Document Notice of Environmental Assessment Determination

  • Project Chinook Power Station Project
  • Document Category: Additional Information
  • Reference Number: 5
  • Updated: 2016-12-02
  • Document: 116535E.html
  • Relevance: 214.68
  • Notice of Environmental Assessment Determination Ottawa – December 2, 2016 – The Canadian Environmental Assessment Agency (the Agency) has decided that a federal environmental assessment is not required for the Chinook Power Station Project pursuant to the Canadian Environmental Assessment Act, 2012 (CEAA 2012). In making this determination, the Agency considered the following factors as indicated in section 10 of CEAA 2012: the description of the project provided by the proponent on ...
1 alternate format found
French HTML
  • Relevance: 163.68
  • Avis de décision d'une évaluation environnementale Ottawa – Le 2 décembre 2016 – L'Agence canadienne d'évaluation environnementale (l'Agence) a décidé qu'une évaluation environnementale du projet de centrale électrique Chinook n'est pas requise en vertu de la Loi canadienne sur l'évaluation environnementale (2012) (LCEE 2012). Afin de prendre cette décision, l'Agence a tenu compte des facteurs suivants tel que présentés à l'article 10 de la LCEE 2012 : la description du projet fournie ...

Document News Release - Public Comments Invited on a Summary of the Project Description

  • Project Chinook Power Station Project
  • Document Category: News Releases
  • Reference Number: 2
  • Updated: 2016-10-19
  • Document: 115846E.html
  • Relevance: 213.45
  • News Release Chinook Power Station Project — Public Comments Invited October 19, 2016 — Ottawa — Canadian Environmental Assessment Agency The Canadian Environmental Assessment Agency must decide whether a federal environmental assessment is required for the proposed Chinook Power Station Project, located approximately 11 kilometres northwest of Swift Current, Saskatchewan. To help inform this decision, the Agency is seeking comments from the public on the project and its potential ...
1 alternate format found
French HTML
  • Relevance: 162.45
  • Communiqué Projet de centrale électrique Chinook — Période de consultation publique Le 19 octobre 2016 — Ottawa — Agence canadienne d'évaluation environnementale L'Agence canadienne d'évaluation environnementale doit décider si une évaluation environnementale fédérale est requise pour le projet de centrale électrique Chinook, situé à environ 11 kilomètres au nord-ouest de Swift Current, en Saskatchewan. En vue de prendre une décision éclairée, l'Agence invite le public à formuler des ...

Document Public Notice - Public Comments Invited on a Summary of the Project Description

  • Project Chinook Power Station Project
  • Document Category: For Public Participation
  • Reference Number: 1
  • Updated: 2016-10-19
  • Document: 115845E.html
  • Relevance: 213.45
  • Public Notice Chinook Power Station Project — Public Comments Invited October 19, 2016 — The Canadian Environmental Assessment Agency must decide whether a federal environmental assessment is required for the proposed Chinook Power Station Project, located near Swift Current, Saskatchewan. To help inform this decision, the Agency is seeking comments from the public on the project and its potential effects on the environment, as described in the summary of the project description. All ...
1 alternate format found
French HTML
  • Relevance: 162.45
  • Avis public Projet de centrale électrique Chinook — Période de consultation publique Le 19 octobre 2016 — L'Agence canadienne d'évaluation environnementale doit décider si une évaluation environnementale fédérale est requise pour le projet de centrale électrique Chinook, situé près de Swift Current, en Saskatchewan. En vue de prendre une décision éclairée, l'Agence invite le public à formuler des commentaires sur le projet et ses effets potentiels sur l'environnement, tels qu'ils sont ...

Document Summary of a Project Description of a Designated Project

  • Project Chinook Power Station Project
  • Document Category: For Public Participation
  • Reference Number: 3
  • Updated: 2016-10-05
  • Document: 115847E.pdf
  • Relevance: 213.07
  • The Chinook Power Station Project Project Summary Submitted to: The Canadian Environmental Assessment Agency Submitted by: Saskatchewan Power Corporation (SaskPower) October 2016 CHINOOK POWER STATION PROJECT Table of Contents 1.0 GENERAL INFORMATION AND CONTACTS ................................................................1.1 1.1 PROJECT’S NAME, NATURE AND PROPOSED LOCATION .......................................... 1.1 ...
1 alternate format found
French PDF
  • Relevance: 162.07
  • Projet de centrale électrique Chinook Résumé de projet Soumis à : L’Agence canadienne d’évaluation environnementale (ACEE) Par : La Saskatchewan Power Corporation (SaskPower) Octobre 2016 PROJET DE CENTRALE ÉLECTRIQUE CHINOOK Table des matières 1.0 INFORMATIONS GÉNÉRALES ET COORDONNÉES .......................................................1.1 1.1 NOM ET NATURE DU PROJET ET EMPLACEMENT PROPOSÉ POUR CELUI-CI ............ ...