New Fibre Installation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The project involves the installation of approximately 150 km of aerial fiber optic cable from the Fort McKay point of presence located at latitude 57.17935 and longitude-111.63689, the fibre will be deployed along the local roads of the Fort McKay First Nation. In addition, the fibre will be deployed along Highway 881 through Gregoire Lake 176A and 176. In Janvier, the fibre will be deployed from point of presence located at latitude 55.92592 and longitude -110.7304 throughout the community's local roads.
Latest update
April 22, 2024 - Innovation, Science and Economic Development Canada has determined that the proposed project is not likely to cause significant adverse environmental effects.
This determination was based on a consideration of the following factors:
- relevant potential environmental effects;
- comments received from the public; and
- technically and economically feasible mitigation measures.
Mitigation and monitoring measures taken into account for this determination included active and adaptive management measures that would be implemented for the protection of the local environment. Based on the consideration of these measures, Innovation, Science and Economic Development Canada is satisfied that that the carrying out of the project is not likely to cause significant adverse environmental effects.
Therefore, Innovation, Science and Economic Development Canada may carry out the project, exercise any power, perform any duty or function, or provide financial assistance to enable the project to be carried out in whole or in part.
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination | - | April 22, 2024 |
1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | March 22, 2024 |
Contacts
Innovation Science and Economic Development CanadaHassan Dahrouj, Technical Officer, Connected Canada Branch
235 Queen Street
1st Floor West Tower, CD Howe Building
Ottawa, Ontario K1A 0H5
Email: Get-connected-brachez-vous@ised-isde.gc.ca
-
Location
- Project site 1: Regional Municipality of Wood Buffalo (Alberta)
- Project site 2: Regional Municipality of Wood Buffalo (Alberta)
- Project site 3: Regional Municipality of Wood Buffalo (Alberta)
- Project site 4: Regional Municipality of Wood Buffalo (Alberta)
-
Nature of Activity
- Other, not otherwise specified
-
Assessment Status
Completed -
Start Date
2024-03-22 -
Proponent
TELUS COMMUNICATIONS INCORPORATED -
Authorities
- Innovation, Science and Economic Development
-
Assessment Type
Project on federal lands -
Reference Number
87429
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
ATCO Gas and Pipelines: 1091764 North Janvier Natural Gas Delivery Pipeline Upgrade Project
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation 2021 Subdivision Project (Phase 1)
Chipewyan Prairie First Nation -
Janvier Secondary Egress Road
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation Housing Project 2020-21 (5 Units)
Chipewyan Prairie First Nation -
Chipewyan Prairie First Nation Wastewater Treatment Plant Expansion
Chipewyan Prairie First Nation -
Fort McMurray First Nation Water and Wastewater Infrastructure
Fort McMurray First Nation -
ATCO Gas and Pipelines Ltd.: 1088748 Gregoire Lake IR No. 176A Lakeshore Drive Gas Distribution System Extension
Fort McMurray First Nation -
Fort McMurray First Nation: Gregoire Lake Water and Sewage Project
Gregoire Lake -
2017 NGTL System Expansion Project
Fort McMurray -
Clearwater Multi-User Access Project, Alberta
Clearwater River -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CLEARWATER RIVER DENE BAND NO. 222 (Tower 2) -
Clearwater River Dene Subdivision
Clearwater River Dene IR 122 -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
06-09-069-04W4 -
Canadian Natural Resources Limited - New radiocommunications towers on 06-09-069-04W4 and 11-04-069-04W4, Cold Lake Air Weapons Range, AB
11-04-069-04W4 -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P162 - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
CNRL proposal to install two new radiocommunications towers on Beaver Lake Cree Nation within the boundary of the Cold Lake Air Weapons range.
P71C - Beaver Lake Cree Nation/Cold Lake Air Weapons Range -
Canadian Natural Resources Limited - New radiocommunications tower on NW 34-68-4 W4M, Cold Lake Air Weapons Range, AB
NW 34-68-4 W4M. , Cold Lake Air Weapons Range, AB -
New Fibre Installation
Project Site 1 - Heart Lake: -
Heart Lake First Nation: Inter-jurisdictional Access Road
Heart Lake First Nation #167 -
Heart Lake First Nation: CU370 Wastewater System Emergency Repairs
Heart Lake First Nation -
New Fibre Installation
Project Site 2 - Heart Lake: -
Heart Lake BF 80752 Bridge Replacement
Heart Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 1) -
Fixed Point-to-Point Link from Buffalo Narrows, SK to Dillon, SK
Buffalo River Dene Nation I.R. 193 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
BUFFALO RIVER DENE NATION I.R. 193 (Tower 2) -
Buffalo River Dene Nation Solid Waste Transfer Station
BUFFALO RIVER DENE NATION RESERVE #193 -
Buffalo River Dene Nation Subdivision Stage 4
Buffalo River Dene Nation IR 193 -
Sundog Renewable Generating Station Project
130 kilometres upstream of Fort McMurray -
Pelican Renewable Generating Station Project
180 kilometres upstream of Fort McMurray -
Suncor Base Mine Extension Project
3 kilometres north of Fort McMurray -
Suncor Energy Coke Fired Boiler Replacement Project
25 kilometres north of Fort McMurray -
Cold Lake Air Weapons Range (CLAWR) Culvert Replacement
4 Wing Cold Lake -
Replacement of Water Crossing and Road Alignment
Primrose Lake Evaluation Range -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 2) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 1) -
Birch Narrows Dene Nation Community Centre
Birch Narrows Dene Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
TURNOR LAKE I.R. 193B (Tower 3) -
Marguerite Lake Compressed Air Energy Storage Project
La Corey -
Fort McKay First Nation: 2023/24 Residential Redevelopment Project
Fort McKay First Nation -
Fort McKay First Nation K-9 School
Fort McKay First Nation -
Beaver Lake Cenovus Housing Initiative - Build Out of 20 Residential Lots, Access Roads, and Water Distribution
Beaver Lake Cree Nation -
Cold Lake First Nation Water System Upgrades
Cold Lake First Nation -
Beaver Lake New School
Beaver Lake Cree Nation -
Beaver Lake Cree Nation Fiber Optic Internet Infrastructure - Universal Broadband Fund Project
Beaver Lake Cree Nation -
Beaver Lake Cree Nation New High School and Resource Centre
Beaver Lake Cree Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 3: Cold Lake -
Cold Lake First Nation: CUZD3 Phase II and III Water Distribution System
Cold Lake First Nation -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Jackpine Mine Expansion Project
Fort McKay -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 2: Cold Lake -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Cold Lake -
Campus Energy - Pipeline Replacement/Removal
4 Wing Cold Lake -
ATCO Gas and Pipelines Ltd.: 1098480 Wabasca IR No. 166 Phase 2 Alfred Road Gas Main & Distribution System
Bigstone Cree Nation -
Building Demolition - 4 Wing Cold Lake
Cold Lake -
21M Range Revitalization (CL220020) - 4 Wing Cold Lake
4 Wing Cold Lake -
Renovation of Building 325 - Pumphouse & Water Purification Plant (CL210010) - 4 Wing Cold Lake
4 Wing Cold Lake -
Demolition of Barrack Block 48 - 4 Wing Cold Lake
4 Wing Cold Lake -
Replacement of Collapsed Storm Sewer Lines - 4 Wing Cold Lake
4 Wing Cold Lake -
Maintenance, Repair, and Installation Work for Storage Tank Systems - Cold Lake Air Weapons Range and 4 Wing Cold Lake
Cold Lake Air Weapons Range and 4 Wing Cold Lake -
Building Demolition and Underground Fuel Line Removal - 4 Wing Cold Lake
4 Wing Cold Lake -
New Fibre Installation
Project Site 5 - Wabasca No. 166: -
Department of National Defence Future Fighter Capability Project - Demolition of Hangars 6 and 7, and Construction of New Supporting Infrastructure
4 Wing Cold Lake, approximately 300 kilometers northeast of Edmonton -
