Moose Cree Sewage System Rehabilitation

Construct a lined sludge dewatering area to the west of the existing lagoon cells, remove sludge from the 3 existing sewage lagoon cells and place sludge in the dewatering area, upgrade the existing sewage lagoon by installing a new aeration system in all 3 cells, construction of Submerged Attached Growth Reactor (SAGR) cells to the east for additional sewage treatment, investigation of the inflow and infiltration in the gravity sewer collection system.


Latest update

Notice of Determination

2021-10-26 –  Infrastructure Canada issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination: Moose Cree Sewage System Rehabilitation - October 26, 2021

Contacts

Aboriginal Consultation and Environmental Services
1100 - 180 Kent St
Ottawa, Ontario K1P 0B6
Email: infc.aboriginalconsultenv-consultautochtonesenv.infc@canada.ca

Infrastructure Canada
Meng Koh, Senior Environmental Review and Approvals Officer
180 Kent Street
Ottawa, Ontario K1P 0B6
Telephone: 343-551-0418
Email: meng.koh@infc.gc.ca


  • Location

    • Moose Cree First Nation (Ontario)
  • Nature of Activity

    • Water Management
  • Assessment Status

    Completed
  • Start Date

    2021-05-07
  • Proponent

    Moose Cree First Nation
  • Authorities

    • Indigenous Services Canada
    • Infrastructure Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    81610