Breach Construction and Maintenance - Iona North Arm Jetty

Raincoast Conservation Foundation is proposing to construct a new linear breach (Breach No. 2) across the Iona Island North Arm Jetty and to conduct repair and maintenance work on the breach constructed in 2022 (Breach No. 1). Pursuant to their legislative duties, the Vancouver Fraser Port Authority is making its determination on both scopes of work, and Transport Canada is making its determination on the proposed construction of Breach No. 2. 

A previous public comment period was held from December 13, 2022, to January 11, 2023, for the construction scope. Given the new maintenance scope, and revised design for Breach No. 2, a new public comment period is now active.  

New construction work for Breach No. 2 consists of:  

  • Excavation of approximately 18,552 cubic metres of material to an elevation of -1.35 metres Geodetic Datum. Material would be used to form part of the breach. 
  • Installation of approximately 4,800 square metres of filter cloth. 
  • Placement of approximately 3,500 cubic metres of filter rock. 
  • Placement of approximately 4,267 cubic metres of riprap. 
  • Monitoring of the breach site for a minimum of two years post-completion. 

The second jetty breach would be approximately 120 meters long and 30 metres wide at the bottom and 55 metres wide at the top.  

Repair and maintenance work for Breach No. 1 consists of:  

  • Temporary removal of existing filter rock and riprap from the east and west slopes. Material will be set aside for re-use.  
  • Re-dress/grade the sand slopes.  
  • Installation of approximately 2,200 square metres of filter cloth.  
  • Placement of approximately 2,327 cubic metres of filter rock. 
  • Replacement of filter rock and riprap.  

Construction equipment and materials would be transported to the site by barge. Works are anticipated to take up to six weeks, within the Fisheries least risk window for the Project area (August 16 to February 28). Some works may be carried out outside of standard hours of work during favourable low tides.  

More


Latest update

Notice of Determination 

Richmond, B.C. – November 10, 2023 – The Vancouver Fraser Port Authority and Transport Canada have respectively determined that the proposed Breach Construction and Maintenance – Iona North Arm Jetty located at the Fraser Arm Estuary is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Breach Construction and Maintenance - Iona North Arm Jetty - November 10, 2023

Contacts

Project and Environmental Review
Vancouver Fraser Port Authority
100 The Pointe, 999 Canada Place
Vancouver, British Columbia V6C 3T4
Email: per@portvancouver.com


  • Location

    • Breach Construction and Maintenance - Iona North Arm Jetty (British Columbia)
  • Nature of Activity

    • Remediation and conservation
  • Assessment Status

    Completed
  • Start Date

    2023-08-16
  • Proponent

    Raincoast Conservation Foundation
  • Authorities

    • Transport Canada
    • Vancouver Fraser Port Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    85846
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: