Dredging at the Commercial Port of Cap-aux-Meules, Îles-de-la-Madeleine

Context

In fall 2024 and 2025, Transport Canada (TC) will continue the dredging work begun in 2020 at Cap-aux-Meules harbour. An environmental impact assessment (EIA) was carried out in 2020 for this project, and covered the dredging of approximately 55,000 m3 (68,700 m2) of sediment in place to reach depths of -7.1 m in the harbour and -6.5 m in the access channel.

Subsequently, three addendums to the EEE were issued for the following activities:

2021-2022: continuation of the 2020 work, with the addition of a new depth to be reached in the channel area, from -6.5 to -6.8 m (total area approx. 10,645 m2);
2022-2023: continuation of the 2021 work, with the addition of a new dredging zone at the fishermen's wharf (5,700 m2). There was also a new depth to be reached in the tanker dock area, from -6.5 to -7.5m (4,508 m2);
2023-2024: continuation of the work carried out in 2022, with the addition of dredging the rocky shoal in front of wharf no. 7 (20 m2) to reach a depth of -2.5m. The access channel was also dredged deeper, from -6.8 m to 7.1 m, and widened, corresponding to an additional 53,000 m2.


Work scheduled for 2024-2025

The areas and depths targeted by dredging work in 2024-2025 will be :

-4.7 m at Quai des Pêcheurs (3,200 m2);
-7 m in the harbor, near the breakwater (400 m2);
-7.1m in the harbor, near the access channel (2,000 m2);
-2.5 m for the rocky shoal in front of quay no. 7 (20 m2) - if not completed by October 24, 2024;
-7.5 m in the access channel (46,270m2 and 53,000 m2 expansion).
The work in the access channel involves a new depth to be reached, from -7.1 m to -7.5 m, and dredging in the event of silting.

The estimated volume to be dredged in 2024-2025 is 60,000 m3 of sediment in place. With regard to the rocky shoal in front of wharf no. 7, to comply with the various clauses of the disposal at sea permit, the contractor will have to crush the shoal with a jackhammer, remove the boulders from the water with his bucket and manage them on land. The seabed in this area will then have to be levelled using a steel beam, scraper blade or hydraulic shovel.

For the other areas, uncontaminated excavated sediments will be removed using a hydraulic shovel, a crane fitted with a half-shell bucket or a pump (hydraulic suction dredge) and disposed of at the PBCM-1 East disposal site (47, 36650°N, -61.79967°W NAD83), located 4.3 km southeast of Cap-aux-Meules harbour (47.37612ºN and -61.85292ºW NAD83).

Under section 82 of the Impact Assessment Act (IAA), DFO, ECCC and TC have a mandate to assess the impact of the project on the environment.

More


Latest update

June 25, 2024 - Transport Canada (TC), Fisheries and Oceans Canada (DFO) and Environment and Climate Change Canada (ECCC) intend to determine whether the project is likely to cause significant adverse environmental effects. In order to contribute to an informed determination, the authorities invite the public to comment on this determination until July 26, 2024.

Participate

Contacts

Environmental and Aboriginal affairs - Québec region
Email: aea-eaa@tc.gc.ca


  • Location

    • Port of Cap-aux-Meules (Quebec)
  • Nature of Activity

    • Ports and Harbours
  • Assessment Status

    In progress
  • Start Date

    2024-06-25
  • Proponent

    Transport Canada
  • Authorities

    • Environment and Climate Change Canada
    • Fisheries and Oceans Canada
    • Transport Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    88669
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: