Generator and Storage Tank Replacement

This project involves the replacement of 4 Storage tanks and 2 generators (diesel), as well as all associated piping, that make up an EC registered storage tank system at the Little Gold Border Crossing:

Two (2) prime diesel generators and associated power electronics

Two (2) day storage tanks (located inside in the utility building, serving generators, and a fire pump) One (1) day tank (located exterior east side of customs building, for heating)

One (1) main storage tank 20,000 L.

The three day tanks are to be replaced with like-for-like capacity tanks. The main storage tank will be replaced with a slightly larger tank (25,000L) that will be seismically restrained on a new concrete housekeeping pad, in the same location as the previous tank. The new portable generators will be installed outside on a new housekeeping pad, east of the utility building.

The system is all above ground - no subsurface material expected to be disturbed. Design and Installation will adhere to all applicable codes, standards and Federal legislation.

More


Latest update

Physical work on this project is set to begin in May 2026.

Participate

Contacts

CBSA Environmental Operations
Canada Border Services Agency
Hayley Buchanan, Manager of Compliance
355 North River Road
Tower B, Floor 19
Ottawa, Ontario K1A 0L8
Telephone: 343-291-5284
Email: Hayley.Buchanan@cbsa-asfc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Little Gold Port of Entry (Yukon)
  • Nature of Activity

    • Other, not otherwise specified
  • Assessment Status

    In progress
  • Start Date

    2025-04-01
  • Proponent

    Canada Border Services Agency
  • Authorities

    • Canada Border Services Agency
  • Assessment Type

    Project on federal lands
  • Reference Number

    89983

Nearby assessments

...within 200 kilometres
Date modified: