Hiawatha First Nation Water Treatment System Upgrades
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The proposed project aims to address critical health and safety risks of inadequately treated groundwater used by residents of Hiawatha First Nation. It involves the construction of 14 Point-of-Entry (POE) systems, connecting 11 homes to a planned water distribution system, and the construction of drilled wells for 10 homes. The project will take place on developed land and include minor clearing of grub and vegetation on site as needed. The project does not include works in water, however, the project is occurring throughout the Hiawatha First Nation reserve land and may include locations in close proximity to waterbodies.
The POE systems will utilize a combination of treatment processes involving sediment filters, air injection oxidation filters, granular activated carbon (GAC) filters, cartridge filters, and ion exchange resin to treat groundwater. Primary disinfection will be achieved using ultraviolet irradiation. The POE treatment systems will be housed in an outdoor wooden enclosure and will be built on member-owned land.
11 watermain service connections will be installed to provide access to potable water to residents of the community. These connections will consist of 25mm piping. All service connections will include a shut-off valve, a water meter, backflow preventor, and a pressure-reducing valve in an accessible location inside the residence. Pipe penetrations for service connections will be located below the frost line and hydraulically sealed prior to commissioning.
In addition, 10 groundwater wells will be drilled at residences affected by low yield and water quality issues with the existing wells. Existing wells will be decommissioned. The UR has indicated that this approach may have the potential to impact groundwater levels in the aquifer. Pump rates will be set so as to not exceed the maximum recharge rate of the well.
The existing infrastructure at all construction areas include overhead hydro lines on hydro poles, underground telephone lines along Hiawatha Line, Lakeshore Road, and Paudash Street. Septic fields on private property have also been identified and appropriate precaution/mitigation will be defined with direct communication with the utility owner prior to finalizing any design drawings.
Latest update
March 20, 2023 - Infrastructure Canada has determined the proposed Hiawatha First Nation Water Treatment System Upgrades (the Project) is not likely to cause significant adverse environmental effects.
This determination was based on a consideration of the following factors:
- Impacts on rights of Indigenous peoples;
- relevant potential environmental effects;
- comments received from the public; and
- technically and economically feasible mitigation measures.
Mitigation and monitoring measures taken into account for this determination included active and adaptive management measures that would be implemented for the protection of the local environment. Based on the consideration of these measures, Infrastructure Canada is satisfied that the carrying out of the Project is not likely to cause significant adverse environmental effects.
Therefore, Infrastructure Canada may carry out the Project, exercise any power, perform any duty or function, or provide financial assistance to enable the Project to be carried out in whole or in part. .
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination | - | March 20, 2023 |
Contacts
Infrastructure CanadaTaslema Khan, Indigenous Consultation and Environmental Assessment Officer
Telephone: 343-551-0416
Email: taslema.khan@infc.gc.ca
-
Location
- Project Area (Ontario)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2022-04-30 -
Proponent
Hiawatha First Nation -
Authorities
- Infrastructure Canada
-
Assessment Type
Project on federal lands -
Reference Number
84268
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Hiawatha First Nation Water Systems Upgrade
Hiawatha First Nation -
Paudash Street Reconstruction
Hiawatha -
Hiawatha First Nation Retirement Residences
Hiawatha First Nation -
Beaver Narrows Resort, 433 Beaver Rd, Pigeon Lake, Omemee - Dredge
Trent-Severn Waterway National Historic Site -
Alderville First Nation - Communal and POE Water Treatment Systems
Alderville First Nation Reserve -
2607 & 2609 Fire Route 14B, Chemong Lake, Selwyn - Dredge
Trent-Severn Waterway National Historic Site -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(2) 1674 Greenwood Lane West, Selwyn, Buckhorn Lake, ON -
Private Residence - Dredging and Shoreline Works Projects for four (4) Properties Bordering the Trent-Severn Waterway
Trent-Severn Waterway National Historic Site of Canada -
Maria Street Swing Bridge - Replacement, Trent-Severn Waterway, Maria Street, Peterborough, Ontario
Trent-Severn Waterway National Historic Site -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(3) 1378 Birchview Road, Douro-Dummer, Stoney Lake, ON -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(4) 36 Fire Route 121, Trent Lakes, Pigeon Lake, ON -
Port Severn Dam 'G' Little Chute Rehabilitation
Trent-Severn Waterway National Historic Site of Canada -
Trent Rapids Power Corporation (TRPC), Peterborough Utilities Inc (PUI) Hydro Intake Excavation
Trent-Severn Waterway National Historic Site -
Nassau Mills Dam Replacement, Trent-Severn Waterway
Trent-Severn Waterway National Historic Site of Canada -
Eastern Mainline Project
Cobourg -
The Proposal by Cameco Corporation for the Redevelopment of its Port Hope Conversion Facility (Vision 2010)
Port Hope -
Peterborough County - County Road 32, Hickey's Bridge Replacement
Trent-Severn Waterway National Historic Site of Canada -
Docks, Hasting Village Marina North and South Side
Hastings Village Marina -
Installation of Hastings Second Watermain Crossing of Trent River
Trent Hills -
County of Peterborough, Chemong Bridge Repair
Trent-Severn Waterway National Historic Site of Canada -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(1) Osprey Trail, Balsam Lake, ON -
Private Residence - Trent-Severn Waterway - 96 Hewall Trail, Katchewanooka Lake - Dredge and Launch Ramp
Trent-Severn Waterway National Historic Site of Canada -
1965 Pinehurst Ave., Selwyn, Upper Chemong Lake - Wet Slip Infill
Trent-Severn Waterway National Historic Site -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(5) 344 Indian Point Road, CKL, Balsam Lake, ON -
Trent-Severn Waterway -1247 Emerald Isle Road, Buckhorn Lake - Dredge and Aquatic Vegetation Removal
Trent-Severn Waterway National Historic Site -
Warkworth Institution - Wastewater Treatment System- Pipe Cleaning and Replacement
Warkworth Institution -
New Delivery Centre - Port Perry ON
6 Easy Street, Port Perry -
Curve Lake First Nation - Water Treatment System
Curve Lake First Nation -
Curve Lake Catch Basin and Roads Stormwater Improvements
Curve Lake Roads Stormwater Improvements -
Campbellford Bridge/Trent River Crossing
Detailed Impact Assessment, Trent-Severn Waterway National Historic Site -
New Fibre Installation
CURVE LAKE FIRST NATION INDIAN RESERVE NO. 35 -
TSW Water Soldier Mechanical Control Trial 2023
Trent-Severn Waterway National Historic Site of Canada -
Nappan Island Bridge Replacement, Municipality of Trent Hills
Municipality of Trent Hills -
Ice Chute Rehabilitation at Healey Falls Generating Station, Trent River, Campbellford, ON
Trent River, Ontario -
Healey Falls Ontario Power Generation Station Ice Run (chute) Concrete Repair
Trent-Severn Waterway National Historic Site of Canada -
Private Residence - Dredging and Shoreline Works Projects for three (3) Properties Bordering the Trent Severn Waterway
Trent-Severn Waterway National Historic Site of Canada -
Burleigh Falls Dam Replacement, Trent-Severn Waterway
Trent-Severn Waterway National Historic Site -
Ontario Waterways- TSW- Pretty Channel Road Upgrade
Trent-Severn Waterway National Historic Site of Canada -
City of Kawartha Lakes - Repair of Existing Stormwater Outlet
Trent-Severn Waterway National Historic Site of Canada -
City of Kawartha Lakes, Shoreline Protection, McDonnel Park, Lindsey, Ontario
Trent-Severn Waterway National Historic Site of Canada -
Bobcaygeon Beach Park Redevelopment, Trent Severn Waterway, Bobcaygeon
Bobcaygeon -
840 Fife's Bay, Marina Lane, Chemong Lake (Private Landowner) - Shoreline Stabilization, Boat Launch, Dredge
Trent-Severn Waterway National Historic Site of Canada -
TSW Water Soldier Herbicide Control 2023
Trent-Severn Waterway National Historic Site -
City of Kawartha Lakes Thurstonia boat-launch/pier stabilization
Trent-Severn Waterway National Historic Site of Canada -
Snug Harbour Marina Upgrade, Sturgeon Lake, Ontario
Trent-Severn Waterway National Historic Site -
Refurbishment and Continued Operation of the Darlington Nuclear Generating Station
Darlington -
Trenton Lock 1, Trent River - Dredge
Trent-Severn Waterway National Historic Site -
Trans Northern Pipelines Inc. (TNPI) Trent River Crossing Repair
Trent-Severn Waterway National Historic Site -
Vegetation Removal - 8 Wing Trenton
8 Wing Trenton -
Remediate Boxcar Road Culvert at 8 Wing Trenton
Boxcar Road, 8 Wing Trenton Ontario -
Air Traffic Control Tower Vegetation Removal - 8 Wing Trenton
8 Wing Trenton -
Eastern Mainline Project
Bowmanville -
Marmora Clean Energy Hub Project
Municipality of Marmora and Lake, in Hastings County -
Culvert Replacement- Taxiway Golf, 8 Wing Trenton
8 Wing Trenton -
Reconfigure South Side Entrance at 8 Wing Trenton, Trenton Ontario
Anson Ave, 8 Wing Trenton from Old Highway 2, Quinte West to Yukon St, 8 Wing Trenton -
Strategic Tanker Transport Capability Project Support Infrastructure, Airfield Modifications Phase 1 - 8 Wing Trenton
8 Wing Trenton -
Design and Construct CJIRU - Geotechnical and Topographical Study at the 8 Wing Trenton Airfield
8 Wing/Canadian Forces Base Trenton -
Outfall Pipe, Lake Scugog, Scugog Township
Scugog Township -
Habitat Improvements on Lake Scugog - Components of the Fisheries Offset Plan for the Lake Scugog Enhancement Project (LSEP)
Trent-Severn Waterway National Historic Site of Canada -
Lake Scugog Enhancement Project
Trent-Severn Waterway National Historic Site of Canada -
Port of Oshawa - Extension of Berm Adjacent to Second Marsh
Oshawa -
Port of Oshawa Salt Terminal
Oshawa -
Port of Oshawa Truck Parking Lot
Port of Oshawa -
Port of Oshawa - Warehouse Upgrade
1050 Farewell Street, Oshawa, Ontario -
Port of Oshawa - East Wharf Storm Water Management and Surfacing
Oshawa -
Grain terminal expansion
Port of Oshawa -
Port of Oshawa East Wharf Extension
Port of Oshawa -
Port of Oshawa - Relocation of Floating Dock
Oshawa, Ontario -
Port of Oshawa Shore Power and Security Upgrades
Oshawa -
Port of Oshawa Camera Installation
Port of Oshawa -
Removal of two underground concrete tanks
Oshawa -
Port of Oshawa West Wharf Fencing project - 1621 Simcoe Street South, Oshawa, Ontario
Port of Oshawa - 1621 Simcoe Street South, Oshawa, Ontario -
Port of Oshawa Maintenance Dredging
Oshawa -
Urgent Fuel Storage Tank Code Compliance
494 Dundas St E, Belleville, ON -
Construction and Operation of Building A-320, at CFB Borden
21c Spitfire Lane, Canadian Forces Base Borden -
Tree Removal, Phase 2 - Canadian Forces Detachment Mountain View
Canadian Forces Detachment Mountain View -
Private Landowner Shoreline stabilization, Trent-Severn Waterway, Shoreline Works Permit 190274
Trent-Severn Waterway National Historic Site -
Whitby West Pier Repairs 2021
Whitby Small Craft Harbour -
Whitby Harbour Sediment Remediation, Whitby, Ontario
Whitby Harbour -
Whitby Harbour Maintenance Dredging 2022
Whitby Harbour -
Ontario Waterways-Trent-Severn Waterway Kirkfield Shops Expansion
Trent-Severn Waterway National Historic Site -
TC - Demo Project
3625 Brougham Rd (PIN614698-2) -
TC - Demo Project
3730 Brock Rd, Pickering (PIN614205) -
Demolition of identified vacant structures located at Pickering Lands Site
PIN 614205 - 3730 Brock Road, Pickering -
TCG National Storage Facility, Spring St., Pickering Ontario
Pickering -
Wheelhouse Marine Supply, Brougham, Ontario
Brougham, Ontario -
Agricultural Drainage System Expansion, Pickering Township Concession 7, Lot 19-22
City of Pickering -
Mohawks of the Bay of Quinte Remedial Action Plan
Parcel 5A/C -
Mohawks of the Bay of Quinte Remedial Action Plan
Parcel 12 -
Mohawks of the Bay of Quinte Remedial Action Plan
Parcel 10 -
Mohawks of the Bay of Quinte Remedial Action Plan
Parcel 1 -
Eastern Mainline Project
Belleville -
Kenhtè:ke Language and Cultural Centre (KLCC)
Shannonville -
Site Office Exterior Columns Review and Repair
5070 Sideline 22, Pickering, Ontario, L1Y 1A3 -
Fisheries Habitat Construction at Big Island Marsh
Trent-Severn Waterway National Historic Site -
Trent-Severn Waterway Durham Regional Road 50 Bridge
Trent-Severn Waterway National Historic Site -
Dockside Dredge Trent-Severn In-Water and Shoreline Works Permit 190113
Trent-Severn Waterway National Historic Site -
Municipal Water Infrastructure, City of Pickering Zone 4 and 5
City of Pickering -
Beaverton Small Craft Harbour Platform Removal
Beaverton, ON -
2022 Aquatic Restoration Program: Stream Rehabilitation and Removal of Instream Barriers in the West Duffins Creek Watershed in Rouge National Urban Park
Rouge National Urban Park -
Wetland Restoration Program 2024-2025 and Crossing Removal
Rouge National Urban Park -
Pefferlaw Small Craft Harbour Tree & Brush Removal
Pefferlaw -
Wetland Restoration Program 2023-2024
Rouge National Urban Park -
PIN 614406 (230 Concession 7), Pickering - Glen Cedars Golf Club - renewed Commercial Lease for a golf course
Pickering -
Reconstruction of a Section of York Road and Rehabilitation of the Mud Creek Bridge
Reconstruction of a Section of York Road and Rehabilitation of the Mud Creek Bridge -
New Fibre Installation (YTN Telecom Network Inc.)
Rouge National Urban Park -
Beach Revitalization and New Boardwalk Trail
Detailed Impact Assessment, Rouge National Urban Park -
Mohawks of the Bay of Quinte First Nation - Watermain Extension Phase III
Mohawks of the Bay of Quinte First Nation, Ontario -
House Decommissioning 2024
Rouge National Urban Park -
Glen Rouge Campground Revitalization
Rouge National Urban Park -
Rouge National Urban Park Study
Rouge National Urban Park and adjacent lands -
Septic System Replacement - 2023
Rouge National Urban Park -
Septic System Replacements
Rouge National Urban Park -
MBQ - Phase IV Watermain Extension
Mohawks of the Bay of Quinte First Nation -
Keswick Post Office Site Remediation
Keswick -
The Mohawks of the Bay of Quinte Community Wellbeing Centre
Tyendinaga Mohawk Territory -
Baldwin East Aerodrome Project
Town of Georgina -
Quinte Mohawk School - Asphalt Play Area rehabilitation
Mohawks of the Bay of Quinte First Nation -
Boyles Cemetery to Bob Hunter Trail Construction
Rouge National Urban Park -
Deer Exclusion Fencing
Rouge National Urban Park -
Beare Wetlands Berm Repair
Rouge National Urban Park -
Rouge Gateway Visitor Learning and Community Centre
Rouge National Urban Park -
Pre-Fabricated Office Installation
Rouge National Urban Park -
Septic System Replacement - 2024
Rouge National Urban Park -
Tile Drainage System
Rouge National Urban Park -
Trailheads and Connections
Rouge National Urban Park -
Dredging Projects for Six (6) Properties Bordering the Trent-Severn Waterway: (1), Balsam Lake, (2) Buckhorn Lake, (3) Stoney Lake, (4) Pigeon Lake, (5) Balsam Lake, and (6) Sparrow Lake
(6) 3500 Lauderdale Point Cres, Severn, Sparrow Lake, O -
Trans Northern Pipeline Integrity Digs
Rouge National Urban Park -
Rouge National Urban Park Cistern Decommissioning
Rouge National Urban Park -
Beaver Creek Institution - New/Existing Pump Station Upgrade
Beaver Creek -
Chippewas of Georgina Island First Nation - South/East Region Watermain Extension
Georgina Island First Nation -
Chippewas of Georgina Island - Rehabilitation of Watermains
Georgina Island -
Georgina Island Fixed Link Project
Lake Simcoe between Georgina Island to Town of Georgina in Ontario -
Conlins Road Stormwater Management Facility Outfall Restoration
Rouge National Urban Park -
Stream Restoration of Morningside Creek Downstream of Casebridge Outfall
Rouge National Urban Park -
Barn Foundation Rehabilitation
Rouge National Urban Park -
Mohawks of the Bay of Quinte - Elder Care Home
Tyendinaga Mohawk Territory -
Mohawks of the Bay of Quinte - Elder and Disabled Care Home Construction
Mohawks of the Bay of Quinte First Nation -
Chippewas of Georgina Island First Nation - Early Childhood Learning Centre
Georgina Island -
Watermain Extension on Old Highway 2, Bells Road and North Street
Tyendinaga Mohawk Territory -
Trent-Severn Waterway, Esson Lake Earth Dam Rehabilitation
Trent-Severn Waterway National Historic Site of Canada -
Mohawks of the Bay of Quinte - Lot Servicing for future houses
Mohawks of the Bay of Quinte -
Generator Replacement
200 Town Centre Court, Scarborough, ON M1P 4X8 -
Eastern Mainline Project
Markham -
Bluffer's Park Central Maintenance - Toronto, Ontario
Bluffer's Park -
BLUFFER'S PARK SOUTHWEST HEADLAND AND BEACH MAJOR MAINTENANCE
Bluffer's Park, Toronto, Ontario -
Bradford Bypass Project
East Limits at Highway 404 -
Septic System Installation and Washroom Construction
Rouge National Urban Park -
Chippewas of Rama - Landfill Decommissioning/Transfer Station Construction
Chippewas of Rama -
Shilling Subdivision Chippewas of Rama First Nation
Chippewas of Rama First Nation -
Ontario Line Project
Ontario Science Centre -
Potential Regional Assessment of the Toronto-Danforth Area
Toronto-Danforth -
Ontario Line
Toronto -
Septic Tank Replacement at Newburgh Post Office
31 Homer Street -
Napanee Generating Station Project
13 kilometres south of Napanee -
Exterior Metal Refurbishing
4905 Dufferin Street, Toronto -
Asphalt Removal and Replacement, 4905 Dufferin Street, Toronto, Ontario
4905 Dufferin Street, Toronto, Ontario -
Refinish Metal Cladding Roof and Exterior Transformer Vault
4905 Dufferin Street, Toronto, Ontario -
Chiller and Cooling Tower Replacement
4905 Dufferin Street, Toronto, Ontario -
Re-leveling of Interlock Stone Pavers
4905 Dufferin Street, Toronto, Ontario -
Ontario Place Spa Complex and Ontario Place Underground Parking Garage Project
Toronto -
Couchiching Lock 42 and Bridge 56 Rehabilitation
Trent-Severn Waterway National Historic Site -
Removal of In Water Structures - Prince Edward Point National Wildlife Area
Prince Edward Point National Wildlife Area -
Demolition of Structures and Removal of Debris - Prince Edward Point National Wildlife Area
Prince Edward Point National Wildlife Area -
Highway 413 Project
Highway 400 -
Bradford Bypass Project
West Limits at Highway 400 -
Ontario Line
Toronto -
Private Landowner Shoreline stabilization, Shore wall, Trent-Severn Waterway, Shoreline Works Permit 200127
Trent-Severn Waterway National Historic Site -
Private Landowner Shoreline stabilization, Shore wall, Trent-Severn Waterway, Shoreline Works Permit 200013
Trent-Severn Waterway National Historic Site -
Bath Institution - Sewer Outfall for Loyalist Township
Bath Institution -
Ontario Line Project
Exhibition/Ontario Place -
Private Landowner Shoreline stabilization, Trent-Severn Waterway, Shoreline Works Permit 210241, Sparrow Lake, ON
Trent-Severn Waterway National Historic Site -
Bath Institution - New 96 Bed Living Unit
Bath -
Resurfacing and Paving Exterior Roadways at Bath/Millhaven Institutions
Bath/Millhaven Institutions -
Septic Tank Replacement at Arden Post Office
1004 Bridge St, Arden, Ontario, K0H1B0 -
Beaver Creek Institution - Parking expansion
Beaver Creek Institution -
Replace Selected Exterior Hardscape, Retaining Wall and Fence
48 Owen Street, Barrie, Ontario -
Long Point (Amherst Island) Crib Repairs
Long Point (Amherst Island) Small Craft Harbour -
Fort Mississauga Shoreline Stabilization
Fort Mississauga National Historic Site of Canada -
Hertz Fuel Dispensing System
Toronto Pearson International Airport (GTAA) -
Geotechnical Investigation for a Future Potential Airport Connection
Geotechnical Investigation -
Rehabilitate Employee Parking Lots
Toronto Pearson International Airport (GTAA) -
Installation of a Hydrogen Fueling Station
Hydrogen Hub Station -
Junior Commissariat Officers' Quarters - Recapitalization Project
Niagara National Historic Sites -
In Situ Vertical Thermal Response Test
Toronto Pearson International Airport (GTAA) -
Installation of Potassium Acetate Tanks
Toronto Pearson International Airport (GTAA) -
Airport Tennis Facility
Airport Tennis Club -
Non-Passenger Screening for Vehicles - North
Toronto Pearson International Airport (GTAA) -
Proposed Hotel and Event Facility Centre Development
Toronto Pearson International Airport (GTAA) -
Nav Canada Toronto Transmitter Back-up Towers Replacement
Toronto Pearson International Airport (GTAA) -
Shell Business Aviation Tank Farm
Shell Business Aviation Tank Farm -
Etobicoke Creek Outfall Restoration
Etobicoke Creek Outfall -
Spring Creek Sediment Clean Out
Toronto Pearson International Airport (GTAA) -
Collins Bay Institution/City of Kingston Sewer Project
Collins Bay Institution -
Region of Peel East to West Wastewater Diversion Project
Toronto Pearson International Airport -
FedEx Facility Parking Lot Expansion
FedEx -
FESTI - Aircraft Rescue Fire Fighting Props Control System Replacement
FESTI -
FEDEX - Asphalt Pad Extension
FedEx Facility 6895 Bramelea Rd, Toronto, L5S 1E2. -
Essential Radar Telecom Modernization Toronto Fiber Installation
Nav Canada Fibre Location -
CAE Flight Simulator Expansion
CAE Flight Simulator -
Retaining Wall Dixie Road and Courtney Park Drive
Toronto Pearson International Airport (GTAA) -
Nav Canada Pearson Localizer 23 Remote Unit
Toronto Pearson International Airport (GTAA) -
Collins Bay Institution - Demolition of 2 Silos and Building FF27
Collins Bay Institution -
Canadian Coast Guard Port Weller Search and Rescue Station Dock Replacement
St. Catharines -
Port Weller Water Level Gauge Station Shoreline Reinforcement Project
St. Catharines -
Full Depth Parking Lot Reconstruction / Repaving at Building P-148
Canadian Forces Base Borden -
Installation of Beaver Baffles in Range and Training Area B2, at Canadian Forces Base Borden
Canadian Forces Base Borden -
Standing Offer for General Construction at CFB Borden, Ontario
Canadian Forces Base Borden -
Grey and Simcoe Foresters Storage Compound Building, Borden - Ontario
Canadian Forces Base Borden -
Construction and Operation of a Transition Centre at CFB Borden, Ontario
Canadian Forces Base Borden -
Pad A Demolition at Building T-126 at CFB Borden
Canadian Forces Base Borden -
Construction of a Winter Maintenance Yard, Canadian Forces Base (CFB) Borden
CFB Borden (the Site). The Site is located approximately 3 km southwest of Angus, ON. -
Borden Satellite Hub
Canadian Forces Base (CFB) Borden -
Stormwater Outfall #21 Repair at the Catawampus Pond - Canadian Forces Base (CFB) Borden, Ontario
Canadian Forces Base (CFB) Borden -
High Speed Driver Training Track Improvements - Canadian Forces Base (CFB) Borden
Canadian Forces Base (CFB) Borden -
Construction of 400 Squadron Transition Infrastructure (H-18), CFB Borden
Canadian Forces Base Borden -
Kingston (Portsmouth Olympic) Harbour - Outer Breakwater Pile Repair
Kingston (Portsmouth Olympic) Harbour -
New RV Compound at CFB Borden
Canadian Forces Base Borden -
Area E2 Road Construction - Canadian Forces Base (CFB) Borden
Canadian Forces Base (CFB) Borden -
Construction and Operation of a new Gas Hut - Canadian Forces Base Borden
Canadian Forces Base Borden -
Construction of Eight Apartment Buildings - Canadian Forces Base Borden
Canadian Forces Base Borden -
Soil Remediation at CFB Borden Firefighter Training Area
CFB Borden Firefighter Training Area which is approximately 3.6 km southeast of Lisle, Ontario -
Dalhousie Yacht Club - Travel Lift
Dalhousie Yacht Club, Port Dalhousie, ON -
Sharbot Lake Harbour Repairs 2021
Sharbot Lake -
Septic (Holding Tank) Installation at Port Severn ON Post Office
3280 Port Severn Road South, Port Severn, Ontario -
CFB Kingston Energy Conservation Project
Kingston Armoury, 100 Montreal St. Kingston -
Storm Sewer, Kingston, Ontario
Kingston -
Normandy Hall (FF10) Foundation Repairs, Fort Frontenac
Fort Frontenac, 346 Ontario Street -
Fort Frontenac Storm Drainage and Parking Lot Reconstruction Project
Fort Frontenac, in Kingston -
Upgrades at Richardson Beach, City of Kingston, Lake Ontario
Richardson Beach, City of Kingston, Lake Ontario -
Kingston Inner Harbour (KIH) Sediment Management Project
Kingston -
LaSalle Causeway Bascule Bridge Rehabilitation
LaSalle Causeway Kingston, Ontario -
LaSalle Causeway Concrete Repairs
LaSalle Causeway Kingston, Ontario -
LaSalle Causeway Bascule Bridge Rehabilitation
Lasalle Causeway, Kingston, Ontario -
Security Enhancements - Royal Military College of Canada
Royal Military College of Canada -
Royal Military College East Shoreline Stabilization
Royal Military College, Kingston Ontario -
Sanitary Lift Station Upgrades at Royal Military College of Canada
Royal Military College of Canada, 20 General Crerar Crescent, Kingston -
HR24 Sanitary Lift Station Upgrades at Canadian Forces Base Kingston
HR24 Sanitary Lift Station at 7 Fort Henry Drive, Kingston -
Canadian Forces Base Kingston McNaughton Building A21 Solar Panel Demolition
Canadian Forces Base Kingston. It is located directly west of the Central Heating Plant, building MA21, located at 15 Craftsman Blvd. -
Installation of a Two-Stage Heat Pump System - Canadian Forces Base (CFB) Kingston
Canadian Forces Base (CFB) Kingston -
Patio Stone Work at Building MB53 - Canadian Forces Base (CFB) Kingston
Canadian Forces Base (CFB) Kingston -
Roadwork - Rehabilitate Apprentice Street, Craftsman Boulevard, Sadie Avenue and Navy Way - Canadian Forces Base (CFB) Kingston
Canadian Forces Base (CFB) Kingston -
Replace Watermain Pipe at Fort Frontenac - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Combined Joint Intelligence Modernization (CJIM) Proposed New Facility - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Canadian Forces Housing Agency New 12-plex Apartments- Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Site Flooding Correction at Central Heating Plant- Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Energy Performance Contract (EPC) McNaughton Feeder Replacement- Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Rehabilitation of Steam Chambers- Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Canadian Forces Housing Agency New 6-plex Apartments - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
R30 Fort Frederick Tower Masonry Repairs - Phase 2 - Royal Military College of Canada
Royal Military College of Canada -
Range Improvements - Canadian Forces Base (CFB) Kingston
Canadian Forces Base (CFB) Kingston -
Martello Tower Electrical Repair - Royal Military College of Canada
Royal Military College of Canada -
Officer's Mess, Heritage Envelope Repairs - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Repair Storm Water Line - Royal Military College of Canada
Royal Military College of Canada -
Installation of New Maintenance Shed- Canadian Forces Base (CFB) Kingston Yacht Club
Canadian Forces Base (CFB) Kingston Yacht Club -
Re-Pave Assoro Crescent and Sicily Drive - Canadian Forces Base (CFB) Kingston
CFB Kingston -
Royal Military College Museum - Design Phase
Royal Military College, Kingston -
Heating, Ventilation, and Air Conditioning (HVAC) and Roof Refit - CFB Kingston
CFB Kingston, 6 Red Patch Avenue, Kingston -
Watermain and Storm Sewer Repair - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Waterline Backflow Installation- Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Backwater Valve Installation - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Building Construction - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Institutions of Bath and Millhaven: Sanitary Sewer Upgrades
Bath -
Crow Lake Harbour Repairs 2021
Crow Lake -
Dock Removal - Georgian Bay Islands National Park
Georgian Bay Islands National Park -
Ontario Waterways, Six Mile Lake Dams Rehabilitation
Trent-Severn Waterway National Historic Site of Canada -
Kingston Mills Outer Weir Masonry Rehabilitation
Rideau Canal National Historic Site of Canada -
Soil Remediation at Jannacks Narrows Minor Shore Light, Bala Park Island, Ontario
Jannacks Narrows Minor Shore Light, Ontario -
Thorold ready-mix concrete plant
1134 Old Thoroldstone Road, Thorold -
Safety Repairs on Canal Trail
City of Thorold -
CFB Kingston Energy Conservation Project
Canadian Forces Base Kingston -
White's Portage Dam Replacement, Trent-Severn Waterway
Trent-Severn Waterway National Historic Site -
Rebuild Raptor Enclosure Structure - Wye Marsh National Wildlife Area
Wye Marsh National Wildlife Area -
Base-Wide Tree Removal at Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Rock Crushing and Tub Grinding - Canadian Forces Base Kingston
Canadian Forces Base Kingston -
Rogers Cell Tower Installation CFB Kingston
Fort Henry Heights, CFB Kingston, Kingston -
Bala North Dam Waterpower, Lake Muskoka, Township of Muskoka Lakes
Bala -
Highway 413 Project
Highway 401/407 -
Honey Harbour Parking Lot
Georgian Bay Islands National Park of Canada -
Eastern Mainline Project
Kingston -
Parking Lot Expansion and Re-pavement at Postal Service (PS) Georgetown, ON
112 Guelph St, Georgetown, ON, L7G 3Z0 -
Joyceville Institution - Fire Protection System Upgrade
Joyceville Institution -
Placement of Permanent Fill below the Upper Control Water Elevation, Five Properties Bordering the Rideau Canal National Historic Site: 845 Artemis Circle, 4563 Stairstep Lane, 4065 Hiawatha Lane, 5496 Old Mill Way, and 7407 Rideau Valley Drive South
Rideau Canal National Historic Site of Canada -
Joyceville Institution Cattle and Goat Barn Construction
Joyceville Institution -
Tobey Dock Reconstruction
Georgian Bay Islands National Park -
Wahta Mohawks - Waste Transfer Station and Landfill Closure
Wahta Mohawks -
Placement of Permanent Fill below the Upper Control Water Elevation, Five Properties Bordering the Rideau Canal National Historic Site: 845 Artemis Circle, 4563 Stairstep Lane, 4065 Hiawatha Lane, 5496 Old Mill Way, and 7407 Rideau Valley Drive South
Rideau Canal National Historic Site of Canada -
Joyceville Institution - Low level intake design
Joyceville Institution -
Safety Repairs on Canal Trail
City of Thorold -
Wahta Mohawk Housing Subdivision Project
Wahta Mohawk -
Lower Brewers Swing Bridge Replacement
Rideau Canal National Historic Site -
Impeed the Reed
Georgian Bay Islands National Park -
YMCA Camp Queen Elizabeth Cabin Improvement Project
Georgian Bay Islands National Park -
MTO Culvert Replacement, Highway 15
Rideau Canal National Historic Site -
Erin Wastewater Treatment Plant Project
Town of Erin -
Parking Lot Asphalt Replacement at Toronto West (Milton) Detachment
Milton -
Various Projects in Wetlands; Six Properties Bordering the Rideau Canal National Historic Site: 39 Silo Road, 2673 River Road, 1067 Rideau Ferry Road, 802 McVeety's Island, 103 Boat Launch Road, and 449 Indian Lake Road
Rideau Canal National Historic Site of Canada -
Milton Logistics Hub Project
Milton -
South Frontenac Township Culvert Rehabilitation, Stafford Lane
Rideau Canal National Historic Site of Canada -
Town of Shelburne Long-Term Well Project
Shelburne -
Burlington Canal Pier safety improvements
Burlington Canal Piers -
Construction of the Former Welland Canal Crossing
Dain City -
Burlington Lift Bridge - Storage Tank Upgrades
Burlington Lift Bridge 1157 Beach Boulevard Hamilton, Ontario -
Burlington Lift Bridge - Security Gate & Fence Installation, Parking Lot Asphalt Paving and New Meeting Room
Burlington Lift Bridge 1157 Beach Boulevard Hamilton, Ontario -
Burlington Light Tower Relocation
Hamilton, Ontario -
Burlington Lift Bridge Deck Replacement
1157 Beach Blvd, Hamilton, ON L8H 6Z9 -
Aubrey Island Navigational Aid Sight Line Restoration (Coast Guard)
Thousand Island National Park of Canada -
Penstock #4 Replacement, Jones Falls Generating Station, Rideau Canal
Rideau Canal National Historic Site -
Boat Slip Sediment Remediation Project
Hamilton Harbour -
Various Projects in Wetlands; Six Properties Bordering the Rideau Canal National Historic Site: 39 Silo Road, 2673 River Road, 1067 Rideau Ferry Road, 802 McVeety's Island, 103 Boat Launch Road, and 449 Indian Lake Road
Rideau Canal National Historic Site of Canada -
Reid Road Reservoir Quarry Project
Milton -
Dain City Multi-use Trail Improvements
Port Colborne, Ontario -
Randle Reef Sediment Remediation Project
Hamilton Harbour -
Fire Pump and Generator Replacement at John Weir Foote Armoury
John Weir Foote Armoury, 200 James Street North in Hamilton -
Gordon Island Shoreline Stabilization
Thousand Islands National Park -
Application of RipRap for Shoreline Stabilization - Tower Island, Big Rideau Lake, ON
Rideau Canal National Historic Site of Canada -
Upgrading of Roadways in Beausoleil First Nation
Beausoleil First Nation Reserve -
Beausoleil First Nation - Stormwater System Upgrade and Existing Drainage Rehabilitation
Beausoleil First Nation Reserve -
Algonquins of Pikwakanagan - Water Supply and Treatment System
Algonquins of Pikwakanagan First Nation, Ontario -
Landon's Bay Temporary Parking
Thousand Islands National Park of Canada -
Construction of the Algonquins of Pikwakanagan Communal Treatment System
Construction of the Algonquins of Pikwakanagan Communal Treatment System -
Child & Family Well-Being Centre
Pikwakanagan -
New Fibre Installation
Thousand Islands National Park of Canada -
Dock Modification and Boathouse Repair - 189 Pine Ridge Lane, Adam's Lake, Rideau Canal National Historic Site
Rideau Canal National Historic Site -
Drummond Street Bridge Rehabilitation, Perth ON
Rideau Canal National Historic Site of Canada -
Various Projects in Wetlands; Six Properties Bordering the Rideau Canal National Historic Site: 39 Silo Road, 2673 River Road, 1067 Rideau Ferry Road, 802 McVeety's Island, 103 Boat Launch Road, and 449 Indian Lake Road
Rideau Canal National Historic Site of Canada -
Various Projects in Wetlands; Six Properties Bordering the Rideau Canal National Historic Site: 39 Silo Road, 2673 River Road, 1067 Rideau Ferry Road, 802 McVeety's Island, 103 Boat Launch Road, and 449 Indian Lake Road
Rideau Canal National Historic Site of Canada -
Rideau Ferry Bridge Rehabilitation, County of Lanark
County of Lanark -
Implementation of the Deer Management Plan on Hill Island and Other Properties Affected by Hyperabundant Deer Populations
Thousand Islands National Park of Canada -
Hill Island Quarry Restoration
Thousand Islands National Park of Canada -
Thornbury Harbour Fuel System Removal and Replacement - 2021
Thornbury Harbour -
Thornbury West Pier Deck Repairs - 2021
Thornbury -
New Fibre Installation - Mississippi Lake
Project site 1: Mississippi Lake -
Port Maitland Dock and Launch Ramp Repair
Port Maitland Small Craft Harbour -
White Lake Partial Wharf Removal
White Lake -
Vegetation Management and Routine Maintenance along Utility Lines Right-of-Ways within Thousand Islands National Park of Canada
Thousand Islands National Park -
Multi-site Dock Replacements, Thousand Islands National Park
Thousand Islands National Park of Canada -
Artificial Turtle Nest Site Creation
Thousand Islands National Park -
Town of Smiths Falls Multi-Use Trail Widening
Rideau Canal National Historic Site -
VIA Rail Slope Stabilization - Old Sly's Lockstation, 2024-25
Rideau Canal National Historic Site of Canada -
Waterloo Airport Runway Project
Region of Waterloo International Airport, Runway 14-32 -
Wasauksing First Nation Peatland Wastewater System Design & Construction
Wasauksing First Nation Peatland Wastewater System Design & Construction -
Canadian Coast Guard Parry Sound Base Helipad Area Repair Project
Parry Sound -
Wasauksing First Nation - Lot Servicing for future houses
Wasauksing First Nation -
Meaford Harbour - Dock Expansion Project
Meaford -
Meaford Harbour Fuel Tank System Installation - 2021
Meaford -
Wasauksing First Nation - Supply Island Lighthouse Demolition and Remediation
Supply Island Lighthouse -
Six Nations of the Grand River Wastewater Lagoons Forcemain Upgrade Construction
Six Nations reserve No. 40 -
New Fibre Installation
Six Nations of the Grand River -
Breaching Range Development in Areas 7 and 8, Range and Training Area, Garrison Petawawa
Range and Training Area, Garrison Petawawa (Area 8) -
Septic Tank Replacement at Pakenham ON Post Office
155 MacFarlane St, Pakenham, ON, K0A2X0 -
Six Nations of the Grand River Territory - Bridge #7 Replacement
Six Nations of the Grand River -
Lighting and Pathway Upgrades
Woodside National Historic Site -
Breaching Range Development in Areas 7 and 8, Range and Training Area, Garrison Petawawa
Range and Training Area, Garrison Petawawa (Area 7)