Chipewyan Prairie First Nation Wastewater Treatment Plant Expansion
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
This project includes the construction of a new facultative (conventional) sewage lagoon, new sewage pumping station and new sewage force main for the community. The purpose of this project is to replace the existing sewage treatment and collection / pumping infrastructure as the existing infrastructure is undersized, does not meet operational standards, and is located adjacent to the community, within the recommended minimum setback distance which poses a health and safety risk.
The new lagoon upgrades will include construction of four (4) new HDPE-lined lagoon cells: two (2) new 2,000 cubic metre anaerobic cells, one (1) new 19,035 cubic metre primary (treatment) cell, and one (1) new 92,785 cubic metre storage cell. Overall the projected lifespan of the new lagoon is a minimum of 20 years. The existing lagoon and related infrastructure will be decommissioned as part of the project, including removal of existing wastewater, leveling and backfilling and site decommissioning to Alberta standards.
The project will also include construction of a new primary sewage pumping station complete with wet / dry style substructure and a timber framed building for housing of all controls and a backup power generator. New building size is approximately 67 square metres. The projected life span of the new pumping station is a minimum of 20 years. The sewage pumping station will be constructed adjacent to the existing primary, submersible wet well style station for the community. The existing station will be decommissioned including removal of all mechanical and electrical equipment, demolishing the existing barrel to below grade, backfill and site grading. The new sewage force main from the pumping station to the lagoon will be approximately 3,200 metres of 150 mm diameter HDPE piping. A new 1,100 metre long access road is also required to access the new lagoon site from the existing roadways.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
4 | Notice of Determination for the Chipewyan Prairie First Nation Wastewater Treatment Plant Expansion Project | - | March 29, 2021 |
1 | Public Comment Period on Intent to Make a Determination | - | November 10, 2020 |
Contacts
Indigenous Services CanadaStacey LeBlanc, Sr. Environment Officer
630 Canada Place, 9700 Jasper Ave
Edmonton, Alberta T5J 4G2
Telephone: 780-782-8350
Email: stacey.leblanc@canada.ca
-
Location
- Chipewyan Prairie First Nation (Alberta)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2020-11-10 -
Proponent
Chipewyan Prairie First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81132
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Cenovus Foster Creek - North Trunk Gate (NTG) in Cold Lake Alberta
Cenovus Foster Creek - North Trunk Gate (NTG) -
Chipewyan Prairie First Nation 2021 Subdivision Project (Phase 1)
Chipewyan Prairie First Nation -
New Fibre Installation
Project site 4: Regional Municipality of Wood Buffalo -
ATCO Gas and Pipelines: 1091764 North Janvier Natural Gas Delivery Pipeline Upgrade Project
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units)
Chipewyan Prairie First Nation -
Janvier Secondary Egress Road
Chipewyan Prairie First Nation -
Cenovus Foster Creek - Maintenance in Cold Lake Alberta.
Cenovus Foster Creek - Maintenance -
Cenovus Energy SCADA system modification Project in Foster Creek on Cold Lake Weapons Range
Cenovus Energy SCADA system modification Project -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
06-09-069-04W4 -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
11-04-069-04W4 -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P162 - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
Canadian Natural Resources Limited - New radiocommunications tower on NW 34-68-4 W4M, Cold Lake Air Weapons Range, AB
NW 34-68-4 W4M. , Cold Lake Air Weapons Range, AB -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P71C - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
Regional Assessment of Beaver Lake Cree Nation's Traditional Territory
Lac la Biche -
Cold Lake Air Weapons Range (CLAWR) Culvert Replacement
4 Wing Cold Lake -
New Fibre Installation
Project Site 1 - Heart Lake: -
Heart Lake First Nations antenna supporting structure located on the Heart Lake First Nations in Lac La Biche County
Heart Lake First Nations antenna supporting structure -
Heart Lake First Nation: CU370 Wastewater System Emergency Repairs
Heart Lake First Nation -
New Fibre Installation
Project Site 2 - Heart Lake: -
Heart Lake First Nation: Inter-jurisdictional Access Road
Heart Lake First Nation #167 -
Heart Lake BF 80752 Bridge Replacement
Heart Lake First Nation -
Replacement of Water Crossing and Road Alignment
Primrose Lake Evaluation Range -
Buffalo River Dene Nation Solid Waste Transfer Station
BUFFALO RIVER DENE NATION RESERVE #193 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 2) -
Buffalo River Dene Nation Fire Hall
Peter Pond Lake Indian Reserve No. 193 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 1) -
Fixed Point-to-Point Link from Buffalo Narrows, SK to Dillon, SK
Buffalo River Dene Nation I.R. 193 -
Buffalo River Dene Nation Subdivision Stage 4
Buffalo River Dene Nation IR 193 -
Fort McMurray First Nation Water and Wastewater Infrastructure
Fort McMurray First Nation -
New Fibre Installation
Project site 3: Regional Municipality of Wood Buffalo -
Marguerite Lake Compressed Air Energy Storage Project
La Corey -
ATCO Gas and Pipelines Ltd.: 1088748 Gregoire Lake IR No. 176A Lakeshore Drive Gas Distribution System Extension
Fort McMurray First Nation -
New Fibre Installation
Project site 2: Regional Municipality of Wood Buffalo -
Fort McMurray First Nation: Gregoire Lake Water and Sewage Project
Gregoire Lake -
Cold Lake First Nation Water System Upgrades
Cold Lake First Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 3: Cold Lake -
Cold Lake First Nation: CUZD3 Phase II and III Water Distribution System
Cold Lake First Nation -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 2: Cold Lake -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Cold Lake -
Campus Energy - Pipeline Replacement/Removal
4 Wing Cold Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 2) -
Clearwater River Dene Subdivision
Clearwater River Dene IR 122 -
21M Range Revitalization (CL220020) - 4 Wing Cold Lake
4 Wing Cold Lake -
Renovation of Building 325 - Pumphouse & Water Purification Plant (CL210010) - 4 Wing Cold Lake
4 Wing Cold Lake -
Demolition of Barrack Block 48 - 4 Wing Cold Lake
4 Wing Cold Lake -
Replacement of Collapsed Storm Sewer Lines - 4 Wing Cold Lake
4 Wing Cold Lake -
Maintenance, Repair, and Installation Work for Storage Tank Systems - Cold Lake Air Weapons Range and 4 Wing Cold Lake
Cold Lake Air Weapons Range and 4 Wing Cold Lake -
Building Demolition and Underground Fuel Line Removal - 4 Wing Cold Lake
4 Wing Cold Lake -
Building Demolition - 4 Wing Cold Lake
Cold Lake -
Department of National Defence Future Fighter Capability Project - Demolition of Hangars 6 and 7, and Construction of New Supporting Infrastructure
4 Wing Cold Lake, approximately 300 kilometers northeast of Edmonton -
Power Grid Modernization - 4 Wing Cold Lake
4 Wing Cold Lake -
Cold Lake First Nation Housing Project 2019 (10 Unit Renovation)
Cold Lake First Nation -
Cold Lake First Nations: Casino Dene Expansion, Event Centre, Parking Project
Cold Lake First Nations -
Cold Lake First Nations Community Gathering Space
Cold Lake First Nations -
Cold Lake First Nations Casino Expansion Project
Cold Lake First Nations -
Beaver Lake Cenovus Housing Initiative - Build Out of 20 Residential Lots, Access Roads, and Water Distribution
Beaver Lake Cree Nation -
Beaver Lake New School
Beaver Lake Cree Nation -
Beaver Lake Cree Nation Fiber Optic Internet Infrastructure - Universal Broadband Fund Project
Beaver Lake Cree Nation -
Beaver Lake Cree First Nation Cardinal Drive Subdivision
Beaver Lake Cree Cardinal Drive Subdivision -
Beaver Lake Cree Nation New High School and Resource Centre
Beaver Lake Cree Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 1: Cold Lake -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Cold Lake First Nation: CUZ46 Wastewater System Expansion
Cold Lake First Nation -
Cold Lake Budget 2018 Year Three Housing Project 2020 (6 Units)
Cold Lake First Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 4: Cold Lake -
Cold Lake First Nation - Frog Lake Regional Water Tie-In
Cold Lake First Nation -
Powwow Arbour Construction
Pierceland -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 1: Cold Lake -
Pelican Renewable Generating Station Project
180 kilometres upstream of Fort McMurray -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 2: Cold Lake -
2017 NGTL System Expansion Project
Fort McMurray -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 5: Cold Lake -
Clearwater Multi-User Access Project, Alberta
Clearwater River -
Sundog Renewable Generating Station Project
130 kilometres upstream of Fort McMurray -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 2) -
Birch Narrows Dene Nation Community Centre
Birch Narrows Dene Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 2) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 3) -
Weepuskow Sahgaiechan IR 165D Timber Harvest Plan 2020-21
WEPUSKOW SAHGAIECHAN IR 165 D -
Kehewin Treatment Centre - 2020-3825
Kehewin Cree Nation -
Kehewin Lift Station Project
Kehewin Cree Nation -
OS -7254 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad - Public Comments Invited
Kehewin Cree Nation -
Telus telecommunications tower located on Kehewin Cree Nation located south of Bonnyville, AB
Telus telecommunications tower located on Kehewin Cree Nation -
Kehewin Cree Nation Telus Tower AB103726
Kehewin Cree Nation -
Whitefish Lake First Nation #128 Waste Transfer Station
Whitefish Lake First Nation #128 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WATERHEN I.R. 130 -
RW-4850 Authorization to Construct and Operate a Right of Way for a gas pipeline
RW-4850 -
Kehewin Transmission System Extension Project
Kehewin Cree Nation -
Kehewin Cree Nation Waste Diversion Station
Kehewin Cree Nation -
Saddle Lake Cree Nation: CU123 Whitefish Lake IR no. 128 Water System - Cistern Repairs & Replacements
Saddle Lake Cree Nation -
Suncor Base Mine Extension Project
3 kilometres north of Fort McMurray -
Ministikwan Lake Cree Nation - Solid Waste Transfer Station
Ministikwan IR161 -
Fixed Point-to-Point Link from Dorintosh, SK to Waterhen Lake, SK
Waterhen 130 Reserve -
Ministikwan Subdivision Development
Ministikwan IR 161 -
Frog Lake First Nation Landfill Cap Construction
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161A -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 2) -
Suncor Energy Coke Fired Boiler Replacement Project
25 kilometres north of Fort McMurray -
Wapachewunak Water Treatment Plant Optimization
Wapachewunak IR 192D -
Frog Lake Waste Management Transfer Station
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 1) -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
Saddle Lake Cree Nation: P047935 Child Welfare Reunification Infrastructure Project
Saddle Lake First Nation -
OS-6870 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
OS-6634 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
OS-7251 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
SaskPower HR-01033 - RPD-511 PQ Rural Rebuild (Makwa Rebuild)
Makwa First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 1) -
Makwa Lake Resort Development
Makwa Lake Indian Reserve No. 129B -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
LA PLONGE I.R. 192 -
Highway 165 Grade Raise near Beauval, SK
Beauval, SK -
La Plonge Solar Project
English River First Nation Reserve -
La Plonge Solar and Battery Energy Storage System
English River First Nation Reserve -
English River First Nation Sewage Lagoon Upgrades
La Plonge Indian Reserve No. 192 -
OS-7250 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 2) -
Saddle Lake Cree Nation Road Rehabilitation
Saddle Lake #125 -
Frog Lake Waskonaman Hill Gravel Project (Amendment)
Frog Lake First Nation -
OS-6825 Authorization to Construct an access road and a Surface Lease Extension and Operate a Multi-well oil pad
OS-6825 -
Saddle Lake Gas Distribution System (Child Welfare Reunification Subdivision)
Saddle Lake Cree Nation -
OS-6826 Authorization to extend an existing surface lease area for a multi-well pad
Frog Lake First Nation -
Frog Lake CFS Equine Centre
Frog Lake -
New Fibre Installation
Saddle Lake 125 -
Saddle Lake Cree Nation 9A Road Saddle Lake Creek Culvert Replacement Project
Saddle Lake Cree Nation -
Saddle Lake Broadband and Cellular Connectivity Upgrade and Resilience Plan Project
Saddle Lake -
Saddle Lake 40 Acre Housing Project
Saddle Lake Cree Nation -
Saddle Lake Cree Nation Women's Shelter Project
Saddle Lake Cree Nation -
ATCO Gas and Pipelines Ltd.: 1098480 Wabasca IR No. 166 Phase 2 Alfred Road Gas Main & Distribution System
Bigstone Cree Nation -
New Fibre Installation
Project Site 5 - Wabasca No. 166: -
New Fibre Installation
Project site 1: Regional Municipality of Wood Buffalo -
Fort McKay First Nation: 2023/24 Residential Redevelopment Project
Fort McKay First Nation -
Fort McKay First Nation K-9 School
Fort McKay First Nation