Public Notice

YUL Montreal-Trudeau International Airport– Extension of taxiways B and P – Public Comment Period

July 16, 2024 - ADM Aéroports de Montréal must determine whether the proposed project is likely to cause significant adverse environmental effects.

To help inform this determination, ADM Aéroports de Montréal is inviting comments from the public respecting that determination. All comments received will be considered public and may be posted online.

Written comments must be submitted by August 15, 2024 to:

Public Affairs
ADM Aéroports de Montréal
800 Place Leigh-Capreol
Office 1000
Dorval, Quebec H4Y 0A5
Email: consultation-projets@admtl.com

The Proposed Project

The project consists in the implementation of two taxiways along the North Runway (06L-24R): taxiways B and P.

In order to maintain its facilities to reliability and safety standards, ADM must proceed with the reconstruction of a section of the apron and of taxiway F. However, taxiway F is frequently used by aircraft to taxi between the apron and the North Runway (06L-24R). The implementation of taxiways B and P as substitutes for taxiway F will allow aircraft to circulate while the work on the apron and taxiway F is being carried out.

The project will be carried out over several years:

  • 2024: first section of taxiway B;
  • 2025: second section of taxiway B and taxiway P;
  • Later: reconstruction of a section of the apron and taxiway F.

The new taxiways will maintain the fluidity of airport operations and will minimize the impact on both passengers and airlines operating at YUL while allowing the necessary rehabilitation work to be carried out on the main apron.

Document reference number: 2