Shellburn Berthing Dolphin Replacement - Amendment PER No. 20-012-01 (Condition 23 - Extended Hours)
The Proposed Project Amendment
Shell Canada Products Ltd. proposes to carry out physical activities related to the replacement of four existing berthing dolphins and the installation of a fifth berthing dolphin at the Shellburn facility 24 hours a day, five days a week for the construction period from January 2021 to June 2022. These works require an amendment to condition 23 of the approved Shellburn Berthing Dolphin Replacement project permit (PER No. 20-012). The rationale for the extended work hours request is to allow for safe, efficient and timely completion of Project activities that are tidally dependent.
Project components associated with this request include formwork removal, fender panel installation, works to support installation of in-water piles such as splicing or welding pile sections together, and deck re-instatement activities. No pile driving activity (installation or removal) will be conducted outside of regular construction hours.
The Proposed Project
Shell Canada Products Limited, (the Applicant) is proposing to replace four existing berthing dolphins and install a fifth berthing dolphin to the existing wharf structure at the Shellburn facility in Burnaby, BC. The project consists of the removal of 185 timber piles and the installation of 65 timber and 29 concrete filled steel pipe piles. Eight temporary timber fender piles will be installed to secure construction-related support vessels and then removed once the project is complete. The project work will be carried out from a floating barge using a spud barge, materials barge, vibratory pile driving hammer and impact pile driving hammer. The proposed maintenance work will be carried out either from a floating barge or from the top of the dock. Marine vessel traffic would include a barge mounted crane for pile installation, and tugs to assist in barge movement. All waste materials will be collected within the immediate project area and transported to an appropriate facility for recycling or disposal. Project works are proposed to take place from July 2020 to March 2022, with in-water works occurring only during the least-risk fisheries window (August 16 to February 28, inclusive).
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Burnaby, B.C. –January 12, 2021 – The Vancouver Fraser Port Authority has determined that the proposed Shellburn Berthing Dolphin Replacement Project – Amendment PER No. 20-012-01 (Condition 23 - Extended Hours) located at 201 Kensington Ave., Burnaby, B.C., not likely to cause significant adverse environmental effects..
List all records
Contacts
Project and Environmental ReviewVancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com
-
Location
- Burnaby (British Columbia)
-
Project Type
- Ports and Harbours
-
Status
Completed -
Start Date
2020-12-11 -
Proponent
Shell Canada Products Limited -
Authorities
- Vancouver Fraser Port Authority
-
Assessment Type
Project on federal lands -
Reference Number
80510
Nearby projects
..within 200 kilometres-
Barge Ramp Beam Installation
Burnaby -
Installation of Eight Steel Pipe Piles - Project Permit No. 18-184 - Extension to the Expiry Date
Burnaby -
Cates Park Foreshore Erosion Protection Project
North Vancouver -
Removal of Concrete Boat Launch
Removal of concrete boat launch -
Existing Dock Upgrade for 4659 Strathcona
Existing Dock Upgrade for 4659 Strathcona -
Chemtrade maintenance dredging
Chemtrade maintenance dredging -
New Pile Installation for Recreational Dock
New Pile Installation for Recreational Dock -
District of North Vancouver Designated Anchorage Area
District of North Vancouver Designated Anchorage Area -
Water Supply Tunnel at Second Narrows - Metro Vancouver - Amendment
Water Supply Tunnel at Second Narrows - Metro Vancouver - Amendment -
Installation of Annex 4 Vacuum System
Installation of Annex 4 Vacuum System -
Rail Expansion with Tent
Rail Expansion with Tent -
Amendment to the construction hours in respect to condition 45 of the approved Pattullo Bridge Replacement Project (PER No. 17-107)
Amendment to the construction hours in respect to condition 45 of the approved Pattullo Bridge Replacement Project (PER No. 17-107) -
Site Upgrades and Road Realignment - Lynnterm - Project Permit No. 17-154-2 - Extension to the Expiry Date
Site Upgrades and Road Realignment - Lynnterm - Project Permit No. 17-154-2 - Extension to the Expiry Date -
Oil Spill Emergency Response Base - Project Permit No. 16-290 - Extension to the Expiry Date
Vancouver -
G3 Terminal Vancouver - G3 Limited - Project Permit No. 15-180 - Extension to the Expiry Date and Extended Work Hours
G3 Terminal Vancouver - G3 Limited - Project Permit No. 15-180 - Extension to the Expiry Date and Extended Work Hours -
Cascadia West Rail Extension
Vancouver -
G3 Terminal Vancouver Berth Pocket Obstruction Removals
G3 Terminal -
South Shore Corridor Project - Extension to Expiry Date
South Shore Corridor Project - Extension to Expiry Date -
Columbia Containers Shoreline Protection Repair
Columbia Containers Shoreline Protection Repair -
Neptune Terminal maintenance dredging at Berth 2 and 3
Neptune Terminal maintenance dredging at Berth 2 and 3 -
Dust Suppression Upgrade - Neptune Bulk Terminals (Canada) Ltd. - Project Permit 16-072 - Extension to the Expiry Date
Dust Suppression Upgrade - Neptune Bulk Terminals (Canada) Ltd. - Project Permit 16-072 - Extension to the Expiry Date -
Neptune - Rail Bypass Track Layout
Neptune - Rail Bypass Track Layout -
Pacific Coast Terminals Co. Ltd. Port Moody Channel Dredging Permit Amendment Request
Pacific Coast Terminals Co. Ltd. Port Moody Channel Dredging Permit Amendment Request -
Neptune Cargill Overpass Extension - Project Permit No. 17-131-1 - Amendment (Condition 17 - Extended Hours)
North Vancouver -
Mariner Seafoods Shoreline Protection
Mariner Seafoods Shoreline Protection -
Dredging to Deepen Berth 1 - Project Permit No. 18-027-1 - Amendment (Condition 23 - Extended Hours)
North Vancouver -
Neptune Coal Capacity Project and West Quadrant Shiploader - Project Permit No. 12-066-1 - Amendment (Condition 18 - Extended Hours)
North Vancouver -
Extension to expiry date of Project Permit No. 18-027: Dredging to deepen berth 1 at Neptune Bulk Terminals
Extension to expiry date of Project Permit No. 18-027: Dredging to deepen berth 1 at Neptune Bulk Terminals -
Extension - Temporary Construction Staging Parking and Barge Loading
Extension - Temporary Construction Staging Parking and Barge Loading -
Marine Operations Facility
Marine Operations Facility -
Trans Mountain Expansion Project
Burnaby -
Pacific Terminals Emergency Vehicle Road Access
Pacific Terminals Emergency Vehicle Road Access -
Pacific Terminals Annex 1 and 2 Vacuum System Upgrade
Pacific Terminals Annex 1 and 2 Vacuum System Upgrade -
Pacific Elevators New Dust Control System and Access
Pacific Elevators New Dust Control System and Access -
Global Container Terminal Vanterm Maintenance Dredging
Vancouver -
Rocky Point Park Boat Ramp Repair in Port Moody
Rocky Point Boat Ramp Repair in Port Moody -
Retaining wall replacement
Retaining wall replacement -
Amendment to dates - Centerm Expansion Project Fisheries Act Authorization
Vancouver -
Centerm Expansion Project - Amendment to Fisheries Act Authorization
Vancouver -
Centerm Expansion Project - Amendment PER No. 15-012-03 (Condition 47 - Extended Hours)
Centerm Expansion Project - Amendment PER No. 15-012-03 (Condition 47 - Extended Hours) -
Maintenance dredging - Centerm
Maintenance dredging - Centerm -
Seabin Installation at Main Street Dock
Vancouver, British Columbia -
Centerm Expansion Project - Amendment (Condition 66 - Dredging)
Centerm Expansion Project - Amendment (Condition 66 - Dredging) -
Schnitzer Fire Suppression Project - Design Amendment
Schnitzer Fire Suppression Project - Design Amendment -
Kings Mill Park Shoreline and Habitat Work
Kings Mill Park Shoreline and Habitat Work -
Maintenance Dredging at FRPD Waterlot
Maintenance Dredging at FRPD Waterlot -
Osprey Nest Platform
Osprey Nest Platform -
Subtidal Cobble Replacement
North Vancouver -
Schnitzer Steel Maintenance Dredging
Schnitzer Steel Maintenance Dredging -
Fraser Mills Foreshore Improvements
Fraser Mills Foreshore Improvements -
Lehigh Materials - Surrey Barge Ramp Project
Lehigh Materials - Surrey Barge Ramp Project -
CN rail bridge seismic retrofit project
CN rail bridge seismic retrofit project -
Georgia Pacific Gypsum Plant Demolition
Georgia Pacific Gypsum Plant Demolition -
Amix Pile and Float Removal
Amix Pile and Float Removal -
Seaspan Ship Load-out Gravel Bed and Shoreline Protection
North Vancouver -
Shoreline protection and retaining wall improvements project
Shoreline protection and retaining wall improvements project -
Fraser Mills Pile Removal
Fraser Mills Pile Removal -
Nanaimo Vancouver Passenger Only Ferry Service - South SeaBus Terminal - Project Permit No. 18-044-02 - Extension to the Expiry Date
Nanaimo Vancouver Passenger Only Ferry Service - South SeaBus Terminal - Project Permit No. 18-044-02 - Extension to the Expiry Date -
SeaBus Terminal Upgrades (Utilities)
SeaBus Terminal Upgrades (Utilities) -
Installation of scour protection
Installation of scour protection -
Shoreline Protection at 177 Duncan Street in New Westminster
Shoreline Protection at 177 Duncan Street in New Westminster -
Amendment to the construction hours and permit expiry date for the approved Sediment Remediation and Dike Construction
Amendment to the construction hours and permit expiry date for the approved Sediment Remediation and Dike Construction -
Flood Barrier
Vancouver -
Fibreco Terminal Enhancement Project Amendment (Stormwater Design)
North Vancouver -
Expansion of the Lumber Transload Facility of Goodrich Terminal2012 Ltd. at the Port of Vancouver
Port of Vancoouver -
Demolition of Office Building and Parking Canopies
Demolition of Office Building and Parking Canopies -
Installation of Pole Lights
100 Annacis Parkway, Annacis Island, Delta -
WWL Underground Storage Tank Removal Annacis Island
Delta -
Queensgate Maintenance Dredging
Queensgate Maintenance Dredging -
Annacis Water Supply Tunnel Safe Havens Amendment
Annacis Water Supply Tunnel Safe Havens Amendment -
Annacis Water Supply Tunnel Safe Havens Amendment
Annacis Water Supply Tunnel Safe Havens Amendment -
Royal Vancouver Yacht Club (RVYC) Coal Harbour Marina Expansion
Royal Vancouver Yacht Club (RVYC) Coal Harbour Marina Expansion -
Containerized dry bulk handling project
Containerized dry bulk handling project -
New Microwave system and antenna proposal at 1959 Marine Dr. North Vancouver, BC
1959 Marine Drive North Vancouver BC -
Barge Loading Facility
Barge loading facility -
Fraser Grain Terminal - Grain Export Facility - Amendment 06 - Grain Cleaner
Fraser Grain Terminal - Grain Export Facility - Amendment 06 - Grain Cleaner -
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-05 - Amendment (Condition 36 - Extended Hours)
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-05 - Amendment (Condition 36 - Extended Hours) -
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01
Creosote Pile Removal and Disposal - Extension PER No. 19-022-01 -
Conveyance for North Shore Wastewater Treatment Plant - Project Permit No. 17-090-1 - Amendment (Condition 51 - Extended Hours)
North Vancouver -
Annacis Island Wastewater Treatment Plant New Outfall - Project Permit No. 17-093-1 - Amendment (Condition 32 - Extended Hours)
Delta -
Surrey Langley SkyTrain Project and Broadway Subway Project
Surrey -
Fire Hydrant Replacement
Surrey Taxation Data Centre -
Delta Cedar New Pile Installation
Delta -
Vito Dock Maintenance Dredging
Delta -
Vito Shipyards Wharf Repairs
Delta -
Vito Shipyards Wharf Repairs amendment
Vito Shipyards Wharf Repairs amendment -
Truck Parking Construction - Nordel Way Area
Truck Parking Construction - Nordel Way Area -
Concrete Batch Plant
Vancouver -
Fraser River Pile and Dredge No. 8 Road Barge Ramp Maintenance Dredging
Richmond -
Delta Grinding Facility Project
Tilbury Island, Delta -
Construct Maintenance Building and Military Vehicle Parking at Richmond Armoury
Richmond Armoury, 5500 #4 Road, Richmond -
Fenceline Construction and Maintenance at Richmond Training Area
Colonel Sherman Armoury and Richmond Training Area -
Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080)
Amendment to the construction hours in respect to condition 18 of the approved Area IV Site Preparation (PER No. 17-080) -
Tilbury Phase 2 LNG Expansion Project
Tilbury Island, Delta -
WesPac Tilbury Marine Jetty Project
Tilbury Island, Delta -
Metro Vancouver - Conveyance for North Vancouver Wastewater Treatment Plant Amendment
Metro Vancouver - Conveyance for North Vancouver Wastewater Treatment Plant Amendment -
Vancouver Airport Fuel Delivery Project
Richmond -
Riparian Habitat Enhancement - Russ Baker Way Lands
Riparian Habitat Enhancement - Russ Baker Way Lands -
Pacific Enterprise Science Centre (PESC) Foreshore Maintenance
Pacific Enterprise Science Centre (PESC) -
Teal-Jones Maintenance Dredging
Teal-Jones Maintenance Dredging -
Katzie First Nation Shoreline Clean Up
Pitt Meadows -
Steveston Paramount Maintenance Dredging
Steveston Paramount Small Craft Harbour -
Langley Outfall Maintenance Dredging
Langley Outfall Maintenance Dredging -
Stormwater outfall and dike upgrades
Stormwater outfall and dike upgrades -
Burnco Langley Maintenance Dredging Project
Burnco Langley Maintenance Dredging Project -
Golden Ears Forcemain (GDEFM) Project
Golden Ears Forcemain Project -
Drainage Maintenance and Improvement Project - Alaksen National Wildlife Area
Alaksen National Wildlife Area -
Surrey Langley SkyTrain Project and Broadway Subway Project
Langley -
Maintenance Dredging, Fraser River, Small Craft Harbours
Kanaka Landing -
Maintenance Dredging, Fraser River, Small Craft Harbours
McMillan Island Harbour -
GCT Deltaport Expansion - Berth Four Project
Delta -
Roberts Bank Terminal 2 Project
Delta -
Westshore Terminals Berth 2 Mooring Dolphin Upgrades
Delta -
Maintenance Dredging, Fraser River, Small Craft Harbours
McIvors Landing -
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours)
Fraser Grain Terminal - Grain Export Facility - Project Permit No. 15-041-04 - Amendment (Condition 36 - Extended Hours) -
Maintenance Dredging, Fraser River, Small Craft Harbours
Whonnock Harbour -
Gibsons Small Craft Harbour Wharf Reconstruction
Gibsons Landing Small Craft Harbour -
BURNCO Aggregate Mine Project
Howe Sound -
Replacement of the Aldergrove Weather Radar
26600 8th Avenue, Langley, BC V0X 1A0 -
Woodfibre LNG Project
Howe Sound -
Telus Communications Inc. Radiocommunication Antenna Addition on Sechelt Band Lands No 2 Reserve, Sechelt BC
5411 Reservoir Road Sechelt BC, Sunshine Coast area on the Sechelt Band Lands No 2 Reserve -
Maintenance Dredging, Fraser River, Small Craft Harbours
Mission Harbour -
Winter Cove Boat Ramp Repair, Saturna Island
Gulf Islands National Park Reserve -
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities)
Fraser Grain Terminal - Grain Export Facility Amendment (Utilities) -
Nav Canada surveillance radar - Gulf Islands National Park Reserve, Saturna Island, BC
Saturna Island, BC - Gulf Islands National Park Reserve of Canada -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
Radio Tower Upgrades, North Pender Island
Gulf Islands National Park Reserve -
Freedom Mobile Installation on Radio Tower Site, North Pender Island
Gulf Islands National Park Reserve -
Porpoise Bay Harbour Boat Grid Removal
Porpoise Bay Harbour -
Canadian Coast Guard Clam Bay Pile Sites Navigation Aids Rebuild
The sites are located within Clam Bay between Thetis and Penelakut Islands on the East Coast of Southern Vancouver Island -
WildFire Risk Reduction Project - fuels managment at three sites in Gulf Islands National Park Reserve
Gulf Islands National Park Reserve -
Sumas IR6 Former Brick Plan Demolition and Remediation
Sumas First Nation Indian Reserve 6 -
GRT Holdings Ltd. Construction and Operation of Soil Treatment Facility -DUKE POINT
Nanaimo -
WCMRC Oil Spill Response Facility at Nanaimo Harbour
Nanaimo -
WCMRC Oil Spill Response Facility at Nanaimo Harbour
Nanaimo -
Nanaimo to Protection Island Submarine Cable Replacement Project
Nanaimo -
Exterior Landscape Redesign
60 Front Street Nanaimo -
SAY Community Centre
Skowkale No. 10 Reserve Land -
Campground Kiosk Install
Gulf Islands National Park Reserve -
Sidney Spit Buoy Upgrades
Gulf Islands National Park Reserve -
Establishing Shrubs in Protective Fenced Areas to Facilitate Forest Restoration on Sidney Island
Gulf Islands National Park Reserve -
Control of English Hawthorn on Sidney Island
Gulf Islands National Park Reserve -
Institute of Ocean Sciences Patricia Bay - Wharf Waterline Replacement
The Institute of Ocean Sciences is located in Sidney BC. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Institute of Ocean Sciences Patricia Bay - Wharf refurbishment
The Institute of Ocean Sciences is located in Sidney BC, on Vancouver Island. The facility is accessible via road access, as well as by water. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Institute of Ocean Sciences Patricia Bay - Miscellaneous Repairs 2020
The Institute of Ocean Sciences is located in Sidney BC. The facility is accessible via road access, as well as by water for vessel/barge access. The site lies on the eastern shore of the Saanich Inlet which runs out into Haro Strait. -
Blue Heron Aeropark Construction of Aircraft Hangars
Victoria International Airport YYJ -
Western Canadian Marine Response Corporation (WCMRC) Saanich Base
Victoria International Airport (YYJ) -
Titan Boats Construction of a Boat Manufacturing Facility
Victoria International Airport (YYJ) -
Temporary Installation of Remotely Piloted Aircraft System (RPAS) Detection Equipment
Victoria International Airport -
Modification of Existing Petroleum Storage Facility
Victoria International Airport -
Pauquachin Legacy Gathering Space
Cole Bay No. 3 Reserve (Pauquachin First Nation), North Saanich BC -
Seabird Island Cultural Education, Community Resource Centre and Long-House Project
Agassiz, British Columbia -
Site preparation for a subdivision on Popkum IR 2
Popkum IR2 -
Shxw'owhámél First Nation Outdoor Recreation Infrastructure Project
Shxw'owhámél First Nation -
Construction of a Boat Storage Facility at Colwood, CFB Esquimalt
CFB Esquimalt's Colwood property, located in the municipality of Colwood. -
Pedestrian Walkway Extension Lot B1
Esquimalt Graving Dock -
G Jetty and Jetty 11 Remediation in Esquimalt Harbour
Colwood, Esquimalt Harbour, located in the municipality of Colwood British Columbia -
EastEnd Dock Extension-Dock Floor/Wall Refurbishment
Esquimalt Graving Dock -
Colwood Fuel Oil Depot - Air Scrubber
Colwood Fuel Oil Depot, Rosebank Road, Colwood -
Victoria Coast Guard Base - Timber Fender Replacement
This project is located on the wharf at the Victoria Coast Guard Base, 25 Huron Street, Victoria, BC. The base is accessible via road access, as well as by water for vessel and barge access. -
Drydock Leak Repairs at HMC Dockyard, Canadian Forces Base Esquimalt
Her Majesty's Canadian Dockyard, Esquimalt Harbour -
Canadian Coast Guard Victoria Base Wharf Refurbishment
The Victoria Coast Guard Base in James Bay, Victoria, British Columbia. The base is situated 2km from downtown Victoria, and lies on the edge of the Victoria's inner harbour, which eventually funnels out into the Strait of Juan de Fuca. -
Canadian Coast Guard Victoria Search and Rescue Float
25 Huron Street, Victoria BC, V8V 4V9 -
Royal Roads University - Japanese Gardens Drainage Upgrades
Royal Roads University, 2005 Sooke Road, Colwood -
Royal Roads University Sustainability Initiative - Overhead Service Upgrades (Lower Campus)
Royal Roads University in Colwood -
Royal Roads University Recreation Centre Change Room Renovation Project
Royal Roads University campus, in the municipality of Colwood, British Columbia -
CREST - Microwave dish and VHF antenna - Mary Hill and Albert Head Road, Metchosin British Columbia
Albert Head Road, Metchosin -
Yale First Nation Recreation Centre
Stulkawhits No. 8 Reserve Land -
CREST - Microwave dish and VHF antenna - Mary Hill and Albert Head Road, Metchosin British Columbia
Mary Hill - 5300 William Head Road, Metchosin -
Canadian Forces Ammunition Depot (CFAD) Rocky Point Main Gates Recapitalization
CFAD Rocky Point, located in the municipality of Metchosin, BC. -
Connect Municipal Water Supply to Canadian Forces Ammunition Depot (CFAD) Rocky Point
Canadian Forces Ammunition Depot (CFAD) Rocky Point , Metchosin -
City of Powell River - Consolidated Waste Water Treatment Project
Powell River -
TOPAZ Submarine fibre-optic cable
Port Alberni -
Raven Underground Coal Mine Project
Buckley Bay -
N'Quatqua Multi-Use Facility Project
N'Quatqua Multi-Use Facility Project -
Canadian Coast Guard - Cape Lazo BC - Oceans Protection Plan - Marine Safety System Modernization Initiative
Cape Lazo -
Kwispaa LNG Project
10 kilometres northeast of Bamfield -
Kingsvale-Oliver Reinforcement Project
Kingsvale -
Lower Nicola Indian Band Community Solar Gardens
Lower Nicola Reserve Lands - Nicola Mameet No. 1, Joeyaska No. 2, and Zoht No. 4 -
Canadian Coast Guard Seymour Narrows Radar Site and Power Line
1km South from Browns Bay and 15km North of Campbell River, British Columbia