Suncor Base Mine Extension Project

Suncor Energy Inc. is proposing to develop the Base Mine Extension Project to sustain the supply of bitumen to the existing upgraders at Suncor's Oil Sands Base Plant operation (Base Plant). The project includes an open-pit mining operation and associated infrastructure to supply bitumen to new froth production facilities and various other production facilities at the existing Base Plant. The project is located adjacent to existing Base Plant operations approximately three kilometres north of Fort McMurray, Alberta, within the Regional Municipality of Wood Buffalo. Project construction is expected to start in 2026 and its footprint is anticipated to be approximately 30 000 hectares.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Latest update

February 26, 2021 — The Impact Assessment Agency of Canada is inviting public comments until April 7, 2021, on the draft Tailored Impact Statement Guidelines and Public Participation Plan for the preparation of the Final Impact Statement Guidelines. These documents specify what should be examined during the impact assessment. The Agency has also resumed the timeline for the Impact Assessment.

 

January 28, 2021 — The Minister of Environment and Climate Change has referred the impact assessment to a review panel.

Participate

Key documents

Key documents
Document Number Document Title File Date
83 Draft Indigenous Engagement and Partnership Plan PDF (965 KB) February 26, 2021
82 Draft Permitting Plan PDF (763 KB) February 26, 2021
81 Notice of Time Limit Resuming - February 26, 2021
79 Draft Public Participation Plan PDF (702 KB) February 26, 2021
78 Draft Tailored Impact Statement Guidelines PDF (1.9 MB) February 26, 2021
70 Public Notice - Suncor Base Mine Extension Project - Comment Period on the Draft Tailored Impact Statement Guidelines and Draft Public Participation Plan - February 26, 2021
75 Notice of Referral to Review Panel - January 28, 2021
72 Notice of Time Limit Suspension with Reasons - September 18, 2020
66 Notice of Impact Assessment Decision with Reasons - August 7, 2020
65 Summary of the Detailed Project Description of a Designated Project PDF (2 MB) July 23, 2020
64 Detailed Project Description of a Designated Project and Responses to Summary of Issues PDF (6.9 MB) July 23, 2020
54 Summary of Issues PDF (142 KB) May 11, 2020
31 Notice of Time Limit Resumption - May 4, 2020
20 Notice of Time Limit Suspension with Reasons - March 30, 2020
24 From Suncor Energy Inc. Base Mine Extension project to the Impact Assessment Agency of Canada re: Timeline Change - Planning Phase PDF (89 KB) March 19, 2020
4 Initial Project Description (updated) PDF (2.8 MB) March 2, 2020
3 Summary of an Initial Project Description (updated) PDF (1.6 MB) March 2, 2020

List all records

Contacts

Suncor Base Mine Extension Project