Underground Complex Substation Replacement, North Bay, ON

The Department of National Defence is replacing the existing Underground Complex's electrical substation at 22 Wing North Bay. The substation is located on Department of National Defence property south of Tower Drive and is the primary electrical service for the Underground Complex.

The existing substation is required to be replaced as it suffered damage in 2019. The replacement system will involve disposal and replacement of existing transformers, grounding systems, switching, metering, overhead support structure, ground grid, conduits, concrete pads, and fencing. In addition, a new surficial switchgear generator will be installed.

Project areas and access-ways disturbed by construction activities will be restored through landscaping operations, fine grading, revegetation and blending with existing grades as required.

More


Latest update

October 15, 2020 – The Department of National Defence issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Contacts

Wing Environment Officer, 22 Wing North Bay, Ontario
Department of National Defence
Shannon Roy, Wing Environment Officer, 22 Wing North Bay, Ontario
22 Wing North Bay
General Delivery Station Main
Hornell Heights, Ontario P0H 1P0
Email: Shannon.Roy@forces.gc.ca


  • Location

    • Approximately 1.8 km south of 22 Wing's Main Base (Ontario)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2020-07-17
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    80853
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 