Stormwater Outfall #21 Repair at the Catawampus Pond - Canadian Forces Base (CFB) Borden, Ontario

The Department of National Defence (DND) is proposing to repair the bottom portion of stormwater outfall #21 as well as a collapsed bank along the northeastern shore of Catawampus Pond in Canadian Forces Base Borden (CFB), Ontario. This project includes: removal of the damaged stormwater outflow pipe, installation of a new stormwater outflow pipe, placement of geotextile and riprap material, and stabilization of the collapsed bank.

It is anticipated that the repairs to the decrepit stormwater outfall will reduce the risk of erosion for areas immediately surrounding the stormwater outfall and reduce the sedimentation that enters Catawampus Pond.


Latest update

October 5, 2026 — The Department of National Defence has issued their Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
2 Notice of Determination - October 5, 2026
1 Public Comment Period on Intent to Make a Determination - November 1, 2023

Contacts

Darrell Shand
Department of National Defence
Darrell Shand, Base Environment Officer, Canadian Forces Base Borden
20 Seine Lane
Canadian Forces Base Borden ON L0M 1C0
Email: Darrell.Shand@forces.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Canadian Forces Base (CFB) Borden (Ontario)
  • Nature of activity

    • Water Management
  • Assessment status

    Completed
  • Start date

    2023-11-01
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment type

    Project on federal lands
  • Reference number

    86057

Nearby assessments

...within 200 kilometres
Date modified: