Notice of Time Limit Suspension with Reasons

Ottawa — February 8, 2023 — On February 6, 2023, the Impact Assessment Agency of Canada (the Agency) suspended the 180-day time limit within which it must provide Mining O3 Inc. (the proponent) with a notice of commencement of the impact assessment of the Marban Gold Mine Project, if the Agency decides that such an assessment is required.

This suspension follows the submission of a written request (in French only) by the proponent to allow sufficient time to provide the Agency with:

  • Details of how it intends to respond to the Summary of Issues provided to the proponent on January 6, 2023; and
  • A detailed description of the project that includes the information prescribed by the Information and Management of Time Limits Regulations.

When the proponent has provided the Agency with its response to the Summary of Issues and a detailed description of the project, the Agency will post a notice that the 180-day time limit will resume.

For further information on this impact assessment, please contact:

Marban Gold Mine Project
Impact Assessment Agency of Canada
Telephone: 418-649-6444
Email: marban@iaac-aeic.gc.ca

Document Reference Number: 30