Attachment Health Canada Response - Comments on the Initial Project Description for the Riverside Power Generating Station Project / Réponse de Santé Canada - Commentaires sur la Description initiale de projet pour le projet de centrale Riverside

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Health Canada
  • Reference number: 33
  • Submitted: 2025-11-03 - 1:21 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • See the attached submission / Veuillez consulter la pièce jointe  
  • Attachment included
  • Page 3 of 8 Environmental Health Program (EHP) Regulatory Operations & Enforcement Branch (ROEB) Health Canada 180 Queen Street West, 10th Floor Toronto, ON M5V 3L7 October 6, 2025 Anna Vypovska Project Manager, Prairie and Northern Region Impact Assessment Agency of Canada Anna.Vypovska@iaac-aeic.gc.ca Sent by email to: Riverside@iaac-aeic.gc.ca Subject: Health Canada’s Comments on the Initial Project Description for the Riverside Power Generating Station Project Dear Anna Vypovska, Thank you for your email dated September 15, 2025, requesting Health Canada’s comments on the Initial Project Description (IPD) for the Riverside Power Generating Station Project (the Project). Health Canada participates in the impact assessment process as a federal authority under the Impact Assessment Act (IAA). Health Canada makes available specialist/expert information or knowledge in its possession to reviewing bodies under the IAA, upon request. Health Canada does not make decisions or issue licenses, permits, or authorizations in relation to the impact assessment of a development project. Health Canada has reviewed the IPD and provided advice in the Attachment (Federal Authority Advice Record or FAAR form). The following highlights the department’s key comment pertaining to potential non-negligible adverse effects on the health of Indigenous Peoples: • In the absence of comprehensive information on all potential air emissions associated with the Project, their exposure levels at Indigenous receptor locations, and the effectiveness of proposed mitigation ...
  • Attachment included
  • Page 1 of 8 Programme de santé environnementale (PSE) Direction générale des opérations réglementaires et de l’application de la loi (DGORAL) Santé Canada 180 rue Queen ouest, 10e étage Toronto, ON M5V 3L7 Le 6 octobre, 2025 Anna Vypovska Gestionnaire de projets, bureau régional des Prairies et du Nord Agence d'évaluation d’impact du Canada Anna.Vypovska@iaac-aeic.gc.ca Envoyé courriel à : Riverside@iaac-aeic.gc.ca Objet: Commentaires de Santé Canada sur la Description initiale de projet pour le projet de centrale Riverside Chère Anna Vypovska, Nous vous remercions de votre courriel daté du 15 septembre 2025, sollicitant les commentaires de Santé Canada concernant la Description initiale du projet (DIP) pour le projet de centrale électrique Riverside (le Projet). Santé Canada participe au processus d'évaluation d'impact en tant qu'autorité fédérale en vertu de la Loi sur l'évaluation d'impact (LEI). Santé Canada fournit à la demande des organismes de révision, l’expertise ou les informations dont elle dispose pour appuyer l’évaluation des impacts sur la santé humaine des projets visés par la LEI. Santé Canada n'approuve et ne délivre aucun permis et n’émet pas d'autorisation relativement à l'évaluation des impacts des projets visés par la LEI. Santé Canada a examiné la DIP et a fourni des conseils en annexe1 (Fiche d’information des autorités fédérales ou FIAF). Voici les principaux commentaires du ministère concernant les effets négatifs potentiels non négligeables sur la santé des peuples autochtones : • Les émissions atmosphériques potentielles associées au Projet pourraient nuire à la santé des peuples autochtones, en particulier dans les zones où la qualité ...

Report

Attachment Environment and Climate Change Canada - Comments on the Initial Project Description for the Riverside Generating Station / Environnement et Changement climatique Canada - Commentaires sur la Description initiale pour le projet de centrale Riverside

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Environment and Climate Change Canada
  • Reference number: 37
  • Submitted: 2025-11-12 - 5:02 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • See the attached submission / Veuillez consulter la pièce jointe  
  • Attachment included
  • Dossier consultatif de l’autorité fédérale (DCAF) La réponse au DCAF doit être soumise avant le 6 octobre 2025 Projet de centrale Riverside – Atura Power Numéro de dossier du Registre : 89801 Ministère ou organisme Environnement et Changement climatique Canada Contact principal Ravi Patel, Agent d’EE Adresse complète 4905 rue Dufferin, Toronto (Ontario) M3H 5T4 Adresse courriel Ravi.patel@ec.gc.ca Téléphone 1-819-307-2472 Autre contact Dan McDonell 1. Votre service ou organisme exercera-t-il un pouvoir, un devoir ou une fonction, ou fournira-t-il une aide financière en rapport avec le projet pour permettre sa réalisation en tout ou en partie? Dans l’affirmative, a) précisez de quels pouvoir, devoir, fonction ou aide financière il s’agit, et la probabilité que cet élément soit nécessaire à la réalisation du projet, en vous basant sur la Description initiale du projet, en précisant s’il s’agit d’un élément nécessaire, potentiel, probable, improbable ou non nécessaire; ECCC ne s’attend pas à devoir exercer un pouvoir ou des attributions en rapport avec le projet pour permettre sa réalisation. Le projet n’a aucune incidence sur le territoire domanial et le promoteur déclare qu’il n’y a pas de végétation naturelle sur le site du projet et qu’aucun défrichage n’est prévu. Ceci pourrait changer puisque d’autres activités ou éléments du projet pourraient être considérés une fois que la portée du projet et de l’évaluation auront été établies par l’Agence. Veuillez noter que les exigences suivantes pourraient s’appliquer au projet :  permis délivrés en vertu de la Loi sur les espèces en péril (LEP) – improbable;  permis délivrés en vertu de la Loi de 1994 sur la convention ...
  • Attachment included
  • Federal Authority Advice Record (FAAR) FAAR Response must be submitted by October 6, 2025 Riverside Generating Station Project – Atura Power Registry File #89801 Department/Agency Environment and Climate Change Canada Lead Contact Ravi Patel, EA Officer Full Address 4905 Dufferin St, Toronto, ON, M3H 5T4 Email Ravi.Patel@ec.gc.ca Telephone 1-819-307-2472 Alternate Contact Dan McDonell 1. Will your department or agency exercise a power, perform a duty or function, or provide financial assistance, related to the project to enable it to be carried out in whole or in part? As relevant, a) Specify the power, duty or function, or financial assistance, and the likelihood that it will be required to construct the project, based on the Initial Project Description, as either Required, Potential, Likely, Unlikely or Not Required ECCC does not expect that it will be required to exercise a power or perform a duty or function related to the Project to enable it to proceed. The project does not impact federal land and the proponent states that there is no natural vegetation at the project site and that no vegetation clearing is anticipated. Once the scope of the Project and of the assessment are established by the Agency, this may change as additional activities or project components could come into scope. Please note the following requirements that may apply to the Project:  Species at Risk Act (SARA) permits –unlikely  Migratory Birds Convention Act (MBCA) permits –unlikely b) Describe any associated Indigenous or public consultation, including timelines ECCC does not expect to exercise any powers or perform a duty or function under any Act of Parliament in relation to ...

Report

Attachment Indigenous Services Canada Response - Comments on the Initial Project Description for the Riverside Generating Station / Réponse de Services aux Autochtones Canada - Commentaires sur la Description initiale pour le projet de centrale Riverside

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Indigenous Services Canada
  • Reference number: 35
  • Submitted: 2025-11-07 - 8:09 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • See the attached submission / Veuillez consulter la pièce jointe  
  • Attachment included
  • Federal Authority Advice Record (FAAR) FAAR Response must be submitted by October 6, 2025 Riverside Generating Station Project – Atura Power Registry File #89801 Department/Agency Indigenous Services Canada Lead Contact Norah Kielland Full Address 10 rue Wellington, Gatineau QC, K1A 0H4 Email norah.kielland@sac-isc.gc.ca Telephone Alternate Contact Anna Kessler anna.kessler@sac-isc.gc.ca 1. Will your department or agency exercise a power, perform a duty or function, or provide financial assistance, related to the project to enable it to be carried out in whole or in part? As relevant, a) Specify the power, duty or function, or financial assistance, and the likelihood that it will be required to construct the project, based on the Initial Project Description, as either Required, Potential, Likely, Unlikely or Not Required b) Describe any associated Indigenous or public consultation, including timelines c) Describe any associated information requirements (e.g., alternative means assessment, habitat offsetting), and specify those that may be coordinated with the impact assessment process, if an impact assessment is required1 d) Identify any associated project-specific guidance or issues of which the proponent should be aware, or information the proponent should provide. Indigenous Services Canada (ISC) will not be required to exercise a power or perform a duty or function related to the project as it is not located on reserve lands. 2. Using Table 1, identify project- and context- specific key issues, based on the expertise within your mandate2 and the information in your possession, including the Initial Project Description, any exchanges with the proponent ...
  • Attachment included
  • Dossier consultatif de l’autorité fédérale (DCAF) La réponse au DCAF doit être présentée avant le 6 octobre 2025 Projet de centrale Riverside – Atura Power Numéro de dossier du Registre : 89801 Ministère ou organisme Services aux Autochtones Canada Personne-ressource principale Norah Kielland Adresse 10, rue Wellington, Gatineau (Québec), K1A 0H4 Adresse courriel norah.kielland@sac-isc.gc.ca Téléphone Autre personne- ressource Anna Kessler anna.kessler@sac-isc.gc.ca 1. Votre service ou organisme exercera-t-il un pouvoir, un devoir ou une fonction, ou fournira-t-il une aide financière en lien avec le projet pour permettre sa réalisation en tout ou en partie? Dans l’affirmative, a) précisez de quels pouvoir, devoir, fonction ou aide financière il s’agit, et la probabilité que cet élément soit nécessaire à la réalisation du projet, en vous basant sur la Description initiale du projet, en précisant s’il s’agit d’un élément nécessaire, potentiel, probable, improbable ou non nécessaire; b) décrivez toute consultation auprès du public ou des Autochtones connexe, y compris les calendriers; c) décrivez toute exigence en matière d’informations connexe (p. ex., évaluation des instruments alternatifs, compensation des habitats) et précisez lesquelles peuvent être coordonnées avec le processus d’évaluation de l’impact, si un tel processus est requis1; d) indiquez toute orientation ou question propre au projet dont le promoteur devrait avoir connaissance, ou toute information qu’il est tenu de fournir. Services aux Autochtones Canada (SAC) ne sera pas tenu d’exercer un pouvoir, un devoir ou une fonction en lien avec le projet, car le projet n’est pas situé sur des terres ...

Report

Attachment Transport Canada Response - Comments on the Initial Project Description for the Riverside Generating Station Project / Réponse de Transports Canada - Commentaires sur la description initiale de projet pour le projet de centrale Riverside

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Transport Canada
  • Reference number: 34
  • Submitted: 2025-11-06 - 1:27 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • See the attached submission / Veuillez consulter la pièce jointe
  • Attachment included
  • Federal Authority Advice Record (FAAR) FAAR Response must be submitted by October 6, 2025 Riverside Generating Station Project – Atura Power Registry File #89801 Department/Agency Transport Canada Lead Contact David Zeit Full Address 4900 Yonge St, North York, ON M2N 6A5 Email david.zeit@tc.gc.ca Telephone 416-428-8163 Alternate Contact 1. Will your department or agency exercise a power, perform a duty or function, or provide financial assistance, related to the project to enable it to be carried out in whole or in part? As relevant, a) Specify the power, duty or function, or financial assistance, and the likelihood that it will be required to construct the project, based on the Initial Project Description, as either Required, Potential, Likely, Unlikely or Not Required b) Describe any associated Indigenous or public consultation, including timelines c) Describe any associated information requirements (e.g., alternative means assessment, habitat offsetting), and specify those that may be coordinated with the impact assessment process, if an impact assessment is required1 d) Identify any associated project-specific guidance or issues of which the proponent should be aware, or information the proponent should provide. Transport Canada will not be exercising a power, performing a duty or function, or providing financial assistance, related to the project to enable it to be carried out in whole or in part. 2. Using Table 1, identify project- and context- specific key issues, based on the expertise within your mandate2 and the information in your possession, including the Initial Project Description, any exchanges with the proponent or others related to the ...
  • Attachment included
  • Dossier consultatif de l’autorité fédérale (DCAF) La réponse au DCAF doit être soumise avant le 6 octobre 2025 Projet de centrale Riverside – Atura Power Numéro de dossier du Registre : 89801 Ministère ou organisme Transports Canada Contact principal David Zeit, Superviseur régional principal en environnement Adresse complète 4900 Yonge Street, Toronto (Ontario) M2N 6A5 Adresse courriel david.zeit@tc.gc.ca Téléphone 416-428-8163 Autre contact 1. Votre service ou organisme exercera-t-il un pouvoir, un devoir ou une fonction, ou fournira-t-il une aide financière en rapport avec le projet pour permettre sa réalisation en tout ou en partie? Dans l’affirmative, a) précisez de quels pouvoir, devoir, fonction ou aide financière il s’agit, et la probabilité que cet élément soit nécessaire à la réalisation du projet, en vous basant sur la Description initiale du projet, en précisant s’il s’agit d’un élément nécessaire, potentiel, probable, improbable ou non nécessaire; b) décrivez toute consultation auprès du public ou des autochtones associée, y compris les calendriers; c) décrivez toute exigence en matière d’informations associée (p. ex., évaluation des instruments alternatifs, compensation des habitats) et précisez lesquelles peuvent être coordonnées avec le processus d’évaluation de l’impact, si un tel processus est requis1; d) indiquez toute orientation ou question propre au projet dont le promoteur devrait avoir connaissance, ou toute information qu’il est tenu de fournir. Transports Canada n’exercera aucun pouvoir, n’accomplira aucune obligation ni fonction, et ne fournira aucune aide financière, en lien avec le projet, pour permettre sa réalisation en tout ou en ...

Report

Attachment 60 days is not meaningful consultation!

  • Riverside Generating Station Project
  • Author: First Nations , Elder
  • Reference number: 28
  • Submitted: 2025-10-27 - 9:41 AM
  • Project phase: Planning
  •                                                          Caretakers of the Land !                               Economic growth at the cost of a hundreds of thousands of residents who's families rely on the clean air and water is not meaningful consultation for those who will have to live through the next 50 years of pollutions expelled. We as caretakers of this land are outraged at the lack of respectful consultation and timeframe given to review and investigate the plans put forward . When money becomes a driving factor and humanity suffers ,that is cause for concern. All the money in the world cannot replace your loved ones who have passed from pollution caused by industrial factors which were avoidable!                    The Atura meeting I attended was 40 minutes, and that did not show expertise in the planing stages, and the staff had no understanding of First Nations relationship to the Land . The slide show presented had very little planning and created more questions than answers.                    The Consultation process even before BillC-5 was flawed. The planning stage with First Nations was not included during the Drafting of Blueprints as well as permissions to move forward . 2016 ,that's 9 years we should have had to present a valid yay or nay to this project . Legal representation or our own environmental experts on our ...

Report

Attachment SUPPLEMENTAL EVIDENCE SUBMISSION

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Walpole Island First Nation
  • Reference number: 31
  • Submitted: 2025-10-27 - 7:13 AM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • EXECUTIVE SUMMARY       I am submitting critical supplemental evidence that significantly strengthens my October 23, 2025 request for federal Impact Assessment designation of the Riverside Generating Station project.   New Evidence: Atura Power presentation to Aamjiwnaang First Nation (June 19, 2025)       Key Finding: Aamjiwnaang First Nation WAS consulted, but was provided fraudulent information identical to what Walpole Island First Nation received in September 2025.       Critical Implication: This is not inadequate consultation—this is systematic, coordinated fraud across multiple Indigenous rights holders to obtain approvals under false pretenses.       What This Changes:       My October 23 submission stated:   "Aamjiwnaang First Nation was not consulted about Riverside despite sharing the threatened Kettle Point Aquifer."       New evidence proves:   "Aamjiwnaang First Nation was consulted with fraudulent information concealing nuclear plans, corporate ownership, and coordinated industrial scheme—proving intentional deception pattern across multiple First Nations."       This evidence transforms the case from "provincial process missed a First Nation" to "provincial process facilitated systematic fraud against multiple First ...
  • Attachment included
  • Riverside Generating Station Public Meeting Land Acknowledgement Atura Power respectfully acknowledges that the proposed Riverside Generating Station will be located on the traditional territory of the Anishinaabeg peoples, including the Ojibwe, Odawa, and Potawatomi Nations, who form the Three Fires Confederacy. This land is part of the territory covered by Treaty 29 and is home to the Aamjiwnaang First Nation and near the Bkejwanong Territory of the Walpole Island First Nation. These Nations continue to uphold their responsibilities as caretakers of the land and waters, as they have for generations. We honour their enduring presence, knowledge systems, and cultural resilience. As we live and work on these lands, we are reminded of our shared responsibility to act as respectful stewards, to listen to Indigenous voices, and to uphold our responsibilities with humility, care, and accountability. Atura Power is committed to building respectful, meaningful, and mutually beneficial relationships with Indigenous Peoples and communities across Ontario — in the spirit of peace, friendship, and trust. Welcome Purpose of public meeting: • Learn about the proposed Riverside Generating Station • Meet the project team • Share your thoughts and ask questions Pictured: Aerial view of the site. Who We Are Atura Power plays a key role in Ontario’s electricity system by generating safe and reliable electricity. • A subsidiary of Ontario Power Generation • Operates the largest fleet of combined-cycle gas turbine generating stations • Investing in gas expansion and new, non-emitting energy technologies including battery energy storage and hydrogen Halton Hills Generating Station (710 ...

