours a day, 7 days a week as this is how the vessel is operated. The project components associated with this request include, creating a two metre high berm around the site to contain the water used to deliver sand, preloading the site by pumping dredged material from the Fraser River to an elevation of 7-12 metres, and the discharge of dewatering water back to the river using a pump and dewatering pipeline after being temporarily treated in drainage swales. Heavy equipment will distribute the sand on site to achieve the desired loading. 

The Vancouver Fraser Port Authority understands that noise generated in relation to the works concerning the delivery and placement of sand on the site will originate primarily from diesel equipment and pumps. This noise is not anticipated to be audible beyond the site boundaries and is consistent with other activities happening in the vicinity of the project site.  

More


Latest update

Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080) – Notice of determination 

November 9, 2020 – The Vancouver Fraser Port Authority has determined that the proposed amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080), located at Area IV – Richmond Logistics Hub, west of No. 7 Road Canal, Richmond is not likely to cause significant adverse environmental effects.

Participate

Contacts

Project and Environmental Review
Vancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com


  • Location

    • Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080) (British Columbia)
  • Nature of Activity

    • Building and Property Development
    • Other, not otherwise specified
  • Assessment Status

    Completed
  • Start Date

    2020-10-02
  • Proponent

    Vancouver Fraser Port Authority
  • Authorities

    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    81045