Northern Pulp Project

Registry Search Mobile

Registry Search

Skip to Filters

10 results

Document Analysis Report

  • Project Northern Pulp Project
  • Document Category: Additional Information
  • Reference Number: 5
  • Updated: 2022-06-10
  • Document: 144093E.pdf
  • Relevance: 335.37
  • Analysis Report WHETHER TO DESIGNATE THE NORTHERN PULP PROJECT IN NOVA SCOTIA PURSUANT TO THE IMPACT ASSESSMENT ACT MAY 2022 IMPACT ASSESSMENT AG ENCY OF CANADA ANALYSIS REPORT i Contents Analysis Report ....................................................................................................... 1 Purpose ...
1 alternate format found
French PDF
  • Relevance: 284.37
  • Rapport d’analyse QUANT À LA DÉSIGNATION OU NON DU PROJET DE NORTHERN PULP EN NOUVELLE-ÉCOSSE CONFORMÉMENT À LA LOI SUR L’ÉVALUATION D’IMPACT MAI 2022 AGENCE D’ÉVALUATION D’ IMPACT DU CANADA RAPPORT D’ANALYSE i Table des matières Rapport d’analyse ................................................................................................... 1 Objet 2 Projet ...

Document Minister's Response

  • Project Northern Pulp Project
  • Document Category: Additional Information
  • Reference Number: 6
  • Updated: 2022-06-10
  • Document: 144094E.html
  • Relevance: 335.37
  • Minister's Response on the Designation Request for the Northern Pulp Project Project Northern Pulp Nova Scotia Corporation is proposing the modernization of its current bleached kraft pulp mill and the construction, operation, and decommissioning of a new effluent treatment facility adjacent to its pulp mill, located at Abercrombie Point near Pictou, Nova Scotia. Treated effluent would be discharged through a new pipeline extending into Pictou Harbour. Decision Non-designated ...
1 alternate format found
French HTML
  • Relevance: 284.37
  • Réponse du ministre concernant la demande de désignation du projet Northern Pulp Projet Northern Pulp Nova Scotia Corporation propose la modernisation de son usine de pâte kraft blanchie, ainsi que la construction, l'exploitation et la désaffectation d'une nouvelle installation de traitement des effluents contiguë à son usine, située à Abercrombie Point, près de Pictou (Nouvelle-Écosse). L'effluent traité serait déchargé par une nouvelle canalisation s'étendant jusqu'au port de ...

Document Notice of Time Limit Resumption

  • Project Northern Pulp Project
  • Document Category: Additional Information
  • Reference Number: 4
  • Updated: 2022-04-21
  • Document: 143652E.html
  • Relevance: 330.91
  • Notice of Time Limit Resumption Ottawa — On April 14, 2022, Northern Pulp Nova Scotia Corporation (the proponent) addressed the information request from the Agency in relation to the Northern Pulp Project. The proponent thereby completed the activity for which it requested the time limit be suspended and the 90-day time limit has resumed. The 90-day time limit is the period of time within which the Minister must respond, with reasons, to a request to designate a physical activity. For ...
1 alternate format found
French HTML
  • Relevance: 279.91
  • Avis de reprise du délai Ottawa — Le 14 avril 2022, Northern Pulp Nova Scotia Corporation (le promoteur) a fourni à l'Agence les renseignements demandés relativement au projet Northern Pulp. Le promoteur a ainsi terminé l'activité pour laquelle la suspension du délai a été demandé, et le délai de 90 jours a repris son cours. Le délai de 90 jours est la période au cours de laquelle le ministre doit répondre, motifs à l'appui, à la demande de désignation de l'activité concrète. Pour obtenir ...

Document Notice Time Limit Suspension with Reasons

  • Project Northern Pulp Project
  • Document Category: Additional Information
  • Reference Number: 3
  • Updated: 2022-04-01
  • Document: 143434E.html
  • Relevance: 329.15
  • Notice of Time Limit Suspension with Reasons Ottawa — April 1, 2022 — The Impact Assessment Agency of Canada (the Agency) has suspended the 90-day time limit within which the Minister must respond, with reasons, to the request for designation of the Northern Pulp Project, proposed by Northern Pulp Nova Scotia Corporation (the proponent). The Agency has taken this action further to a written request from the proponent that the time limit be suspended in order that the proponent have ...
1 alternate format found
French HTML
  • Relevance: 278.15
  • Avis de suspension du délai avec motifs Ottawa — 1er avril 2022 — L'Agence d'évaluation d'impact du Canada (l'Agence) a suspendu le délai de 90 jours au cours duquel le ministre doit répondre, motifs à l'appui, à la demande de désignation du projet Northern Pulp proposé par Northern Pulp Nova Scotia Corporation (le promoteur). Cet avis fait suite à la présentation par le promoteur d'une demande écrite (en anglais seulement) de suspendre le délai afin que le promoteur puisse bénéficier de ...

Refine SearchDisplay Filters

Last UpdatedDisplay Filters

Filters

Result Type Display Filters

Document Category Display Filters

Date modified: