Water Control Infrastructure and Dike Repair and Maintenance Part I - St. Clair National Wildlife Area
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Ducks Unlimited Canada (DUC) is proposing to undertake maintenance and repair activities to improve the dike infrastructure within the St. Clair National Wildlife Area, located in Pain Court, Ontario. These dikes are crucial to controlling the water levels within the National Wildlife Area. They also help mitigate the risk of flooding and improve wildlife habitat. Proper functioning of this infrastructure is necessary to ensure the effective management of the area for wildlife, their habitats, federal infrastructure, and public visitor access.
DUC will complete dike grading along approximately 2.8km of dyke top in the Bear Creek Unit and 4km in the St. Clair Unit. Using heavy machinery, ruts and holes will be filled in to create a more level dyke top. DUC will also use heavy machinery to repair and replace the existing pump station debris screens in the St. Clair Unit.
An inspection in 2022, determined the existing two pump stations were rusted and in need repair. The McFarlane Relief Drain Pump will have the existing screw gate repaired. The Lakeside Pump station will have both the debris screen and fence replaced. These works will be completed with the use of a cofferdam to isolate the work area. Turbidity curtains will be deployed to reduce sedimentation and section off the work area.
The proposed work will be completed during in the fall to winter within the Department of Fisheries and Oceans species at risk timing windows. Prior to any work commencing the areas will be searched by qualified individuals to remove any wildlife. Exposed soil and excavated material will be re-graded, stabilized and/or re-seeded using appropriate native plants, soils, seed mix and seed application at the completion of construction. Sediment and erosion control will be used where necessary.
Latest update
Participate
Key documents
| Document Number | Document Title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination | - | October 5, 2023 |
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | August 10, 2023 |
Contacts
Environment and Climate Change Canada, Canadian Wildlife ServiceJohn Viengkone, Protected Areas Officer - Ontario
4905 Dufferin St.
Toronto, Ontario M3H 5T4
Telephone: 416-884-5148
Email: john.viengkone@ec.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- St. Clair National Wildlife Area (Ontario)
-
Nature of Activity
- Water Management
- Maintenance activities (fences, walls)
-
Assessment Status
Completed -
Start Date
2023-08-10 -
Proponent
Ducks Unlimited Canada -
Authorities
- Environment and Climate Change Canada
-
Assessment Type
Project on federal lands -
Reference Number
85827
Nearby assessments
...within 200 kilometres-
Break Wall Section Replacement - St. Clair National Wildlife Area
St. Clair National Wildlife Area -
Water Control Infrastructure and Dike Repair and Maintenance Part II - St. Clair National Wildlife Area
St. Clair National Wildlife Area -
Full Restoration of Parking Garage Ramp and Repairs to Parking Structure
65 William Street, Chatham, Ontario -
New Fibre Installation
Walpole Island First Nation -
Squirrel Island Range Towers Replacement Project
Squirrel Island - Walpole First Nation Territory -
Replacement of Tecumseh Road Culvert
Wallaceburg -
Septic Tank Decommissioning
CBSA Walpole Island Ferry -
CBSA Walpole Island - New Building
Walpole Island -
Dresden Waste and Recycling Facility Project
Dresden -
Range and Training Area Upgrades – Canadian Armed Forces Training Area (CAFTA) Cedar Springs
Canadian Armed Forces Training Area (CAFTA) Cedar Springs -
Accommodations and Classroom Upgrades - Canadian Armed Forces Training Area (CAFTA) Cedar Springs
Canadian Armed Forces Training Area (CAFTA) Cedar Springs -
Totten Farm Access Road
1367 County Road 46, South Woodslee -
Wheatley Harbour Dredging Project - Winter 2020
Wheatley Harbour -
Wheatley Harbour Project
Wheatley Harbour -
Wheatley Harbour Maintenance Dredging - 2020-2021
Wheatley Harbour -
Caldwell First Nation - Subdivision Development
Caldwell First Nation -
Natural infrastructure for Caldwell First Nation
Caldwell First Nation - Leamington -
Rondeau Jetty Refurbishment 2021
Erieau, ON -
Rondeau Jetty 5 Rehabilitation
Rondeau Harbour, Erieau -
Vegetation Maintenance at Point Pelee National Park
Point Pelee National Park -
Sewage Treatment System Replacements and Upgrades at Point Pelee National Park
Point Pelee National Park -
Decommissioning of the Power Corridor at Point Pelee National Park
Point Pelee National Park -
Deer Herd Reduction, Point Pelee National Park
Point Pelee National Park -
Point Pelee Marsh Restoration Project
Detailed Impact Assessment, Point Pelee National Park -
Boat Lift Replacement - GOC6384448
6080 Riverside Drive E, Windsor ON -
Repair Retaining Wall - GOC3450716
6080 Riverside Drive E, Windsor ON -
Hydrogen Ready Power Plant Project
Courtright -
Green Electron Natural Gas Power Generation Project
St. Clair Township -
Madbin Jina Picnic Shelter Replacement and Gate Installation
Point Pelee National Park of Canada -
Parking Lot Re-pavement at Mail Processing Plant (MPP) Windsor, ON
4255 Walker Road, Windsor, Ontario -
Riverside Generating Station Project
St. Clair Township -
Septic Tank Decommissioning
Point Pelee National Park of Canada -
Cedar Beach Minor Dredging
Cedar Beach, ON -
Cedar Beach - Fixed Dock Demolition
Cedar Beach -
Ambassador Bridge Enhancement Project
Windsor -
HMCS Hunter Embankment Erosion Repair
HMCS Hunter, 90 Mill Street in Windsor -
Sterling Fuels Windsor - upgrades to facilities and operations
3600 Russell Street, Windsor -
J5D OPGW Upgrade Project
Windsor -
J5D OPGW Upgrade Project
Windsor -
Colchester Harbour Maintenance Dredging Project 2021
Colchester Harbour -
Vidal Street South Area Watermain Replacement
Sarnia -
Pelee Island Harbour Dock Replacement
Pelee Island Small Craft Harbour -
Alma Street Parkette Shoreline Protections
Town of Amherstburg -
Canadian Coast Guard Amhersburg Base Wharf Repair Project
Amherstburg -
Electrical and Exterior Lighting Upgrades Project at Canadian Coast Guard Base Amherstburg
Canadian Coast Guard Base, 370 Dalhousie Street, Amherstburg, Ontario, N9V 1X3 -
Boblo Island Ferry Dock Demolition
Amherstburg -
Oneida of the Thames Water System Upgrades
Oneida of the Thames First Nation -
Oneida Language Survivance
Southwold -
Installation of Temporary Housing at Stony Point (Former Camp Ipperwash), Ontario
Stony Point is located at 9356 Army Camp Road within the municipality of Lambton Shores -
Building Demolitions and Associated Soil Remediation at Stony Point (former Camp Ipperwash), Ontario
Stony Point is located at 9356 Army Camp Road within the municipality of Lambton Shores, in southwestern Ontario -
Decommission Small Arms Range Target and Remediation of Contaminated Soils - Stony Point (Former Camp Ipperwash), Ontario
Stony Point (Former Camp Ipperwash) -
Foundation Demolition and Associated Soil Remediation at Stony Point (former Camp Ipperwash), Ontario
Stony Point is located at 9356 Army Camp Road within the municipality of Lambton Shores. -
Infrastructure Removal and Soil Remediation - Stony Point (Former Camp Ipperwash), Ontario
Stony Point (Former Camp Ipperwash -
Ammo Compound Demolition at Stony Point (former Camp Ipperwash), Ontario
9356 Army Camp Road within the municipality of Lambton Shores, in southwestern Ontario. -
Courtyard Pavement Refurbishment and Sealing of the Underground Roof Garage
451 Talbot Street, London, Ontario -
Municipality of Lambton Shores Fuel System Replacement at Grand Bend
Grand Bend Small Craft Harbour (Ontario) -
Grand Bend Harbour Dredging - Spring 2021
Grand Bend Harbour -
Grand Bend Harbour Underground Storage Tank Removal
Grand Bend -
Port Burwell Maintenance Dredging
Lake Erie, Port Burwell, Ontario -
Port Burwell Marina Floating Docks
Port Burwell, ON -
Municipality of Bluewater Storage Tank System Replacement
Bayfield Small Craft Harbour -
Bayfield Harbour - North and South Pier Minor Works and Shore Protection
Bayfield Harbour -
Bayfield Annual Dredge Project
Bayfield -
Replacement of Big Creek Bridge on Long Point Causeway
Replacement of Big Creek Bridge on Long Point Causeway -
Installation of Boundary Fencing - Big Creek National Wildlife Area
Big Creek National Wildlife Area -
Water Control Infrastructure and Dike Repair and Maintenance Part II - Big Creek National Wildlife Area
Big Creek National Wildlife Area -
Water Control Infrastructure and Dike Repair and Maintenance - Big Creek National Wildlife Area
Big Creek National Wildlife Area -
Goderich Search and Rescue Station Fuel Tank Replacement
Goderich Search and Rescue Station -
Street work and Stormwater Outfall Improvements, Port Dover, Ontario
Port Dover -
Port Dover Search and Rescue Station Floating Dock Repairs
Port Dover -
Demolition of Structures, Minor Construction and Removal of Debris - Long Point National Wildlife Area
Long Point National Wildlife Area -
Lighting and Pathway Upgrades
Woodside National Historic Site