Carry The Kettle First Nation Lagoon Expansion

The Proposed Project

A new HDPE DR 11 Sewage Force main to be installed in the ditch of the lagoon access road parallel to the existing sewage force main. New Storage 66,000 Cubic Metres storage cell for the facultative lagoon. New 1.5 Ha Primary Cell for the Facultative Lagoon
New Wet Dry Style Sewage Pumping Station.

During construction top soil will be stripped, the ground will be excavated and lagoon berms will be constructed around the excavation. The lagoon will be lined with a HDPE liner to prevent effluent from seeping into the ground. Weeping tile will be installed under the liner. 300mm of sand will be installed on top of the liner for puncture protection. Topsoil will be replaced on the berms and seeded. Concrete effluent transfer structures will be installed for the new lagoon cells.

A new sewage forcemain will be installed via open trenching down the ditch of an existing roadway next to the existing sewage force main. Top soil will be stripped, replaced and seeded upon completion.

The new sewage pumping station will be excavated near the existing sewage pumping station to tie-into existing gravity sewer infrastructure. The structure will be approximately 6-7 meters in depth and will be comprised of concrete walls. The area will be excavated, temporary formwork for the walls will be constructed, rebar placed and concrete poured. Upon completion of the foundation a small 750 square foot building will be constructed housing a backup generator, motor control center and pumping equipment.

General construction waste, wood, plastics, and access materials will be disposed of off site properly as per provincial laws and regulations. Any access soils and earthworks will be used in the thickening of the lagoon berms.

More


Latest update

May 31, 2021 - Indigenous Services Canada issued its notice of determination https://iaac-aeic.gc.ca/050/evaluations/document/139261 and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination for Carry The Kettle First Nation Lagoon Expansion - May 31, 2021
1 Public Comment Period on Intent to Make a Determination - April 30, 2021

Contacts

ISC-SKENV
Indigenous Services Canada
1827 Albert Street
Regina, Saskatchewan S4P 2S9
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca


  • Location

    • Assiniboine IR 76 (Saskatchewan)
  • Nature of Activity

    • Water Management
    • Waste Management
  • Assessment Status

    Completed
  • Start Date

    2022-06-01
  • Proponent

    Carry The Kettle First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    81589
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: