Kingfisher Lake First Nation K4-10 School
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The project includes the development of a 4.8 ha greenfield site for a new school, located on the north side of
Church Road (also known as "Airport Road") approximately 300 m west of the main community townsite. The
project includes the construction of a new K4-10 school building (2,446 m2), gravel parking lot (25 stall) and bus loop
drop off, outdoor play area and play structure, volleyball court, heated warehouse, and baseball diamond/soccer
field (Appendix A, Figure 2). The project includes site development (clearing, grubbing, grading, and landscaping)
along with site servicing including power, telecommunications, water, and wastewater services (see Infrastructure
Section below).
Directly across Church Road from the new school site, will be the site for the development of 6 teacherage buildings
(875 m2 total) in a new greenfield area (Appendix A, Figure 2) including duplexes and bungalows, gravel parking
areas, and access road. The teacherage units will be serviced by the same infrastructure as the school building (see
below).
References:
Architecture 49. 2019. Kingfisher Lake First Nation School Pre-Design Study. Final Report. Winnipeg, MB.
INAC (Indigenous and Northern Relations Canada). 2019. First Nation Profiles: Kingfisher. Available online at:
https://fnp-ppn.aadnc-aandc.gc.ca/fnp/Main/Search/FNRegPopulation.aspx?BAND_NUMBER=212&lang=eng.
[accessed April 20, 2021].
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination for the Kingfisher Lake First Nation K4-10 School | - | July 11, 2021 |
1 | Kingfisher Lake First Nation K4-10 School | - | June 7, 2021 |
Contacts
Indigenous Services CanadaAaron Pervais, Environmental Officer
Indigenous and Northern Affairs Canada 100 Anemki Place Suite 101 Fort William First Nation
Thunder Bay, Ontario P7J 1A5
Telephone: 807-624-5921
Email: aaron.pervais2@canada.ca
-
Location
- Kingfisher Lake First Nation/Reserve No. 1 (Ontario)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
Completed -
Start Date
2021-06-06 -
Proponent
Kingfisher Lake First Nation/Reserve No. 1 -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81679