Driftpile Cree Nation Gas Line Connector Project

Install a 3" low pressure gas line into the First Nation to ensure there is no gas shortage to the expanding community. The new line will provide enough gas to support the Nation for years to come.


Latest update

December 6, 2021 – Indigenous Services Canada issued its notice of determination https://iaac-aeic.gc.ca/050/evaluations/document/142328 and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination for the Driftpile Cree Nation Gas Line Connector Project - December 6, 2021
1 Public Comment Period on Intent to Make a Determination - November 1, 2021

Contacts

Indigenous Services Canada
Stacey LeBlanc, Sr. Environment Officer
630 Canada Place, 9700 Jasper Ave
Edmonton, Alberta T5J 4G2
Telephone: 780-782-8350
Email: stacey.leblanc@canada.ca


  • Location

    • Driftpile Cree Nation (Alberta)
  • Nature of Activity

    • Oil and Gas
  • Assessment Status

    Completed
  • Start Date

    2021-11-01
  • Proponent

    Prairie River Gas Co-op
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    83129
Disclaimer