Report

Attachment  Riverside Generating Station Project - Technical Evidence - Multiple First Nations - Shared Aquifer - Federal Jurisdiction Required

  • Riverside Generating Station Project
  • Author: Member of Walpole Island Unceded Anishinaabeg First Nation and Treaty #2 and St. Anne's Island Treaty
  • Reference number: 27
  • Submitted: 2025-10-23 - 6:11 PM
  • Project phase: Planning
  • Riverside Generating Station Project - Technical Evidence Multiple First Nations - Shared Aquifer - Federal Jurisdiction Required Date: October 23, 2025 From: Amy White, Bkejwanong Territory Re: Supplemental Technical Evidence Supporting Federal Impact Assessment Designation EXECUTIVE SUMMARY This supplemental submission provides critical technical evidence demonstrating that the proposed Riverside Generating Station requires federal Impact Assessment under the Impact Assessment Act. Key Jurisdictional Facts: Location: Former Lower Indian Reserve lands (Brick Line Road), approximately 12-15 kilometers from Walpole Island First Nation (Bkejwanong Territory) Adjacent to: Aamjiwnaang First Nation traditional territory Critical Infrastructure: Directly above the Kettle Point Aquifer providing drinking water to both Indigenous communities Multiple Rights Holders: Two distinct First Nations sharing the same threatened water resource Cumulative Context: Communities already bearing disproportionate environmental burden from Chemical Valley industrial legacy Federal Jurisdiction Imperative: When a project on former reserve lands threatens shared water resources critical to multiple Indigenous communities, federal Impact Assessment is not optional—it is constitutionally and legally required. TECHNICAL EVIDENCE ...
  • Attachment included
  • Please see the attachment to view the content.
  • Attachment included
  • Please see the attachment to view the content.
  • Attachment included
  • Please see the attachment to view the content.
  • Attachment included
  • Please see the attachment to view the content.

Report

Attachment Fisheries and Oceans Canada Response - Federal Authority Advice Form for the Riverside Generating Station Project / Réponse de Pêches et Océans Canada - Dossier consultatif de l’autorité fédérale pour le Projet de centrale Riverside

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Fisheries and Oceans Canada
  • Reference number: 30
  • Submitted: 2025-10-14 - 5:34 PM
  • Project phase: Planning
  • See the attached submission / Veuillez consulter la pièce jointe  
  • Attachment included
  • Unclassified - Non-Classifié Dossier consultatif de l’autorité fédérale (DCAF) La réponse au DCAF doit être soumise avant le 6 octobre 2025 Projet de centrale Riverside – Atura Power Numéro de dossier du Registre : 89801 Ministère ou organisme Pêches et Océans Canada Contact principal Amanda Conway, chef d’équipe par intérim, Triage et planification Adresse complète 867, chemin Lakeshore, Burlington (Ontario) L7S 1A1 Adresse courriel Amanda.Conway@dfo-mpo.gc.ca Téléphone 289-556-8651 Autre contact Sheeva Nakhaie, Sheeva.Nakhaie@dfo-mpo.gc.ca 1. Votre service ou organisme exercera-t-il un pouvoir, un devoir ou une fonction, ou fournira-t-il une aide financière en rapport avec le projet pour permettre sa réalisation en tout ou en partie? Dans l’affirmative, a) précisez de quels pouvoir, devoir, fonction ou aide financière il s’agit, et la probabilité que cet élément soit nécessaire à la réalisation du projet, en vous basant sur la Description initiale du projet, en précisant s’il s’agit d’un élément nécessaire, potentiel, probable, improbable ou non nécessaire; Une autorisation donnée au titre de l’alinéa 35(2)b) de la Loi sur les pêches sera requise si le projet est susceptible de causer la détérioration, la destruction ou la perturbation de l’habitat du poisson et/ou une autorisation donnée au titre de l’alinéa 34.4(2)b) de la Loi sur les pêches sera requise si le projet est susceptible d’entraîner la mort du poisson. D’après les renseignements fournis, nous comprenons qu’il n’y aura pas de travaux dans l’eau liés à ce projet. Par conséquent, il est peu probable que Pêches et Océans Canada (MPO) soit tenu d’exercer un pouvoir ou une fonction pour permettre la ...
  • Attachment included
  • Unclassified - Non-Classifié Federal Authority Advice Record (FAAR) FAAR Response must be submitted by October 6, 2025 Riverside Generating Station Project – Atura Power Registry File #89801 Department/Agency Fisheries and Oceans Canada Lead Contact Sheeva Nakhaie, A /Team Leader, Triage and Planning Full Address 867 Lakeshore Road, Burlington, ON L7S 1A1 Email Sheeva.Nakhaie@dfo-mpo.gc.ca Telephone 289-556-8651 Alternate Contact Sheeva Nakhaie, Sheeva.Nakhaie@dfo-mpo.gc.ca 1. Will your department or agency exercise a power, perform a duty or function, or provide financial assistance, related to the project to enable it to be carried out in whole or in part? As relevant, a) Specify the power, duty or function, or financial assistance, and the likelihood that it will be required to construct the project, based on the Initial Project Description, as either Required, Potential, Likely, Unlikely or Not Required A Fisheries Act paragraph 35(2)(b) Authorization will be required if the project is likely to cause the harmful alteration, disruption, or destruction to fish habitat and/or a Fisheries Act paragraph 34.4(2)(b) Authorization if the project is likely to result in the death of fish. Based on the information provided, it is our understanding that there will be no in-water works related to this project. As such, it is not likely that Fisheries and Oceans Canada (DFO) would be required to exercise a power or perform a duty of function to allow this project to proceed. Should works be proposed that may impact fish and fish habitat (including, for example, water crossings that may be required to access the site), we recommend that the proponent submit a Request for ...

Report

Attachment Ontario Ministry of Citizenship and Multiculturalism - Provincial Authority Advice Form for the Riverside Generating Station Project

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Ontario Ministry of Citizenship and Multiculturalism
  • Reference number: 26
  • Submitted: 2025-10-08 - 11:01 AM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • See the attached submission / Veuillez consulter la pièce jointe  
  • Attachment included
  • 1 Provincial Authority Advice Record Form #1: Authority and Summary of Issues Response requested by: October 6, 2025 Riverside Generating Station Project – Atura Power CIAR No.: 89801 The Impact Assessment Agency of Canada (IAAC) encourages comments to be submitted via the Submit a Comment feature available on the project’s Canadian Impact Assessment Registry page (Reference #89801) at https://iaac-aeic.gc.ca/050/evaluations/proj/89801?culture=en-CA. Letters and forms can be uploaded using this feature. If you have any difficulties submitting this way, please contact IAAC using the information provided below for assistance. Ministry/Agency: Ministry of Citizenship and Multiculturalism (MCM) Primary Contact Name: Anastasia Abrazhevich, Heritage Planner, Heritage Planning Unit Email: anastasia.abrazhevich@ontario.ca Phone: 437-240-2379 Alternate Contact Name: Karla Barboza, Team Lead, Heritage, Heritage Planning Unit Email: karla.barboza@ontario.ca Phone: 416-660-1027 Please complete this form. 1. Would your ministry/agency participate in the federal impact assessment process for this project? If so, provide the information of the main point of contact. The Ministry of Citizenship and Multiculturalism will participate in the federal impact assessment process for this project. Please contact: Anastasia Abrazhevich, Heritage Planner, Heritage Planning Unit (anastasia.abrazhevich@ontario.ca) and Karla Barboza, Team Lead, Heritage Planning Unit (karla.barboza@ontario.ca). 2. Will your jurisdiction be undertaking a review and analysis of the project? Would your jurisdiction participate in a cooperative review of the project information? The Ministry of ...

Report

Attachment Riverside comments

  • Riverside Generating Station Project
  • Author: Chippewas of the Thames First Nation
  • Reference number: 22
  • Submitted: 2025-10-06 - 11:57 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Please see attached letter from the Consultation Unit of Chippewas of the Thames First Nation. 
  • Attachment included
  • 320 Chippewa Road Muncey, ON, N0L 1Y0 Tel: 519-289-5555 Fax: 519-289-2230 info@cottfn.com 1 October 6, 2025 Submitted to the online Registry To the Impact Assessment Agency of Canada, Re: Riverside Generating Station Project (ref # 89801) The proposed Riverside Generating Station Project would be located on Chippewas of the Thames First Nation’s Treaty and Traditional Territory, as recognized by Canada in the Big Bear Creek Settlement Agreement (2013). COTTFN holds ancestral connections to the lands and waters and continues to exercise stewardship and practice inherent rights in Deshkan Ziibiing Anishinaabe Aki. Consultation staff have met with Atura Power and reviewed the IPD, but the project is still undergoing review by leadership and the community. For this reason, we are only able to provide preliminary comments. Given the short comment period, COTTFN expects that the Agency will consider any future communications. As Ontario procures new energy capacity, Rights Holding First Nations must be fully involved in assessing cumulative impacts, designing mitigation measures, and participating in economic opportunities taking place in our territories. As a forward-looking Nation, COTTFN is interested in projects that will sustainably meet our energy needs while upholding and respecting Anishinabek rights. While the modelling for the Riverside Project suggests that key pollutants would measure below applicable limits, we are concerned about the cumulative impacts to air quality in the Sarnia/St Clair region, including for our sister Nation of Aamjiwnaang. Air pollution from this gas plant could impact the health of neighbouring human and non-human relatives. The air quality ...

Report

Attachment Why Methane Gas?

  • Riverside Generating Station Project
  • Author: Seth Klompstra
  • Reference number: 21
  • Submitted: 2025-10-06 - 11:16 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Re: Proposed Riverside Generating Station (Project Reference No. 89801) Hi all, As a young member of the local community, as well as a part of the technological development in the St. Clair area I am excited to hear the site is being considered for redevelopment. That being said, based on the available information I have a couple questions specific to the project: Why are other grid stabilizing technologies considered incompatible with the site? Notably small modular reactors. Best deployed in fleets, complementing those planned for Darlington Able to handle baseload generation Contributes to skilled labour in the area and nation Has a future beyond 2050 Diversifies local grid Will pollution from existing local industrial regions compound with the proposed plants pollution? 3/10 of Ontarios largest fossil fuel generating stations (By Watt capacity) are currently operating in the area. The proposed project will result in 4/10 being within 15KM of the Corunna-Mooretown area The area contains an above average amount of industrial manufacturing The area has a history of environmental concerns, especially amongs First Nations people Carbon dioxide and methane gas are currently the largest human-caused contributors to greenhouse gasses   Thanks for the time and opportunity to comment! -Seth

Report

Attachment Please find attached our comments

  • Riverside Generating Station Project
  • Author: Sarnia Lambton Chamber of Commerce
  • Reference number: 20
  • Submitted: 2025-10-06 - 4:39 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  •   To:  Impact Assessment Agency of Canada Project: Riverside Generating Station (Registry #89801) Letter of Support – Atura Power’s Proposed Riverside Generating Station Project On behalf of the Sarnia Lambton Chamber of Commerce, we are writing to express our support for Atura Power’s proposed Riverside Generating Station (GS), to be located at Ontario Power Generation’s former Lambton Generating Station site in St. Clair Township, Ontario. The Chamber represents a broad network of local businesses and industries that are deeply invested in the region’s economic vitality, energy reliability, and environmental stewardship. The proposed Riverside GS aligns strongly with these priorities for several key reasons: Economic Growth and Local Investment The Riverside project will bring significant direct and indirect economic benefits to the Sarnia–Lambton region through local construction activity, procurement opportunities, and ongoing operations. The reuse of an existing industrial site demonstrates responsible land use and supports the retention of skilled trades and technical expertise in our community. Energy Reliability and Transition Ontario’s growing electricity demand requires dependable, flexible generation to complement renewable energy sources. The Riverside GS will provide critical system reliability and support the province’s transition toward a lower-carbon electricity grid. Reliable, affordable power is essential to ...

Report

Attachment Aamjiwnaang First Nation comments on Atura Power Proposed Riverside Generating Station Project

  • Riverside Generating Station Project
  • Author: Aamjiwnaang First Nation
  • Reference number: 19
  • Submitted: 2025-10-06 - 4:03 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Please see attached submisssions of Aamjiwnaang First Nation.
  • Attachment included
  • AAMJIWNAANG FIRST NATION Band Council 978 TASHMOO AVENUE SARNIA, ONTARIO N7T 7H5 Phone: 519-336-8410 Fax: 519-336-0382 1 Fraser Thomson and Reid Gomme 1910-777 Bay Street, PO Box 106 Toronto, Ontario M5G 2C8 Tel: 416-368-7533 ext. 545; 708 Fax: 416-363-2746 fthomson@ecojustice.ca rgomme@ecojustice.ca October 6, 2025 Submitted online to IAA Canada Registry and Addressed to: Riverside Generating Station Project Impact Assessment Agency of Canada 1145-9700 Jasper Avenue Edmonton, Alberta T5J 4C3 The Honourable Julie Dabrusin MP Place Vincent Massey Building 351 Saint-Joseph Boulevard Gatineau QC K1A 0H3 Portlands Energy Centre LP (d/b/a Atura Power) 200-1415 Joshua Creek Drive Oakville, ON L6H 7G4 Dear Agency, Minister and Atura Power: Re: Atura Power Proposed Riverside Generating Station Project (IAA Ref # 89801) Impact Assessment Planning Phase Ecojustice provides these comments on behalf of Aamjiwnaang First Nation (“Aamjiwnaang” or the “Nation”) to explain the need for an impact assessment of the Riverside Generating Station Project (the “Project”). These comments are addressed to the Impact Assessment Agency of Canada (the “Agency”), the Minister of Environment and Climate Change (the “Minister”) and Atura Power (the “Proponent”). Aamjiwnaang draws the Agency’s attention to information and issues that are relevant to the Agency’s mandatory considerations under s. 16(2)(b), (c), (d) and (g) of the Impact Assessment Act (the “Act”) in anticipation of the Agency’s screening decision.1 However, and as detailed below, Aamjiwnaang also reserves its constitutional rights to provide further submissions to the Agency after ...

Report

Attachment Letter of Support for Atura Power’s proposed Riverside Generating Station Project

  • Riverside Generating Station Project
  • Author: Sarnia-Lambton Economic Partnership
  • Reference number: 18
  • Submitted: 2025-10-06 - 4:03 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • October 6, 2025 Impact Assessment Agency of Canada 22nd Floor, Place Bell 160 Elgin Street Ottawa ON K1A 0H3 RE: Letter of Support for Atura Power’s proposed Riverside Generating Station Project To Whom it May Concern, The Sarnia-Lambton Economic Partnership (SLEP) is pleased to offer our strong support for Atura Power’s proposed Riverside Generating Station Project in St. Clair Township (Lambton County). The Sarnia-Lambton Economic Partnership is the lead economic development agency for the Sarnia-Lambton, Ontario area. Our mandate includes fostering economic stability, growth and diversification across the Sarnia-Lambton area, to enhance the quality of life and create a vibrant place to live and work. Once completed, Atura’s proposed project stands to be a significant economic driver for the Sarnia-Lambton area and all of Ontario, via the region’s transmission and distribution capabilities, through the addition of 500 megawatts. The additional energy capacity could be leveraged to accommodate the energy needs of future economic growth in Sarnia-Lambton including the potential for investment in low-carbon hydrogen, large scale manufacturing, data centres, and value-added agriculture projects. The Riverside Generating Station Project would be a complementary addition to Sarnia-Lambton’s existing energy production cluster with its highlighted natural gas, wind, and solar generation totalling over 2,800 megawatts of energy production capabilities. Natural gas-based power generation currently takes place in Lambton County at five production locations contributing to both the public grid and ...
  • Attachment included
  • Address: 1086 Modeland Road, Bldg. 1050, Ste. 100, Sarnia, ON N7S 6L2 | Phone: 519-332-1820 | Website: sarnialambton.on.ca October 6, 2025 Impact Assessment Agency of Canada 22nd Floor, Place Bell 160 Elgin Street Ottawa ON K1A 0H3 RE: Letter of Support for Atura Power’s proposed Riverside Generating Station Project To Whom it May Concern, The Sarnia-Lambton Economic Partnership (SLEP) is pleased to offer our strong support for Atura Power’s proposed Riverside Generating Station Project in St. Clair Township (Lambton County). The Sarnia-Lambton Economic Partnership is the lead economic development agency for the Sarnia-Lambton, Ontario area. Our mandate includes fostering economic stability, growth and diversification across the Sarnia-Lambton area, to enhance the quality of life and create a vibrant place to live and work. Once completed, Atura’s proposed project stands to be a significant economic driver for the Sarnia- Lambton area and all of Ontario, via the region’s transmission and distribution capabilities, through the addition of 500 megawatts. The additional energy capacity could be leveraged to accommodate the energy needs of future economic growth in Sarnia-Lambton including the potential for investment in low-carbon hydrogen, large scale manufacturing, data centres, and value-added agriculture projects. The Riverside Generating Station Project would be a complementary addition to Sarnia-Lambton’s existing energy production cluster with its highlighted natural gas, wind, and solar generation totalling over 2,800 megawatts of energy production capabilities. Natural gas-based power generation currently takes place in Lambton County at five production locations contributing to ...

Report

Attachment Submission - Public Comments on Atura Power's Proposed Riverside Generating Station (CKSPFN/Three Fires Group)

  • Riverside Generating Station Project
  • Author: Three Fires Group/Chippewas of Kettle and Stony Point First Nation
  • Reference number: 17
  • Submitted: 2025-10-06 - 2:27 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Dear Impact Assessment Agency of Canada, Please find below the Chippewas of Kettle and Stony Point First Nation’s comments on Atura Power’s proposed Riverside Generating Station, submitted through the Three Fires Group Consultation Office. Our submission reflects the Nation’s preliminary review of the Initial Project Description and highlights key concerns related to cumulative air quality effects, greenhouse gas emissions, and the ongoing duty to consult under Section 35 of the Constitution Act. We respectfully request that these comments be entered into the public registry and considered in the development of the Summary of Issues for the project. Kind regards, Jessica Wakefield Executive Director, Major Projects and IBAs Three Fires Group / Chippewas of Kettle and Stony Point First Nation
  • Attachment included
  • A-9119 West Ipperwash Road Kettle & Stony Point First Nation, Ontario N0N 1J1 Public Comment – Riverside Generating Station (Atura Power) Submitted by: Chippewas of Kettle and Stony Point First Nation / Three Fires Group Date: October 6, 2025 The Chippewas of Kettle and Stony Point First Nation (CKSPFN), through its Consultation Office (Three Fires Group), submits the following comments on Atura Power’s Initial Project Description for the proposed 500 MW Riverside Generating Station near Sarnia, Ontario. The project is located within Treaty 29 territory and within a region already burdened by industrial air emissions. CKSPFN is concerned that the federal Impact Assessment process continues to apply too narrow a definition of “federal jurisdiction,” excluding issues such as air quality, greenhouse gas (GHG) emissions, and regional cumulative effects. These issues directly affect Indigenous rights, health, and territorial stewardship under Section 35 of the Constitution Act. Air Quality Concerns: Atura’s preliminary air quality modeling (SLR Consulting) may underestimate actual and cumulative effects. It assumes only 1,500 operating hours per year, yet no binding regulation ensures this limit will persist. Increased operation could elevate NOx and ground-level ozone levels—already a concern in Sarnia–Lambton. The cumulative effects assessment also excludes other regional gas proposals such as the Hydrogen Ready project. Greenhouse Gas Emissions: Atura’s estimate of 345,000 tonnes of GHGs per year relies on optimistic efficiency assumptions and limited operational modeling. It is unclear whether the project will be considered “planned” or “new” under the federal Clean Electricity ...

Report

Attachment Letter of Support

  • Riverside Generating Station Project
  • Author: Bluewater Association for Safety, Environment and Sustainability
  • Reference number: 16
  • Submitted: 2025-10-06 - 1:58 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Please find attached a Letter of Support for the Riverside Generation Station Project on behalf of BASES.
  • Attachment included
  • 1086 Modeland Rd., Building 1020 Suite 100N, Sarnia, ON N7S 6L2 519-383-1222 www.lambtonbases.ca September 2, 2025 Impact Assessment Agency of Canada Subject: Letter of Support for the Atura Power Proposed Riverside Generating Station Project (Registry #89801) To whom it may concern, The Bluewater Association for Safety, Environment, and Sustainability (BASES) is a regional non-profit industrial association representing the petrochemical industry in Sarnia-Lambton. We are writing to express our support for the proposed Riverside Generating Station project, submitted by Atura Power. With many of our partners directly involved in and impacted by projects of this scale, we emphasize the importance of supporting the well-being of local workers and the broader community. As a long-term facility expected to operate for decades, Riverside will provide sustained employment opportunities, strengthen the local workforce, and contribute to the safety, resilience, and long-term prosperity of the Sarnia-Lambton region. Reliable energy infrastructure is important for the economic and social well-being of Sarnia-Lambton. For generations, Sarnia-Lambton has been recognized as a centre of industrial expertise, with a skilled workforce and supply chain experienced in managing complex projects safely and effectively. Our established industrial partnerships and collaborative approach further ensure that initiatives like Riverside Generating Station can be executed efficiently, supporting a lower-carbon energy future while continuing to safeguard workers, the environment, and the community. BASES fully supports the Riverside Generating Station project and is confident that ...

Report

Attachment Carpenters’ Union Support for the Riverside Generating Station Project

  • Riverside Generating Station Project
  • Author: Local 1256
  • Reference number: 15
  • Submitted: 2025-10-06 - 8:55 AM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Good Morning,  Please see attachment.  Thank you.
  • Attachment included
  • United Brotherhood of Carpenters Local 1256 100 Business Park Drive Sarnia Ontario N7W 0A3 T: 519-344-2352 To Whom It May Concern, October 3, 2025 Re: Carpenters’ Union Support for the Riverside Generating Station Project UBC Local 1256, an affiliated local union of the United Brotherhood of Carpenters and Joiners of America (the “UBC” or “Carpenters’ Union”) representing over 1,000 carpenters and other allied trades in the Sarnia-Lambton area, would like to formally issue this letter in support of the proposed the Riverside Generating Station project. As a dedicated advocate for skilled tradespeople and the broader region in which our members work, we want to make clear the positive impact that this project will have on the local workforce, economy and long-term sustainability of Sarnia-Lambton and its surrounding areas. The Riverside Generating Station provides a vital opportunity to create and sustain high quality employment for our members, who bring decades of expertise in delivering complex construction projects safely and efficiently. Our union is committed to the highest standards of worker safety, environmental responsibility and community well-being. With Sarnia-Lambton’s established reputation as a hub of industrial excellence, our skilled carpenters are well- equipped to contribute to successful execution of this project. The Carpenters’ Union is confident that, through collaboration with partners and local stakeholders, the Riverside Generating Station will be a model of safe, sustainable and innovative development. UBC Local 1256 members stand ready to ...

Report

Attachment Please do not build this.

