Canadian Coast Guard Purfleet Point Front and Rear Range Rebuild

Based on an ongoing review process, the Canadian Coast Guard identifies locations where fixed aids to navigation are required to be constructed, maintained, modified, or relocated and seeks the assistance of qualified consultants and contractors in providing these services. This project area is within the Lower Fraser River at the southwest end of Annacis Is. The project proposes to remove and rebuild 2 navigational aids in the Fraser River and remove 1 abandoned aid  structure.  LL357 Purfleet Point Rear Range  and the abandoned site are based on the shore of Annacis Island and LL 356 Purfleet Front Range is in-water and the tower has fallen over.  Each Range site is currently a light and sign board attached to a skeleton tower. The towers are secured to concrete platforms that sit on nine creosote timber piles.  Before the current aid is decommissioned the new aid will be built adjacent to the current one.  The components of the new aids will each consist of a single hollow, steel, 42" pile (1.067mØ) with a 19.1 mm wall thickness. It will also consist of a ladder to the concrete platform,  concrete platform secured to the pile that will house the steel tower with sign board and light, battery box with batteries and solar panel,  and railings. The steel pile driving will be completed with a spudded  barge and crane and the use of a vibratory hammer, with the potential for utilizing an impact hammer if the conditions require it. The platform, ladder and navigation aid component (light unit and day marker) will be installed on the new steel dolphin piling and will require some minor welding of metal tabs. The abandoned site consist of  nine piles  and is on the shore of Annacis Is. An Environmental Protection Plan is being developed.

In-water  work will occur on the two dolphin pile sites using a crane barge (marine contractor) and tug boat, and a small CCG work vessel. The project proposes to remove all 27 creosote timber piles, placing Purfleet Front Range with 1 hollow steel pile and Purfleet Rear Range with 1 hollow steel pile. The barge will function as the project's work platform and for containment of equipment, material and any wastes. All wastes will be removed from the work site. If heavy machinery has to access the land and the sites cannot be reached from the barge protective matts will be placed down in the intertidal area. Two small pockets of sediment will require dredging in front of the Rear Range and the abandoned site for the barge and equipment to access the work area. Pile extraction and installation will be completed according to CCG construction drawings using a spudded or anchored barge crane and the use of a vibratory hammer, with the potential for utilizing an impact hammer if the conditions require it. The platform, ladder and navigation aid component (light unit and day marker) will be installed on the new steel dolphin piling and will require some minor welding of metal tabs. The footprint of each site (nav-aid) will decrease. The CCG will be on the work barge during all pile driving and at completion of work. See attached files for site details. Work activities with the potential to adversely impact will follow DFO mitigation measures to prevent harm to fish and fish habitat. A request for review has been prepared and will be submitted to Fish and Fish Habitat Protection Program (FFHPP) for Review as well as an application to the Vancouver Port Authority and project review through Front Counter BC for provincially protected species. An application has also been submitted to Transport Canada in regards to the Navigation Protection Program.  Spill response kits will be present at both shore and in-water work sites.

The project is estimated to start sometime mid-March 31 2021 with work period of 5 days for the Front Range and mid-August 2021 (period of days still to be determined).

More


Latest update

February 12, 2021 – The public comment period on the project and its potential for causing adverse effects is closed. The Canadian Coast Guard The Canadian Coast Guard, Transport Canada, Fish and Fish Habitat Program and the Vancouver Fraser Port Authority  are considering comments received to inform its determination on whether the project is likely to cause significant adverse environmental effects. .

Participate

Contacts

Andrew Wight
Maritime and Civil Infrastructure, Canadian Coast Guard
Andrew Wight, Project Engineer
25 Huron Street
Victoria, British Columbia V8V 4V9
Telephone: 250-413-2835
Email: andrew.wight@dfo-mpo.gc.ca


  • Location

    • Lower Fraser River of the Vancouver Regional District, New Westminster, Annacis Island, British Columbia (British Columbia)
    • Lower Fraser River of the Vancouver Regional District, New Westminster, Annacis Island, British Columbia (British Columbia)
  • Nature of Activity

    • Other, not otherwise specified
  • Assessment Status

    Completed
  • Start Date

    2021-02-14
  • Proponent

    Canadian Coast Guard
  • Authorities

    • Fisheries and Oceans Canada
    • Transport Canada
    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    81286
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: