Water Main Replacement at the NRC - Montreal Road South Campus

The scope of the project includes water mains replaced by either open-cut excavation, Cure-In Place-Pipe (CIPP), or a hybrid approach using both methods on NRC Montreal Road South Campus .

The project consists of linear excavation of 2100 linear meter. The project includes tree removal. Trees are anticipated to be removed for this project and will be compensated as part of the project. The project work would take approximately five months from start to completion (May 2026 to November 2026).


Latest update

January 05, 2026 – The public comment period on the project is closed. The NRC is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.

Participate

Key documents

Contacts

National Research Council of Canada
Email: NRC.ImpactAssessment-Evaluationdimpact.CNRC@nrc-cnrc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • National Research Council of Canada (Ontario)
  • Nature of Activity

    • Building and Property Development
    • Maintenance activities (fences, walls)
  • Assessment Status

    Completed
  • Start Date

    2025-12-01
  • Proponent

    National Research Council of Canada
  • Authorities

    • National Research Council of Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    90041