Suncor Base Plant Water Treatment Plant Project
Suncor Energy Inc. is proposing to construct a wastewater treatment facility, located within the existing Suncor Base Plant area, north of Fort McMurray, Alberta. As proposed, the Suncor Base Plant Water Treatment Plant Project would include the construction of a new water pipeline and wastewater treatment facility, and modification of the existing outfall at Suncor's Base Plant. The project would treat oil sands process water and discharge into the Athabasca River, with a maximum design production rate of approximately 12 million cubic metres per year. The project is expected to operate for about 20 years.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 5 | Fifth request for designation of project | PDF (1.7 MB) | October 5, 2026 |
| 4 | Fourth request for designation of project | PDF (3.4 MB) | September 25, 2026 |
| 3 | Third request for designation of project | PDF (972 KB) | September 2, 2026 |
| 2 | Second request for designation of project | PDF (1.6 MB) | August 25, 2026 |
| 1 | Request for designation of project | PDF (1.2 MB) | August 21, 2026 |
Contacts
Prairie and Northern Regional OfficeImpact Assessment Agency of Canada
1145-9700 Jasper Avenue
Edmonton AB T5J 4C3
Telephone: 780-495-2037
Fax: 780-495-2876
Email: PNR-RPN@iaac-aeic.gc.ca
Media Relations
Impact Assessment Agency of Canada
160 Elgin Street, 22nd Floor
Ottawa ON K1A 0H3
Email: media@iaac-aeic.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- 20 kilometres north of Fort McMurray (Alberta)
-
Nature of activity
- Water Management
-
Assessment status
In progress -
Start date
2026-09-10 -
Proponent
Suncor Energy Inc. -
Authorities
- Impact Assessment Agency of Canada
-
Assessment type
Request for designation -
Reference number
90251
Nearby assessments
...within 200 kilometres-
Suncor Energy Coke Fired Boiler Replacement Project
25 kilometres north of Fort McMurray -
Suncor Base Mine Extension Project
3 kilometres north of Fort McMurray -
Pathways Alliance CO2 Transportation Network and Storage Hub Project
Carbon Capture Infrastructure and Lateral Pipelines -
Clearwater Multi-User Access Project, Alberta
Clearwater River -
New Fibre Installation
Project site 1: Regional Municipality of Wood Buffalo -
2017 NGTL System Expansion Project
Fort McMurray -
Fort McKay First Nation: 2023/24 Residential Redevelopment Project
Fort McKay First Nation -
Fort McKay First Nation K-9 School
Fort McKay First Nation -
Jackpine Mine Expansion Project
Fort McKay -
Fort McMurray First Nation New Housing Construction Project
GREGOIRE LAKE NO. 176A -
Fort McMurray First Nation: Gregoire Lake Water and Sewage Project
Gregoire Lake -
New Fibre Installation
Project site 2: Regional Municipality of Wood Buffalo -
ATCO Gas and Pipelines Ltd.: 1088748 Gregoire Lake IR No. 176A Lakeshore Drive Gas Distribution System Extension
Fort McMurray First Nation -
New Fibre Installation
Project site 3: Regional Municipality of Wood Buffalo -
Fort McMurray First Nation Water and Wastewater Infrastructure
Fort McMurray First Nation -
Fort McMurray First Nation New Housing Construction Project
GREGOIRE LAKE NO. 176 -
Pierre River Mine Project
Fort McKay -
Frontier Oil Sands Mine Project
Fort McKay -
Pathways Alliance CO2 Transportation Network and Storage Hub Project
Main Transportation Pipeline -
Sundog Renewable Generating Station Project
130 kilometres upstream of Fort McMurray -
Janvier Secondary Egress Road
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units)
Chipewyan Prairie First Nation -
ATCO Gas and Pipelines: 1091764 North Janvier Natural Gas Delivery Pipeline Upgrade Project
Chipewyan Prairie First Nation -
0861 - Upgrade (33 & 48 - 60mm) North Janvier
Janvier -
New Fibre Installation
Project site 4: Regional Municipality of Wood Buffalo -
Chipewyan Prairie First Nation 2021 Subdivision Project (Phase 1)
Chipewyan Prairie First Nation -
Chipewyan Prairie Subdivision Phase 5
Janvier 194 -
1121393 - 0861 - SubD(13RUP) CPFN Janvier - Phase 2
Janvier -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 1) -
Clearwater River Dene Subdivision
Clearwater River Dene IR 122 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 2) -
Armand Bekkattla Treatment Centre Recapitalization and Expansion
Clearwater River Dene Band 222 -
La Loche Hotel
La Loche -
Patterson Lake South Mine Project
Patterson Lake -
Big Bear Camp Aerodrome Project
Grygar Lake -
Rook I Project
Patterson Lake -
Pelican Renewable Generating Station Project
180 kilometres upstream of Fort McMurray -
Big Egg Lake Water Control Structure
Athabasca Chipewyan First Nation Jackfish Reserve (I.R. 201) -
Chipewyan Prairie First Nation Wastewater Treatment Plant Expansion
Chipewyan Prairie First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 2) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 1) -
Birch Narrows First Nation Solid Waste Transfer Station
Turnor Lake Indian Reserve 193B -
Birch Narrows Dene Nation Community Centre
Birch Narrows Dene Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 3) -
New Fibre Installation
Project Site 5 - Wabasca No. 166: -
ATCO Gas and Pipelines Ltd.: 1098480 Wabasca IR No. 166 Phase 2 Alfred Road Gas Main & Distribution System
Bigstone Cree Nation -
New Fibre Installation
Project Site 3 - Wabasca No. 166C: -
Wabasca Water Treatment Plant Upgrades Project
Wabasca -
ATCO Gas and Pipelines Ltd.: 1088866 Bigstone Cree Nation & Hamlet of Sandy Lake Gas Feeder and Mains at Wabasca IR No. 166
Bigstone Cree Nation -
ATCO Gas and Pipelines Ltd.: 1088866 Wabasca IR No. 166A Gas Distribution Extension
Bigstone Cree Nation Wabasca IR No. 166A -
Bigstone Cree Nation Oilfield Supply Store
Wabasca #166 -
Hoole Creek Road Subdivision Apex Utilities
Wabasca 166A -
APEX Utilities Inc. - Opasikoniwew Housing Authority: Hoole Creek Road Subdivision Phase 2 Gasification Project
Wabasca -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Dog Camp Water Control Structure
Wood Buffalo National Park of Canada -
Bigstone Cree Nation Education Authority: CU254 Oksi Pasikoniwew Kakik School Secondary Access Road Project
Bigstone Cree Nation -
Bigstone Cree Nation New High School
Bigstone Cree Nation -
Bigstone Cree Nation Education Authority
Bigstone Cree Nation Education Authority antenna supporting structure located on Bigstone Cree Nation in Wabasca-Desmarais, AB. -
Bigstone B.O.S.S Modular Construction and Fabrication Yard Expansion Project
Bigstone Cree Nation -
Bigstone Cree Nation Temporary Modular Office Complex
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-10 TSAG ID No. 07 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation Education Authority
Bigstone Cree Nation Education Authority antenna supporting structure located on Bigstone Cree Nation in Wabasca-Desmarais, AB. -
New Fibre Installation
Project Site 1 - Bigstone Cree Nation: -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-17 TSAG ID No. 03 Replacement
Bigstone Cree Nation -
Peace-Athabasca Delta Field Station
Detailed Impact Assessment, Wood Buffalo National Park -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-18 TSAG ID No. 04 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation High School Waterline Project
Wabasca -
Establish Water Survey of Canada river depth station on north branch of Quatre Fourches
Wood Buffalo National Park -
Buffalo River Dene Nation School Bypass Road Relocation
Buffalo River Dene Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 1) -
Fixed Point-to-Point Link from Buffalo Narrows, SK to Dillon, SK
Buffalo River Dene Nation I.R. 193 -
Peerless Housing CMHC Site 2
Peerless Trout IR No. 238 -
Peerless CMHC Housing PTFN Camp Area
Peerless Trout IR No. 238 -
Buffalo River Dene Nation Fire Hall
Peter Pond Lake Indian Reserve No. 193 -
New Fibre Installation
Project Site 2 - Wabasca No. 166B : -
Buffalo River Dene Nation Lagoon Expansion
BUFFALO RIVER DENE NATION RESERVE NO. 193 -
Buffalo River Dene Nation Stage 5 Subdivision
BUFFALO RIVER DENE NATION RESERVE NO. 193 -
Maskotehk Flood Mitigation Upgrades - Borrow Pits
Wabasca 166D -
Buffalo River Dene Nation Subdivision Stage 4
Buffalo River Dene Nation IR 193 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 2) -
Bigstone Cree Nation: P057828 - Maskotehk Flood Mitigation Upgrades at Cattleman Drive & Cee Too Drive
Wabasca IR 166D -
Buffalo River Dene Nation Solid Waste Remediation
BUFFALO RIVER DENE NATION RESERVE NO. 193 -
Buffalo River Dene Nation Solid Waste Transfer Station
BUFFALO RIVER DENE NATION RESERVE #193 -
New Fibre Installation
Project Site 4 - Wabasca No. 166D: -
OS-7241 Wabasca IR 166D | Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell pad
Wabasca IR # 116D -
Bigstone Cree Nation Flood Recovery Program: Culvert 166D-27 Replacement
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166D-08 TSAG ID No. 08 Replacement
Bigstone Cree Nation -
166D Pumphouse Upgrades
166D Pumphouse Upgrade -
Rogers Communications Inc., new radiocommunications tower (W6225) on Peerless Trout First Nation land, near Peerless Lake, AB.
W6225 - Peerless Trout First Nation Land (near Peerless Lake) -
North Corridor Expansion Project
Peerless Lake