BC Hydro Field Energy Storage Facility Temporary Generator

BC Hydro will be installing a temporary diesel backup generator and fuel tank for up to 2 years on the site of the Energy Storage Facility (ESF) backup system for the Village of Field. The backup generator is required after a catastrophic fire destroyed the ESF in February of 2021. Temporary office (on trailer, no foundation required) will be needed on-site, as existing building is fully destroyed.


Latest update

May 7 2026 – Parks Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Contacts

Yoho National Park
P.O. Box 99
Field, British Columbia V0A 1G0
Telephone: 250-343-6783
Email: noelle.summers@pc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Yoko National Park (British Columbia)
  • Nature of Activity

    • Other, not otherwise specified
  • Assessment Status

    Completed
  • Start Date

    2021-09-02
  • Proponent

    BC Hydro
  • Authorities

    • Parks Canada Agency
  • Assessment Type

    Project on federal lands
  • Reference Number

    82964