Cold Lake First Nation Housing Project 2019 (10 Unit Renovation)
Cold Lake First Nation -
ATCO Gas and Pipelines Ltd.: 1088866 Bigstone Cree Nation & Hamlet of Sandy Lake Gas Feeder and Mains at Wabasca IR No. 166
Bigstone Cree Nation -
Cold Lake First Nations: Casino Dene Expansion, Event Centre, Parking Project
Cold Lake First Nations -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 1: Cold Lake -
Cold Lake First Nation Subdivision Project
Cold Lake First Nation -
Cold Lake First Nation: CUZ46 Wastewater System Expansion
Cold Lake First Nation -
Cold Lake Budget 2018 Year Three Housing Project 2020 (6 Units)
Cold Lake First Nation -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 4: Cold Lake -
Cold Lake First Nation - Frog Lake Regional Water Tie-In
Cold Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 1) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 2) -
Powwow Arbour Construction
Pierceland -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
New Tower 1: Cold Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
CANOE LAKE I.R. 165 (Tower 3) -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 2) -
ATCO Gas and Pipelines Ltd.: 1088866 Wabasca IR No. 166A Gas Distribution Extension
Bigstone Cree Nation Wabasca IR No. 166A -
Wapachewunak Water Treatment Plant Optimization
Wapachewunak IR 192D -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 2: Cold Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WAPACHEWUNAK I.R. 192D (Tower 1) -
Cold Lake First Nations LTE Fixed Wireless Upgrade Project
Existing Tower 5: Cold Lake -
Bigstone Cree Nation Oilfield Supply Store
Wabasca #166 -
Bigstone Cree Nation Education Authority: CU254 Oksi Pasikoniwew Kakik School Secondary Access Road Project
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-10 TSAG ID No. 07 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation New High School
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-17 TSAG ID No. 03 Replacement
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-18 TSAG ID No. 04 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 1 - Bigstone Cree Nation: -
Whitefish Lake First Nation #128 Waste Transfer Station
Whitefish Lake First Nation #128 -
Bigstone Cree Nation High School Waterline Project
Wabasca -
Bigstone B.O.S.S Modular Construction and Fabrication Yard Expansion Project
Bigstone Cree Nation -
Pierre River Mine Project
Fort McKay -
Weepuskow Sahgaiechan IR 165D Timber Harvest Plan 2020-21
WEPUSKOW SAHGAIECHAN IR 165 D -
New Fibre Installation
Project Site 3 - Wabasca No. 166C: -
OS-7241 Wabasca IR 166D | Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell pad
Wabasca IR # 116D -
Wabasca Water Treatment Plant Upgrades Project
Wabasca -
New Fibre Installation
Project Site 2 - Wabasca No. 166B : -
Bigstone Cree Nation Flood Recovery Program: Culvert 166D-27 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 4 - Wabasca No. 166D: -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166D-08 TSAG ID No. 08 Replacement
Bigstone Cree Nation -
Frontier Oil Sands Mine Project
Fort McKay -
Patterson Lake South Mine Project
Patterson Lake -
Rook I Project
Patterson Lake -
Rogers Communications Inc., new radiocommunications tower (W6238) on Peerless Trout First Nation land, near Trout Lake, AB.
W6238 - Peerless Trout First Nation Land (near Trout Lake) -
Rogers Communications Inc., new radiocommunications tower (W6225) on Peerless Trout First Nation land, near Peerless Lake, AB.
W6225 - Peerless Trout First Nation Land (near Peerless Lake) -
North Corridor Expansion Project
Peerless Lake -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Peace-Athabasca Delta Field Station
Detailed Impact Assessment, Wood Buffalo National Park -
Establish Water Survey of Canada river depth station on north branch of Quatre Fourches
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Winter Road creation, maintenance, and breakdown
Wood Buffalo National Park