Development of 10 Lot Residential Subdivision on Eabametoong First Nation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Proposed Project
Eabametoong First Nation is proposing the construction of a small subdivision (1200 m2) consisting of 10 lots for the eventual construction of 10 residential houses. Project activities include:
Road Construction
- Clearing, grubbing and leveling of road section;
- Road will be 200 m long and 8 m wide and built in accordance with MTO standards;
- 4:1 side slope with a minimum 0.75 m deep ditch with 3:1 ditch back slope; And
- Site drainage and water diversion, and installation of new culverts along the road section.
Lot Development and Servicing
- Clearing, grubbing and peat removal along the road right-of-way;
- Construction of driveways for individual lots; And
- Installation of water and sewer lines that will terminate 5 m past the front property line.
Water Main Distribution Extension
- Installation of PVC watermain along the proposed subdivision, connecting the existing mainline; And
- Fire hydrants to be installed at 150 m intervals along the proposed water main.
Wastewater Collection Extension
- Installation of PVC sanitary main along the proposed subdivision for a gravity sewage system.
Hydro Extension
- Extension of overhead transmission lines to future residential homes.
The construction of this subdivision will help alleviate some of the housing needs of the community that is currently experiencing a crisis due to the lack of suitable housing available to accommodate the community's growing population.
Latest update
End of Public Comment Period
October 20, 2024 – The public period on the project is closed. Indigenous Services Canada is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.
Participate
Contacts
Indigenous Services CanadaHannah Silvaggio, Environment Officer
100 Anemki Place, Suite 101
Fort William First Nation, Ontario P7J 1A5
Telephone: 807-624-5921
Email: hannah.silvaggio@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Eabametoong First Nation (Ontario)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
In progress -
Start Date
2024-09-21 -
Proponent
Eabametoong First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
88927
Nearby assessments
...within 200 kilometres-
East End Subdivision Development - Eabametoong First Nation
Eabametoong First Nation -
Replacement of Bridge for Winter Road Crossing - Eabametoong First Nation
Eabametoong First Nation -
Neskantaga Community Recreation Centre
Neskantaga First Nation Reserve -
Neskantaga First Nation New Construction of an 8-plex teachers residence
Neskantaga First Nation -
Northern Road Link Project
150km north of the Municipality of Greenstone -
Marten Falls Community Access Road Project
Northern end of Painter Lake forestry road -
Electrical Distribution System Upgrades - Marten Falls First Nation
Marten Falls First Nation -
Winter Road Bridge Crossing Construction on Nibinamik First Nation
Nibinamik First Nation -
Marten Falls Community Access Road Project
Marten Falls -
Regional Assessment in the Ring of Fire Area
Ring of Fire -
Webequie Supply Road Project
Webequie First Nation - Western limit -
Whitesand First Nation - Lot Servicing Project
Whitesand First Nation -
New Fibre Installation
Project Site 3 -
Stormwater Management (SWM) Infrastructure Remediation
Armstrong -
Whitesand Elder's Unit (6-Plex)
Whitesand First Nation -
The Elders Lodge at Aroland First Nation
Aroland Elder's Lodge -
Webequie First Nation - Nursing Station Bulk Fuel Storage Upgrades
Webequie First Nation -
New Osnaburgh Water Treatment Plant Upgrades
New Osnaburgh -
New Fibre Installation
Project Site 5 -
Mishkeegogamang Ojibway Nation Broadband Tower Construction
203 Mishkeegogamang -
Sachigo Lake First Nation Water Treatment Project
Sachigo Lake First Nation -
Eagle's Nest Project
Ring of Fire -
Northern Road Link Project
McFaulds Lake area - Northern Limit -
Eagle's Nest Mine Project
Ring of Fire -
Webequie Supply Road Project
McFaulds Lake area - Eastern limit -
Wunnumin H1RCI Compound Construction
Wunnumin Lake -
Cliffs Chromite Project
McFaulds Lake -
Wunnumin Lake First Nation Teacherages Project
Wunnumin Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Sandy Lake PoP -
New Fibre Installation
Project Site 4 -
New Fibre Installation / Upgrade Multiple Towers
Bearskin Lake PoP -
New Fibre Installation / Upgrade Multiple Towers
Slate Falls PoP