Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units)
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
5 units - 1736 sq. ft. in size, all with direct line drinking water system except for one unit (2006 AJ with a water tank drinking system), all with sewage tank system except for one unit (2002 DN with a direct line sewage system), and all units with natural gas heating type.
Latest update
August 31, 2022 – Indigenous Services Canada issued its notice of determination Notice of Determination for the Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units) - Canada.ca (iaac-aeic.gc.ca) and determined that the project is not likely to cause significant adverse environmental effects.
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination for the Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units) | - | August 31, 2022 |
1 | Public Comment Period on Intent to Make a Determination | - | December 24, 2020 |
Contacts
Indigenous Services CanadaStacey LeBlanc, Sr. Environment Officer
630 Canada Place, 9700 Jasper Ave
Edmonton, Alberta T5J 4G2
Telephone: 780-782-8350
Email: stacey.leblanc@canada.ca
-
Location
- Chipewyan Prairie First Nation (Alberta)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
Completed -
Start Date
2020-12-24 -
Proponent
Chipewyan Prairie First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81260
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Janvier Secondary Egress Road
Chipewyan Prairie First Nation -
New Fibre Installation
Project site 4: Regional Municipality of Wood Buffalo -
ATCO Gas and Pipelines: 1091764 North Janvier Natural Gas Delivery Pipeline Upgrade Project
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation 2021 Subdivision Project (Phase 1)
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation Wastewater Treatment Plant Expansion
Chipewyan Prairie First Nation -
Fort McMurray First Nation Water and Wastewater Infrastructure
Fort McMurray First Nation -
New Fibre Installation
Project site 3: Regional Municipality of Wood Buffalo -
ATCO Gas and Pipelines Ltd.: 1088748 Gregoire Lake IR No. 176A Lakeshore Drive Gas Distribution System Extension
Fort McMurray First Nation -
New Fibre Installation
Project site 2: Regional Municipality of Wood Buffalo -
Fort McMurray First Nation: Gregoire Lake Water and Sewage Project
Gregoire Lake -
Cenovus Foster Creek - North Trunk Gate (NTG) in Cold Lake Alberta
Cenovus Foster Creek - North Trunk Gate (NTG) -
Cenovus Energy SCADA system modification Project in Foster Creek on Cold Lake Weapons Range
Cenovus Energy SCADA system modification Project -
Cenovus Foster Creek - Maintenance in Cold Lake Alberta.
Cenovus Foster Creek - Maintenance -
2017 NGTL System Expansion Project
Fort McMurray -
Clearwater Multi-User Access Project, Alberta
Clearwater River -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 2) -
Clearwater River Dene Subdivision
Clearwater River Dene IR 122 -
Regional Assessment of Beaver Lake Cree Nation's Traditional Territory
Lac la Biche -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
06-09-069-04W4 -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
11-04-069-04W4 -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P162 - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P71C - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
Canadian Natural Resources Limited - New radiocommunications tower on NW 34-68-4 W4M, Cold Lake Air Weapons Range, AB
NW 34-68-4 W4M. , Cold Lake Air Weapons Range, AB -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 1) -
Fixed Point-to-Point Link from Buffalo Narrows, SK to Dillon, SK
Buffalo River Dene Nation I.R. 193 -
Buffalo River Dene Nation Fire Hall
Peter Pond Lake Indian Reserve No. 193 -
New Fibre Installation
Project Site 1 - Heart Lake: -
Heart Lake First Nation: Inter-jurisdictional Access Road
Heart Lake First Nation #167 -
Heart Lake First Nation: CU370 Wastewater System Emergency Repairs
Heart Lake First Nation -
Heart Lake First Nations antenna supporting structure located on the Heart Lake First Nations in Lac La Biche County
Heart Lake First Nations antenna supporting structure -
New Fibre Installation
Project Site 2 - Heart Lake: -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 2) -
Heart Lake BF 80752 Bridge Replacement
Heart Lake First Nation -
Buffalo River Dene Nation Solid Waste Transfer Station
BUFFALO RIVER DENE NATION RESERVE #193 -
Buffalo River Dene Nation Subdivision Stage 4
Buffalo River Dene Nation IR 193 -
Sundog Renewable Generating Station Project
130 kilometres upstream of Fort McMurray -
Suncor Base Mine Extension Project
3 kilometres north of Fort McMurray -
Pelican Renewable Generating Station Project
180 kilometres upstream of Fort McMurray -
Suncor Energy Coke Fired Boiler Replacement Project
25 kilometres north of Fort McMurray -
Cold Lake Air Weapons Range (CLAWR) Culvert Replacement
4 Wing Cold Lake -
Replacement of Water Crossing and Road Alignment
Primrose Lake Evaluation Range -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 2) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 1) -
Birch Narrows Dene Nation Community Centre
Birch Narrows Dene Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 3) -
Marguerite Lake Compressed Air Energy Storage Project
La Corey -
New Fibre Installation
Project site 1: Regional Municipality of Wood Buffalo -
Fort McKay First Nation: 2023/24 Residential Redevelopment Project
Fort McKay First Nation -
Fort McKay First Nation K-9 School
Fort McKay First Nation -
Beaver Lake Cenovus Housing Initiative - Build Out of 20 Residential Lots, Access Roads, and Water Distribution
Beaver Lake Cree Nation -
Cold Lake First Nation Water System Upgrades
Cold Lake First Nation -
Beaver Lake New School
Beaver Lake Cree Nation -
Beaver Lake Cree First Nation Cardinal Drive Subdivision
Beaver Lake Cree Cardinal Drive Subdivision -
Beaver Lake Cree Nation Fiber Optic Internet Infrastructure - Universal Broadband Fund Project
Beaver Lake Cree Nation -
Beaver Lake Cree Nation New High School and Resource Centre
Beaver Lake Cree Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 3: Cold Lake -
Cold Lake First Nation: CUZD3 Phase II and III Water Distribution System
Cold Lake First Nation -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Jackpine Mine Expansion Project
Fort McKay -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 2: Cold Lake -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Cold Lake -
Campus Energy - Pipeline Replacement/Removal
4 Wing Cold Lake -
Building Demolition - 4 Wing Cold Lake
Cold Lake -
21M Range Revitalization (CL220020) - 4 Wing Cold Lake
4 Wing Cold Lake -
Renovation of Building 325 - Pumphouse & Water Purification Plant (CL210010) - 4 Wing Cold Lake
4 Wing Cold Lake -
Demolition of Barrack Block 48 - 4 Wing Cold Lake
4 Wing Cold Lake -
Replacement of Collapsed Storm Sewer Lines - 4 Wing Cold Lake
4 Wing Cold Lake -
Maintenance, Repair, and Installation Work for Storage Tank Systems - Cold Lake Air Weapons Range and 4 Wing Cold Lake
Cold Lake Air Weapons Range and 4 Wing Cold Lake -
Building Demolition and Underground Fuel Line Removal - 4 Wing Cold Lake
4 Wing Cold Lake -
ATCO Gas and Pipelines Ltd.: 1098480 Wabasca IR No. 166 Phase 2 Alfred Road Gas Main & Distribution System
Bigstone Cree Nation -
Department of National Defence Future Fighter Capability Project - Demolition of Hangars 6 and 7, and Construction of New Supporting Infrastructure
4 Wing Cold Lake, approximately 300 kilometers northeast of Edmonton -
New Fibre Installation
Project Site 5 - Wabasca No. 166: -
Power Grid Modernization - 4 Wing Cold Lake
4 Wing Cold Lake -
Cold Lake First Nation Housing Project 2019 (10 Unit Renovation)
Cold Lake First Nation -
ATCO Gas and Pipelines Ltd.: 1088866 Bigstone Cree Nation & Hamlet of Sandy Lake Gas Feeder and Mains at Wabasca IR No. 166
Bigstone Cree Nation -
Cold Lake First Nations: Casino Dene Expansion, Event Centre, Parking Project
Cold Lake First Nations -
Cold Lake First Nations Community Gathering Space
Cold Lake First Nations -
Cold Lake First Nations Casino Expansion Project
Cold Lake First Nations -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 1: Cold Lake -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Cold Lake First Nation: CUZ46 Wastewater System Expansion
Cold Lake First Nation -
Cold Lake Budget 2018 Year Three Housing Project 2020 (6 Units)
Cold Lake First Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 4: Cold Lake -
Cold Lake First Nation - Frog Lake Regional Water Tie-In
Cold Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 2) -
Powwow Arbour Construction
Pierceland -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 1: Cold Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 2) -
Wapachewunak Water Treatment Plant Optimization
Wapachewunak IR 192D -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 1) -
ATCO Gas and Pipelines Ltd.: 1088866 Wabasca IR No. 166A Gas Distribution Extension
Bigstone Cree Nation Wabasca IR No. 166A -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 2: Cold Lake -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 5: Cold Lake -
Bigstone Cree Nation Oilfield Supply Store
Wabasca #166 -
Bigstone Cree Nation Education Authority: CU254 Oksi Pasikoniwew Kakik School Secondary Access Road Project
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-10 TSAG ID No. 07 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation New High School
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-17 TSAG ID No. 03 Replacement
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-18 TSAG ID No. 04 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 1 - Bigstone Cree Nation: -
Whitefish Lake First Nation #128 Waste Transfer Station
Whitefish Lake First Nation #128 -
Bigstone Cree Nation High School Waterline Project
Wabasca -
Bigstone B.O.S.S Modular Construction and Fabrication Yard Expansion Project
Bigstone Cree Nation -
Pierre River Mine Project
Fort McKay -
Weepuskow Sahgaiechan IR 165D Timber Harvest Plan 2020-21
WEPUSKOW SAHGAIECHAN IR 165 D -
New Fibre Installation
Project Site 3 - Wabasca No. 166C: -
OS-7241 Wabasca IR 166D | Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell pad
Wabasca IR # 116D -
Wabasca Water Treatment Plant Upgrades Project
Wabasca -
New Fibre Installation
Project Site 2 - Wabasca No. 166B : -
Bigstone Cree Nation Flood Recovery Program: Culvert 166D-27 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 4 - Wabasca No. 166D: