Schnitzer Fire Suppression Project - Design Amendment

Schnitzer Steel Canada Ltd., proposes to carry out physical activities related to the instalment of a fire suppression system, including four piers for the foundation of two fire monitor towers, until December 31, 2021. This would require an extension to the approved project permit (PER 18-196-01), which has an expiry date of April 30, 2021.

Due to materials shipment delays, the project would not be completed prior to April 30, 2021. There are no changes to construction activity or the scope of the work.


Latest update

Notice of Determination

Vancouver, B.C. –May 14, 2021– The Vancouver Fraser Port Authority has determined that the proposed Schnitzer Fire Suppression Project Amendment located at 12301 Musqueam Drive, Surrey, BC is not likely to cause significant adverse environmental effects..

Participate

Contacts

Project and Environmental Review
Vancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com


  • Location

    • Schnitzer Fire Suppression Project - Design Amendment (British Columbia)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    Completed
  • Start Date

    2021-04-13
  • Proponent

    Schnitzer Steels Canada Ltd.
  • Authorities

    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    80603