Ebb and Flow First Nation - Road and Drainage Upgrades

  • Upgrade 6 existing community roads
  • Construct new drainage ditching and swales along roads and re-grade existing ditching and swales
  • Replace and install new culverts on upgraded road sections.
  • Reconstruct driveaway approaches along upgrade road sections.
  • Existing road surface will be re-graded and re-constructed with compacted subgrade and granular road base from local borrow pits.
  • 75,000 sq.m.

Latest update

June 24, 2024 – Indigenous Services Canada intends to make a determination regarding whether the carrying out of the project is likely to cause significant adverse environmental effects. To help inform this determination, Indigenous Services is inviting public comments until July 24, 2024 respecting that determination.

Participate

Key documents

Key documents
Document Number Document Title File Date
1 Notice of Intent to Make a Determination - Start of Public Comment Period - June 24, 2024

Contacts

Indigenous Services Canada (ISC)
Shelly Johnson, Senior Environmental Specialist
200 - 365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-227-3891
Email: shelly.johnson@sac-isc.gc.ca


  • Location

    • Ebb and Flow First Nation (Manitoba)
  • Nature of Activity

    • Highways and Roads
  • Assessment Status

    In progress
  • Start Date

    2024-06-24
  • Proponent

    Ebb and Flow First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    88664
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: