Canada Nickel Company is proposing the construction, operation, decommissioning and abandonment of an open-pit nickel-cobalt mine and on-site metal mill, located 43 kilometres north of Timmins, Ontario. As proposed, the Crawford Nickel Project would have a mine ore production capacity of 275,000 tonnes per day and a mill ore input capacity of 120,000 tonnes per day. The project would operate for about 43 years.


Latest update

June 27, 2024 — The Impact Assessment Agency of Canada is making funding available to support the participation of Indigenous Peoples and the public in the impact assessment for this project. Applications received by July 29, 2024 will be considered.

At a glance

Planning

Planning

Completed 179/180 days

Key documents

Impact Statement

Impact Statement

In progress 451/1095 days

Key documents

Impact Assessment

Impact Assessment

Not started 0/300 days
Decision Making

Date of decision

Anticipated on November 17, 2025

Decision Making

Not started 0/30 days
Post Decision

Post Decision phase is an ongoing process

If approved, the project may proceed to construction as federal authorizations and permits are issued, and as conditions and other requirements are met.

Post Decision

Not started

Participate

Contacts

Crawford Nickel Project
Impact Assessment Agency of Canada
600-55 York Street
Toronto, Ontario M5J 1R7
Telephone: 416-952-1576
Email: Crawford@iaac-aeic.gc.ca


  • Location

    • 43 km north of Timmins (Ontario)
  • Nature of Activity

    • Mines and Minerals
  • Assessment Status

    In progress
  • Start Date

    2022-08-08
  • Proponent

    Canada Nickel Company
  • Authorities

    • Impact Assessment Agency of Canada
  • Assessment Type

    Impact Assessment by the Agency
  • Reference Number

    83857