  • Riverside Generating Station Project
  • Author: Nicole Corrado
  • Reference number: 14
  • Submitted: 2025-10-05 - 11:44 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Please do not put a generating station in a natural area.  Please do not have any more coal or natural gas or nuclear.  Renewables only.   I noticed a lot of wildlife live here.  ?????Please preserve the trees at this location. Please do not harm animals with this project. Please do not use animal testing for pollution and effluent monitoring. https://www.change.org/p/stop-testing-sewer-water-on-laboratory-fish ?Please work with the Canadian Centre for the Alternatives to Animal Methods. https://www.uwindsor.ca/ccaam/ Please only use non lethal ways to live with geese, beavers, and other wildlife. Develop a Living With Coyotes program with the animal welfare organization Coyote Watch Canada. www.coyotewatchcanada.com Please only use non lethal ways to manage wildlife. There are humane, non lethal ways to deal with beavers. Here's a great resource. https://thefurbearers.com/downloads/PDFs/Beaver%20Book%20-%202019-10-08%20The%20Fur-Bearers.pdf?fbclid=IwAR1fP2wOYQKbWREX0E5QzYBhZLf9VjwMov3p37Vh8ToW1-NeQvAoVATZhEg%0A%0A https://www.change.org/p/stop-banff-from-killing-animals-after-conflicts https://www.humanesociety.org/resources/humanely-scare-away-canada-geese https://www.canadageese.org/nlcontrol.html https://www.peta.org/wp-content/uploads/2021/06/humane-goose-control-pdf.pdf https://www.humanesociety.org/resources/what-do-about-canada-geese This company makes non lethal products. https://margosupplies.com/ca-en/ ? Conventional rodent control uses cruel methods. The companies use glue traps, and snap traps, which, like legholds, can cause injury. They also use ...

Report

Attachment Comments on the Summary of the Initial Project Description for the Riverside Generating Station Project (Reference No. 89801) 

  • Riverside Generating Station Project
  • Author: Administrator on behalf of Peter Mayhew
  • Reference number: 23
  • Submitted: 2025-10-03 - 8:37 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • To the Impact Assessment Agency of Canada,  I am writing to express my significant concerns regarding the proposed Riverside Generating Station (Reference No. 89801), a natural gas-fueled peaker plant proposed by Atura Power for the former Lambton Generating Station site in St. Clair Township. I have reviewed the summary of the Initial Project Description and ask that the following issues related to air, water, overall health, and available alternatives be given comprehensive and priority consideration during the impact assessment process.  1. Concerns Regarding Water Quality and the Walpole Island First Nation  The project's location near the St. Clair River, a vital water resource, is highly concerning, particularly for Indigenous communities.  Impact on Drinking Water: I am gravely concerned that the Walpole Island First Nation (Bkejwanong Territory) obtains its drinking water from the water system that will be impacted by this peaker plant's water usage and/or discharge. The IA must be required to provide absolute assurance, in consultation with the First Nation, that the project will not compromise the quality or security of their water supply, during all phases (construction, operation, and decommissioning).  Water Consumption and Discharge: I request full transparency and a rigorous assessment of the plant's anticipated water withdrawal and consumption rates. As a fossil fuel facility, it will require water and wastewater infrastructure. The IA must clearly outline the projected quality and location of all wastewater (liquid effluents) discharge to ensure no contamination of surface or groundwater, ...

Report

Attachment Sarnia Lambton Building and Construction Trades support this project

  • Riverside Generating Station Project
  • Author: Sarnia Lambton Building and Construction Trades
  • Reference number: 13
  • Submitted: 2025-10-03 - 12:34 PM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • On behalf of the Sarnia Lambton Building Trades, I express our full support for the proposed Riverside Generating Station project by Atura Power.
  • Attachment included
  • **Impact Assessment Agency of Canada** **Subject: Letter of Support for the Atura Power Proposed Riverside Generating Station Project (Registry #89801)** To Whom It May Concern, On behalf of the Sarnia Lambton Building Trades, I express our full support for the proposed Riverside Generating Station project by Atura Power. This initiative is vital for our local workforce and the community, providing stable employment and fostering the well-being of Sarnia-Lambton. Our affiliated unions possess the expertise to successfully construct projects of this scale, ensuring safety, staying within budget, and meeting deadlines. We believe that Atura Power's Riverside Generating Station is a significant step toward a lower-carbon energy future, a commitment to our region's economic vitality, and, above all, a commitment to safety and sustainability. We wholeheartedly endorse this project and believe in the ability of our skilled workforce to ensure its successful implementation. Thank you for considering our support. Sincerely, John Swart President 144 Lochiel Street, Sarnia, ON (519) 344-4680 sarniabt@outlook.com Sarnia Lambton Building and Construction Trades Council

Report

Attachment Letter of Support for Riverside Generating Station

  • Riverside Generating Station Project
  • Author: Sarnia Construction Association
  • Reference number: 12
  • Submitted: 2025-10-03 - 11:38 AM
  • Project phase: Planning
  • Participation notice: Public Notice - Public Comments Invited and Information Sessions on the Summary of the Initial Project Description
  • Please see attached file RE: Letter of Support.
  • Attachment included
  • SARNIA CONSTRUCTION ASSOCIATION IA 954 UPPER CANADA DRIVE (stg) 344-7441 Fax (226) 778-0602 P.O. Box 545 Sarnia N7T 7J4 Email admin@sarniaconstruction.ca October 3,2025 Impact Assessment Agency of Canada 22"d Floor, Place Bell 160 Elgin Street Ottawa, ON KlA 0H3 RE: Atura Power Proposed Riverside Generating Station Project (Registry #89801) Dear Impact Assessment Agency of Canada, We are a mixed-trade construction association representing contractor members who provide construction services to major oil and gas refineries, petrochemical facilities, and other industrial clients in the Sarnia-Lambton region. These contractors employ a highly skilled, unionized workforce drawn from a labour pool of approximately 6,000 tradespeople. The livelihoods of both our contractors and tradespeople depend on the strength, stability, and growth of our industrial base. Sarnia's Chemical Valley is one of the most highly concentrated petrochemical hubs in North America and is recognized as Ontario's largest industrial center. The long-term economic health of this sector is a shared priority for all stakeholders, and reliable infrastructure is essential to sustaining that growth. It is in this context that we wish to express our strong support for the proposed Riverside Generating Station. Its development will have a significant positive impact on both the local and regional economies. Beyond the immediate creation of construction jobs, the project will generate long-term employment through ongoing maintenance and operations These opportunities will help ensure that our workforce remains strong and well-prepared to meet the needs of our clients. The addition of a 500 MW natural gas-fuelled generating station will also enhance ...