Chinook Power Station Project
Saskatchewan Power Corporation (SaskPower) is proposing to construct and operate a 350-megawatt combined cycle natural gas power station located approximately 11 kilometres northwest of Swift Current, Saskatchewan. As proposed, the Chinook Power Station Project would have an operating lifespan of at least 30 years and include a power generation facility, a switchyard, and a new underground water pipeline.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
December 2, 2016 - The Canadian Environmental Assessment Agency issued its environmental assessment determination and decided that an environmental assessment of the designated project is not required.
Participate
Contacts
Impact Assessment Agency of Canada160 Elgin Street, 22nd Floor
Ottawa, Ontario K1A 0H3
Telephone: 613-957-0700 or 1-866-582-1884
Fax: 613-957-0862
Email: information@iaac-aeic.gc.ca
-
Location
- Approximately 11 kilometres northwest of Swift Current (Saskatchewan)
-
Nature of Activity
- Oil and Gas
-
Assessment Status
Completed -
Proponent
Saskatchewan Power Corporation (SaskPower) -
Authorities
- Canadian Environmental Assessment Agency
-
Assessment Type
Assessment not applicable -
Reference Number
80133
Nearby assessments
...within 200 kilometres-
Great Plains Generating Station Project
Northwest of Swift Current -
Ocean Man Indian Reserve 69E Pipeline
Ocean Man Indian Reserve 69E -
Nekaneet Fuel Station and Convenience Store
Nekaneet Cree Nation -
Decommissioning of Tenaille Lake Water Infrastructure
Tenaille Lake -
Gravel Pit Activation
Grasslands National Park -
Maple Creek Irrigation Project- Decommissioning of Dry Side
near Maple Creek -
Lake Diefenbaker Irrigation Expansion Projects
Lake Diefenbaker -
Road Operational Plan
Grasslands National Park -
Harvesting tame forage in Grasslands National Park
Grasslands National Park -
Installation of Primary Identification Signs at Grasslands National Park
Grasslands National Park -
Remediation of Top Dogtown Trail and Parking Area
Grasslands National Park of Canada -
License of Occupation to Graze Domestic Livestock in the Two Trees Pastures
Grasslands National Park of Canada -
Demolition and Disposal of Buildings in the West Block of Grasslands National Park
Grasslands National Park -
Prairie National Wildlife Area Units 25 and 26 Natural Gas Well Abandonment
Prairie National Wildlife Area Unit 25 -
Dixon Bridge Replacement
Grasslands National Park -
Burying Overhead Power Line in Grasslands National Park
Grasslands National Park -
Dugout Expansion in the West Block of Grasslands National Park
Grasslands National Park -
Prairie National Wildlife Area Units 25 and 26 Natural Gas Well Abandonment
Prairie National Wildlife Area Unit 26 -
Burying overhead power lines in township 1, range 1, west of the 3rd meridian in Grasslands National Park
Grasslands National Park -
Agricultural License of Occupation for former Walker Ranch
Grasslands National Park -
Agricultural License for Grazing Former Mankota Community Pasture
Grasslands National Park of Canada -
WireIE (Canada) Inc. - Radiocommunication Tower - Monchy Border Crossing, Hwy 4, Monchy SK
Monchy Border Crossing -
Walker Bridge Replacement in the West Block of Grasslands National Park
Grasslands National Park of Canada -
Dugout Expansion in the West Block of Grasslands National Park
Grasslands National Park -
WireIE (Canada) Inc. - Antenna Structure - Climax Border Crossing, Hwy 37, P.O. Box 330 Climax, SK
Climax Border Crossing -
Weather Station Installation in the West Block of Grasslands National Park
Grasslands National Park -
Solar Pumping Station Installation at Spring 263 in the East Block of Grasslands National Park
Grasslands National Park of Canada -
Water Development for Livestock in Former McCrae Pasture in the East Block of Grasslands National Park
Grasslands National Park -
Pilot Spring Development Project in the East Block of Grasslands National Park
Grasslands National Park -
Solar Pumping Station at Spring 263
Grasslands National Park -
Wildfire Risk Reduction Program for Fort Walsh National Historic Site 2023-2026
Fort Walsh National Historic Site -
Wildfire Risk Reduction at Fort Walsh National Historic Site
Fort Walsh National Historic Site -
East Block Interior Roads Stream Crossings Upgrades
Grasslands National Park -
Moose Jaw Combined Cycle Power Station Project
Moose Jaw -
WireIE (Canada) Inc. - Radiocommunication Tower - West Poplar River Border Crossing, Hwy 2, West Poplar, SK
West Poplar River Border Crossing -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Dakota Springs Spa
Whitecap IR #94 -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Enbridge Line 3 Replacement Program
Kerrobert -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Storage Tank Decommissioning and Relocation at Multiple Locations - 3rd Canadian Division Support Base, Southern Alberta
Patterson Armoury - Medicine Hat -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn