Summit Lake PG LNG Project

Comment Search Mobile

Comment Search

Skip to filters

36 results

Attachment Nazko First Nation Comments - Summit Lake PG LNG Early Engagement

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Nazko First Nation
  • Reference number: 27
  • Submitted: 2024-05-22 - 2:18 PM
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • PO Box 4129, Quesnel, British Columbia V2J 3J2 Tel: (250) 992-9085 Fax: (250) 992-7982 John Antill Project Assessment Manager Environmental Assessment Office PO Box 9426 Stn. Prov Gov Victoria, B.C. V8W 9V1 Re: Nazko First Nation Comments – Summit Lake PG LNG Early Engagement Dear John, Nazko First Nation’s Natural Resources Department has conducted a high-level review of the Summit Lake PG LNG Project Liquified Natural Gas Facility Initial Project Description, dated February 12, 2024, prepared by Keywest Projects Ltd., on behalf of JX LNG Canada Ltd. Below are Nazko First Nation’s initial comments on the Summit Lake PG LNG Project Liquified Natural Gas Facility (the “Project”). • Based on an initial assessment, Nazko First Nation has determined that the Project will have an impact on its Aboriginal Rights and interests. • Nazko First Nation will use the British Columbia and Federal assessment processes to determine its position, potential Project consent, and appropriate accommodation measures if Project consent is provided. • As part of the consultation process, Nazko First Nation requires adequate resources to participate in the British Columbia and Federal assessment processes. • At this time, Nazko First Nation does not support the substitution request pursuant to the Impact Assessment Act (IAA) and in accordance with the ‘Impact Assessment Cooperation Agreement Between Canada and British Columbia’ (the Cooperation Agreement) for the proposed Project because adequate resources from the BC EAO, IAAC, or JX LNG Canada Ltd., have not been confirmed for Nazko First Nation’s participation in the assessment processes. After review, we look forward to ...

Report

Attachment NO MORE FOSSIL FUEL PROJECTS, INCLUDING LNG EXPORTS

  • Summit Lake PG LNG Project
  • Author: Roger Bryenton
  • Reference number: 23
  • Submitted: 2024-05-06 - 11:09 PM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • SUMMIT LAKE LNG PROJECT COMMENT Methane leaks are possible catastrophes, as well as massive global heating impacts. Global climate is the crux - methane emissions at 120 times the warming of CO2, and we want to provide more to the planet?  NO Cumulative effects of exploration, drilling, and fracking to supply the gas, the pipelines to transport it, the railway line through communities where an accident cojuld decimate the entire community in minutes, and if in fire season, could burn thousands of hectares of forests, a railway adjacent to a single transport corridor, a rail line adjacent to major rivers where spills could cause unknown harm and fires,  ALL THIS FOR A FEW JOBS AND A FEW DOLLARS?     THIS PROPOSAL IS MADNESS How thoroughly did the project examine cumulative impacts of all the LNG projects across BC, on the availability of fossil gas, the impact of fracking and extraction, the need for electricity, or combustion of the gas for transport, compression and liquefaction? Risk to humans, wildlife, fish, migrating species, communities, transportation corridor, as well as end users. Emissions MUST INCLUDE "SOURCE TO USE"!   CUMULATIVE IMPACTS, not just locally, regionally or nationally, but internationally. LNG IS NOT A CLEAN FUEL.  IN FACT, REPLACING OIL AND COAL WITH LNG WILL INCREASE GLOBAL TEMPERATURE, AS THE CARBON AND AEROSOL PARTICLES WITH OIL AND COAL HAVE BEEN SUPPRESSING THE GLOBAL HEATING FACTOR! Emissions must include FULL CUMULATIVE ASPECTS:  exploration - roads, trails, seismic lines; well development, drilling, water supply and use, waste water disposal - all fracking ...

Report

Attachment JX LNG Canada Ltd. proposed Summit Lake PG LNG Project, IAAC Reference Number 87307, Comments of the Citizen's Oil & Gas Council

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Mike Sawyer
  • Reference number: 24
  • Submitted: 2024-05-02 - 10:02 PM
  • Updated: 2024-05-08 - 11:53 AM
  • Rationale: Comment updated for administrative purposes
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe   
  • Attachment included
  • Page 1 of 5 Citizen’s Oil & Gas Council PO Box 1175 Nanton, Alberta, Canada T0L 1R0 May 2, 2024 VIA EMAIL Summit Lake PG LNG Project Impact Assessment Agency of Canada 210A - 757 West Hastings Street Vancouver, British Columbia, V6C 3M2 Re: JX LNG Canada Ltd. proposed Summit Lake PG LNG Project IAAC Reference Number 87307 Comments of the Citizen’s Oil & Gas Council Dear Sirs/Madams These are the comments of the Citizen’s Oil & Gas Council (hereafter “the COGC”) with respect to Initial Project Description (hereafter “the Project Description”) prepared by JX LNG Canada Ltd. (hereafter “the Proponent”) with respect to its proposed Summit Lake PG LNG Project (hereafter “the Project”). The COGC comments will focus on the Project purpose and rationale, climate change implications of the Project, implications of rail transportation of produced LNG to Prince Rupert, LNG storage in Prince Rupert, Cumulative effects of the Project and the need for the Project. These comments are not intended to be exhaustive but instead are designed to highlight what in the COGC opinion are the most significant failings in the Proponent’s Project Description. Each of these failings will be addressed below. 1. Project Purpose and Rationale 1.1. The Project Description states that the main purpose of the Project would be: “…Demand for LNG is increasing across the globe as governments are looking to phase out coal use while still supplying the growing demand for energy. According to the Canadian Association of Petroleum Producers (2018), natural gas releases approximately 40% fewer greenhouse gases than coal when utilized for generating electricity. By replacing higher-emitting fuel sources in overseas ...

Report

Attachment Public Notice Summit Lake PG LNG Project Public Comments Invited & Information Sessions

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Nicole Corrado
  • Reference number: 25
  • Submitted: 2024-05-02 - 4:21 PM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Please do not build another natural gas pipeline.  Please do not frack the land,  We are in the midst of a climate crisis.  This proposal, which would damage and destroy the homes of grizzly bears, caribou, birds, fish, and many animals, is terrible.  And gas plants destroy all sorts of animals in laboratory testing of their effluents, and in lethal sampling of birds, fish, frogs, etc.  We do not need more.      Please preserve the trees at this location.  Please do not build on an area that has a lot of trees, and do not build on a wetland either.  Please do not harm animals with this project. Please do not use animal testing for pollution monitoring.  https://can01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.change.org%2Fp%2Fstop-testing-sewer-water-on-laboratory-fishPlease&data=05%7C02%7Csummitlake%40iaac-aeic.gc.ca%7C1c2b612a47c7436c2ab508dc6ae56426%7C35d07687f4f24fbc8b3efa87a26b3b7b%7C0%7C0%7C638502781349749000%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=CJGVv2D8YSPFUUbz5DhGXQCCb3ANAYvYVPGHimcL2k8%3D&reserved=0 only use non lethal ways to live with geese, beavers, and other wildlife.  Develop a Living With Coyotes program with the animal welfare organization Coyote Watch Canada.  ...

Report

Attachment This is not a step in the right direction

  • Summit Lake PG LNG Project
  • Author: Nick Veeken
  • Reference number: 22
  • Submitted: 2024-05-02 - 1:28 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • I'd be surprised by an LNG project that would last 5 years from 2024 but a project that is considered to only start construction in 2028 and last 30 years is unbelievable. I also have to question the need for a column in Appendix C of the project description that shows the calculated values for the green house gases emitted by this project as a percentage of BC's total emission. Is this necessary or is it provided to demonstrate how insignificant these numbers are compared to the whole of BC. These values also do not account for the supposed reduction in emissions from the 2007 baseline for the province of British Columbia, which by the projects end in the late 2050's would put the percentage of emissions contributed by the LNG project to BC's annual emissions at closer to 0.75% than 0.17%. How much money would this bring in to Canada, B.C., and the communities around Summit Lake? Is B.C. or Canada subsidizing this project, if so how much money is being put towards it? Why invest in LNG when we can invest in true renewables with much less emissions than LNG and without the potential of leaking methane which has a higher warming potential than carbon dioxide?  Why invest in LNG when renewables are shown to be cheaper and will help solve a problem instead of worsening it?  If there is a leak of natural gas what might prevent a bad actor from not reporting it?

Report

Attachment Please do not allow more development

  • Summit Lake PG LNG Project
  • Author: Nicole Corrado
  • Reference number: 21
  • Submitted: 2024-05-01 - 1:48 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Please do not build another natural gas pipeline.  Please do not frack the land,  We are in the midst of a climate crisis.  This proposal, which would damage and destroy the homes of grizzly bears, caribou, birds, fish, and many animals, is terrible.  And gas plants destroy all sorts of animals in laboratory testing of their effluents, and in lethal sampling of birds, fish, frogs, etc.  We do not need more.   Please preserve the trees at this location.  Please do not build on an area that has a lot of trees, and do not build on a wetland either.  Please do not harm animals with this project. Please do not use animal testing for pollution monitoring.  https://www.change.org/p/stop-testing-sewer-water-on-laboratory-fishPlease only use non lethal ways to live with geese, beavers, and other wildlife.  Develop a Living With Coyotes program with the animal welfare organization Coyote Watch Canada.  www.coyotewatchcanada.com Please only use non lethal ways to manage wildlife.  There are humane, non lethal ways to deal with beavers.  Here's a great resource.  https://thefurbearers.com/downloads/PDFs/Beaver%20Book%20-%202019-10-08%20The%20Fur-Bearers.pdf?fbclid=IwAR1fP2wOYQKbWREX0E5QzYBhZLf9VjwMov3p37Vh8ToW1-NeQvAoVATZhEg%0A%0A https://www.humanesociety.org/resources/humanely-scare-away-canada-geese https://www.canadageese.org/nlcontrol.html https://www.peta.org/wp-content/uploads/2021/06/humane-goose-control-pdf.pdf https://www.humanesociety.org/resources/what-do-about-canada-geese This company makes non lethal products. https://margosupplies.com/ca-en/ ? Conventional rodent control uses ...

Report

Attachment Please do not allow fracking or natural gas pipelines

  • Summit Lake PG LNG Project
  • Author: Nicole Corrado
  • Reference number: 20
  • Submitted: 2024-05-01 - 1:42 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Please do not build another natural gas pipeline.  Please do not frack the land,  We are in the midst of a climate crisis.  This proposal, which would damage and destroy the homes of grizzly bears, caribou, birds, fish, and many animals, is terrible.  And gas plants destroy all sorts of animals in laboratory testing of their effluents, and in lethal sampling of birds, fish, frogs, etc.  We do not need more coal.     Please preserve the trees at this location.  Please do not build on an area that has a lot of trees, and do not build on a wetland either.  Please do not harm animals with this project. Please do not use animal testing for pollution monitoring.  https://www.change.org/p/stop-testing-sewer-water-on-laboratory-fishPlease only use non lethal ways to live with geese, beavers, and other wildlife.  Develop a Living With Coyotes program with the animal welfare organization Coyote Watch Canada.  www.coyotewatchcanada.com   Please only use non lethal ways to manage wildlife.  There are humane, non lethal ways to deal with beavers.  Here's a great resource.  https://thefurbearers.com/downloads/PDFs/Beaver%20Book%20-%202019-10-08%20The%20Fur-Bearers.pdf?fbclid=IwAR1fP2wOYQKbWREX0E5QzYBhZLf9VjwMov3p37Vh8ToW1-NeQvAoVATZhEg%0A%0A   https://www.humanesociety.org/resources/humanely-scare-away-canada-geese   https://www.canadageese.org/nlcontrol.html   https://www.peta.org/wp-content/uploads/2021/06/humane-goose-control-pdf.pdf   https://www.humanesociety.org/resources/what-do-about-canada-geese   This ...

Report

Attachment Proposed Summit Lake LNG PG Project comment submission

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Les and Janice Baker
  • Reference number: 19
  • Submitted: 2024-04-29 - 12:09 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Hello Christine,   It was nice meeting you at the Summit Lake LNG Project Open House in Prince George last week.  Thank you for providing your contact details.  Our comments and questions about the project follow, as we were unable to find a comment field that allowed us to address all of our comments.   Summit LNG comments and questions – Les and Janice Baker   We have read through the JX Energy’s Summit Lake PG LNG Project Description with interest and excitement for the potential economic benefits and employment and contracting opportunities for Lheidli T’enneh and Lheidli T’enneh members.   We are interested in the project’s projected benefits and in its goal of reducing global GHG emissions.  Employment and contracting opportunities for Lheidli T’enneh members, close to their homes, will provide well paid jobs without the need to leave their community and families.   We are supportive of the Project and its potential benefits for Lheidli T’enneh members but want assurance the project will minimize habitat and ecosystem loss, protect air and water quality, mitigate impacts, and truly provide benefits for Lheidli people.   Having attended the April 10 Community Engagement session in Prince George, BC, we have the following questions and comments:         Will a cumulative effects assessment be undertaken?  Specifically for air and water quality?         Will the proponent install air quality monitoring stations on Lheidli ...

Report

Attachment Transport Canada Federal Authority Advice Record - Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Transport Canada
  • Reference number: 16
  • Submitted: 2024-04-18 - 1:15 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by April 10, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File: 005908 Department/Agency Transport Canada Lead contact Jessica Low Full address TC Programs, Environmental Services, 800 Burrard St, Vancouver, BC V6Z 2J8 Email jessica.low@tc.gc.ca Telephone 236-330-2687 Alternate Contact Philip Bartha (236-339-3719, philip.bartha@tc.gc.ca) 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. Based on the information provided in the Initial Project Description (IPD), Transport Canada would not likely have a power or perform a duty or function related to the Project. Transport Canada would like to share the following information regarding the Canadian Navigable Waters Act, which may require Transport Canada to exercise a power or perform a duty or function: Canadian Navigable Waters Act There appear to be no scheduled waterways in the project footprint as per the CNWA. As such, no CNWA approval would be required. However, should any navigable waterways be impacted by the proposed construction of the project, then the proponent, potentially alongside Enbridge (pipeline), and/or BC Hydro (powerline), will be required to conduct a self-assessment, using the Project Review Tool, to determine if they are minor works or need to either follow the public resolution process or submit an application for approval. Please see additional information below. Under the Canadian Navigable ...

Report

Attachment Environment and Climate Change Canada Federal Authority Advice Record - Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Environment and Climate Change Canada
  • Reference number: 13
  • Submitted: 2024-04-18 - 1:12 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • Federal Authority Advice Record (FAAR) Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File: 005908 Department/Agency Environment and Climate Change Canada Lead contact Kelsey Lee Full address Douglas Jung Building 401 Burrard St., Suite 201 Vancouver, BC V6C 3R2 Email Kelsey.Lee@ec.gc.ca Telephone (778) 617-2272 Alternate Contact Jennifer Huxter, Jennifer.huxter@ec.gc.ca 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. Based on the Initial Project Description (IPD), ECCC expects that it may be required to exercise a power, or perform a duty or function related to the Project, to enable it to proceed. Once the scope of the Project and of the assessment are established by the Agency, this may change as additional activities or project components could come into scope. Species at Risk Act Permits For species listed in Schedule 1 of the Species at Risk Act (SARA) as Extirpated, Endangered or Threatened, a permit may be required from ECCC (section 73 of SARA) for activities that affect a listed terrestrial wildlife species, any part of its critical habitat, or the residences of its individuals, where those prohibitions are in place. Such permits may only be issued: if all reasonable alternatives to the activity that would reduce the impact on the species have been considered and the best solution has been adopted; if all feasible measures will be taken to minimize the impact of the activity on the species or its critical habitat or the residences of its individuals; and if ...

Report

Attachment Health Canada Federal Authority Advice Record - Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Health Canada
  • Reference number: 14
  • Submitted: 2024-04-18 - 1:08 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • 1 Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by March 18, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Health Canada Lead contact Herbert Antill Full address 757 W Hastings Street, Vancouver, BC V6C 1A1 Email herbert.antill@hc-sc.gc.ca Telephone 604-809-7652 Alternate Contact Yota Hatziantoniou, yota.hatziantoniou@hc-sc.gc.ca 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, including when it would take place. Not applicable (N/A) 2. Is your department or agency in possession of specialist or expert information or knowledge in one of your fields of expertise that may be relevant to the conduct of an impact assessment of the Project? Specify the specialist or expert information or knowledge. As a federal authority, Health Canada (HC) will provide specialist or expert information and knowledge in the Department’s possession (expertise) to support the assessment of impacts on human health from projects considered individually or cumulatively under the Impact Assessment Act (IAA). It should also be noted that expertise related to assessing human health that is relevant to impact assessment (IA) may be held by other federal, provincial, and municipal partners, reflecting the shared jurisdiction for environmental and human health within Canada. ...

Report

Attachment Crown Indigenous Relations and Northern Affairs Canada Federal Authority Advice Record - Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Crown Indigenous Relations and Northern Affairs Canada
  • Reference number: 12
  • Submitted: 2024-04-18 - 1:06 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • GCDOCS # 122457999 Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by March 18, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Crown Indigenous Relations and Northern Affairs Canada Lead contact Felexce Ngwa Acting Manager, Major Projects Management Office Full address 25 Eddy Street, 6th Floor Gatineau, Quebec K1A 0H4 Canada Mail Stop 25E-14, Floor 6 Email felexce.ngwa@rcaanc-cirnac.gc.ca Telephone Felexce Ngwa – (343) 630-6765 Alternate Contact Claire Murphy (claire.murphy@rcaanc-cirnac.gc.ca) Michael Rowan (michael.rowan@rcaanc-cirnac.gc.ca) 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. It is not probable that Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC) will exercise a power or perform a duty or function related to the Project to enable it to proceed as CIRNAC is not a regulatory department with respect to the proposed project. CIRNAC does not have a regulatory function relative to the proposed project but can offer subject matter expertise as required of Federal Authorities under the Impact Assessment Act. CIRNAC’s Major Projects Management Office(MPMO) facilitates communication and coordination of subject matter expertise from within the department and provides this expertise to partner departments and agencies involved in the Impact Assessment Process – Horizontal Initiative. The current contact for CIRNAC’s MPMO is Felexce Ngwa (felexce.ngwa@rcaanc ...

Report

Attachment Indigenous Services Canada Federal Authority Advice Record - Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Indigenous Services Canada
  • Reference number: 15
  • Submitted: 2024-04-18 - 1:04 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • GCDOCS # 123523247GCDOCS # 123523247 Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by March 18, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Indigenous Services Canada Lead contact Lee-Ann Hamilton Full address 10 rue Wellington, Gatineau Email Lee-Ann.Hamilton@sac-isc.gc Telephone Alternate Contact . Jan.Triska2@sac-isc.gc.ca 819-743-4795 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, including when it would take place. Indigenous Services Canada (ISC) will not be required to exercise a power or perform a duty or function related to the Project as it is not responsible for approving or issuing licences, permits or authorizations for the assessments of large, proposed projects. 2. Is your department or agency in possession of specialist or expert information or knowledge in one of your fields of expertise that may be relevant to the conduct of an impact assessment of the Project? Yes Specify the specialist or expert information or knowledge. Indigenous Services Canada has a mandate to support Indigenous people (First Nations, Inuit and Métis) in their efforts to improve social well-being, health and economic prosperity; to develop healthier, more sustainable communities; and to participate more fully in Canada's ...

Report

Attachment Fisheries and Oceans Canada - Federal Authority Advice Record for Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Fisheries and Oceans Canada
  • Reference number: 11
  • Submitted: 2024-04-18 - 12:59 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • See the attached submission / Veuillez consulter la pièce ci-jointe 
  • Attachment included
  • Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by April 10, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Fisheries and Oceans Canada Lead contact James Dwyer Full address 401 Burrard Street, Vancouver BC, V6C 3S4 Email James.Dwyer@dfo-mpo.gc.ca Telephone (236) 335-7602 Alternate Contact Tessa Richardson Tessa.Richardson@dfo-mpo.gc.ca (604) 362-4645 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. Unknown – The Executive Summary of the Initial Project Description (IPD) states that the Project is being designed to have no direct impacts to water or aquatic life; however, Section 11. 1 states that the Project has the potential to affect fish and fish habitat and aquatic species at risk. Authorization under Section 34.4(2)(b) and 35(2)(b) of the Fisheries Act may be required if the death of fish or the harmful alteration, disruption, or destruction (HADD) of fish habitat resulting from works, undertakings or activities during the construction of the Project cannot be avoided or mitigated. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, including when it would take place. Consultation with Indigenous groups would be undertaken following DFO receipt of a complete and adequate application for a Fisheries Act authorization, if required, from the proponent. 2. Is your department or agency in ...

Report

Attachment Impact on North Salmon River Forrest Service Road

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Tom Muirhead
  • Reference number: 18
  • Submitted: 2024-04-16 - 7:24 PM
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • To the south and west of the LNG project they propose a long siding next to the CN rail line.     Today there is not a lot of traffic on the FS road.  Ten years for now that may not be the case.  Should there be a long line of flat cars parked on the siding will they obstruct vehicle traffic using the North Salmon FS road?   In the Prince George area we have a road that goes to the Otway community, there are three railroad crossings on this road.  As the community has grown there has been increasing community pressure to either reroute the road or build overpasses.  There may come a day when the North Salmon road interconnects with a road to the west.  Alternate transportation routes are gaining importance when principal transportations routes are blocked by major traffic accidents or forest fires.   The North Salamon FS road serves most industrial uses today.   Should there be an accident to the west, what priority does passage along this road have for emergency vehicles?   The site of the LNG facility is in the headwaters of the Fraser River.  The Salmon River is an important spawning area for anadromous fish.  Is there going to be any specific care to collect surface water from the site?   Grading, ditching and retention ponds are much easier to construct before infrastructure appears on the site. 

Report

Attachment Summit Lake PG LNG Project, Project reference number: 87307, Comments on Proposed Substitution Agreement

  • Summit Lake PG LNG Project
  • Author: Administrator on behalf of Micheal D. Sawyer.
  • Reference number: 26
  • Submitted: 2024-04-14 - 6:33 PM
  • See the attached submission / Veuillez consulter la pièce ci-jointe
  • Attachment included
  • Page 1 of 4 Michael D. Sawyer P.O. Box 1175 Nanton, Alberta, T0L 1R0 April 14, 2024 VIA EMAIL The Honourable Steven Guilbeault Minister of Environment and Climate Change House of Commons Ottawa, Ontario, K1A 0A6 and Impact Assessment Agency of Canada 210A - 757 West Hastings Street Vancouver, British Columbia, V6C 3M2 Dear Sirs/Madams Re: Summit Lake PG LNG Project Project reference number: 87307 Comments on Proposed Substitution Agreement The Government of British Columbia has requested that the federal impact assessment with respect to the above referenced Project be substituted to the province1. If you, in your capacity of Minister of Environment and Climate Change, grant that request, the British Columbia Environmental Assessment Office (hereafter “the BCEAO”) would conduct the project's impact assessment on behalf of the Federal Government. The Canadian Impact Assessment Agency has asked for public comments on the proposed substitution agreement and this letter constitutes my comments with respect to the proposed substitution agreement. I submit that the proposed substitution agreement is not in the public interest and that it should not be approved by the Government of Canada. My reasons for this position are as follows. Meeting Legislative Requirements Section 31(1) of the Impact Assessment Act (hereafter “the Act”) provides you with the discretion to enter into a substitution agreement with the BCEAO with respect to the Project but that discretion is constrained by Section 33(1) of the Act which provides that you can only approve a substitution if you is satisfied that all of the enumerated conditions are met. Specifically, Section 33(1) requires, among other ...

Report

Attachment Natural Resources Canada's Comments to the Federal Authority Advice Record (FAAR) For the Summit Lake PG LNG Project

  • Summit Lake PG LNG Project
  • Author: Natural Resources Canada
  • Reference number: 10
  • Submitted: 2024-04-12 - 1:56 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Please see attached, Natural Resources Canada's Comments to the Federal Authority Advice Record (FAAR). Should you have any questions, do not hesitate to contact Kathy McPherson (kathy.mcpherson@nrcan-rncan.gc.ca). Thank you, Kathy McPherson Impact Assessment Division Office of the Chief Scientist, Natural Resources Canada 9860 West Saanich Rd, Sidney, BC V8L 4B2  
  • Attachment included
  • UNCLASSIFIED - NON CLASSIFIÉ Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by April 10, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Natural Resources Canada Lead contact Kathy McPherson Full address 9860 West Saanich Rd, Sidney, BC V8L 4B2 Email Kathy.mcpherson@nrcan-rncan.gc.ca Telephone 250-361-7045 Alternate Contact Rani Al Anid (rani.alanid@nrcan-rncan.gc.ca) 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, including when it would take place. Based on the information provided to date, NRCan is not likely to be required to exercise a power or perform a duty or function pursuant to the Department’s regulatory role under the Explosives Act. 2. Is your department or agency in possession of specialist or expert information or knowledge in one of your fields of expertise that may be relevant to the conduct of an impact assessment of the Project? Specify the specialist or expert information or knowledge. Based primarily on its diverse scientific research programs, NRCan possesses the following expertise that may be relevant to the conduct of an impact assessment for this Project:  Under the Department of Natural Resources Act, NRCan provides advice and information to the Minister of Energy and Natural Resources, as well as departmental ...

Report

Attachment FAAR Form

  • Summit Lake PG LNG Project
  • Author: Canadian Transportation Agency
  • Reference number: 8
  • Submitted: 2024-04-09 - 11:38 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Enclosed is the completed FAAR form for the proposed Summit Lake project with CTA's response.
  • Attachment included
  • Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by April 10, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Canadian Transportation Agency (CTA) Lead contact Sarah Bunting - Environmental Officer, Determinations and Compliance Branch Full address Canadian Transportation Agency 60 Laval Street, Unit 01 Gatineau, QC J8X 3G9 Email sarah.bunting@otc-cta.gc.ca Telephone 819-271-7290 Alternate Contact John Woodward - Senior Environmental Officer, Determinations and Compliance Branch Email: john.woodward@otc-cta.gc.ca Phone: 819-962-0472 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? No – Assuming that there is no new Federally Regulated Railway Company (FRRC), the Project does not require approval under section 98 of the Canada Transportation Act in order for the proponent to construct the proposed LNG Facility for the following reasons:  The proponent is not a FRRC, nor is the proponent facilitating the implementation of the proposed Project as a third party on behalf of a FRRC;  The proposed Project is located on public lands (i.e., provincial crown land), that are not Federal Crown lands, or lands owned by a FRRC; and  The works and/or lands of the proposed Project are not to be under the oversight of, operated by, or serviced by a FRRC. If yes, specify the Act of Parliament and that power, duty or function. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, ...

Report

Attachment ESDC's FAAR and Final IPD comments

  • Summit Lake PG LNG Project
  • Author: Employment and Social Development Canada
  • Reference number: 7
  • Submitted: 2024-04-08 - 12:29 PM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Hello, Please see attached -- Employment and Social Development Canada's Federal Authority Advice Record and input on the Final Initial Project Description for the Summit Lake PG LNG Project. Thank you,
  • Attachment included
  • Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by April 10, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File: 005908 Department/Agency Employment and Social Development Canada (ESDC) Lead contact Sarah Strapps - Director of Policy Integration and Special Projects (PISP) branch of the Skills and Employment Branch (SEB) Full address Phase IV 140 Promenade du Portage, Gatineau, Québec K1A 0J9 Canada Email sarah.strapps@hrsdc-rhdcc.gc.ca Telephone 1-873-355-9643 Alternate Contact Aspa Kotsopoulos – Acting Manager (PISP-SEB) 1-819-664-0469 aspa.kotsopoulos@hrsdc-rhdcc.gc.ca 1 . a) I s i t p r o b a b l e t h a t y o u r d e p a r t m e n t o r a g e n c y m a y b e r e q u i r e d t o e x e r c i s e a p o w e r o r p e r f o r m a d u t y o r f u n c t i o n r e l a t e d t o t h e P r o j e c t t o e n a b l e i t t o p r o c e e d ? I f y e s , s p e c i f y t h e A c t o f P a r l i a m e n t a n d t h a t p o w e r , d u t y o r f u n c t i o n . E S D C d o e s n o t e x e r c i s e p o w e r s , n o r p e r f o r m s p e c i f i c d u t i e s o r f u n c t i o n s r e l a t e d t o t h e P r o j e c t t o e n a b l e i t t o p r o c e e d . T h e E S D C M i n i s t e r ’ s p o w e r s , d u t i e s a n d f u n c t i o n s e x t e n d t o a n d i n c l u d e a l l m a t t e r s r e l a t i n g t o h u m a n r e s o u r c e s a n d s k i l l s d e v e l o p m e n t i n C a n a d a o r t h e s o c i a l d e v e l o p m e n t o f C a n a d a o v e r w h i c h P a r l i a m e n ...

Report

Attachment WAGE's FAAR/Comments on IPD

  • Summit Lake PG LNG Project
  • Author: WAGE
  • Reference number: 6
  • Submitted: 2024-04-08 - 9:55 AM
  • Project phase: Planning
  • Participation notice: Public notice - Public Comments Invited & Information Sessions
  • Thank you.
  • Attachment included
  • Federal Authority Advice Record (FAAR) The FAAR must be submitted to the Registry by March 18, 2024. Summit Lake PG LNG Project – JX LNG Canada Ltd. Agency File : 005908 Department/Agency Women and Gender Equality Canada (WAGE) Lead contact Denise Gareau, Director, GBA Plus Directorate, Research, Data, and Intersectionality (RDI) Branch Full address 22 Eddy Street, 10th Floor Gatineau, QC J8X 2V6 Email FEGC.EvaluationImpacts-ImpactsAssessment.WAGE@fegc-wage.gc.ca Telephone 819-938-1132 Alternate Contact Jessica Bialek, A/Senior Analyst, GBA Plus Directorate, Research, Data, and Intersectionality (RDI) Branch Jessica.Bialek@fegc-wage.gc.ca 1. a) Is it probable that your department or agency may be required to exercise a power or perform a duty or function related to the Project to enable it to proceed? If yes, specify the Act of Parliament and that power, duty or function. b) Please describe any Indigenous or public consultation that will be undertaken in relation to the exercise of that power, duty or function, including when it would take place. 1. a) WAGE does not hold any regulatory power, functions, or duties. 1. b) N/A 2. Is your department or agency in possession of specialist or expert information or knowledge in one of your fields of expertise that may be relevant to the conduct of an impact assessment of the Project? Specify the specialist or expert information or knowledge. WAGE holds expertise in the application of GBA Plus (as intersectional analysis) as well as information related to gender equality, including gender-based violence (GBV). 3. Has your department or agency exercised a power or performed a duty or function under any Act of Parliament in relation to ...

Report

Date submitted Display filters

Filters

Consultation typesDisplay filters

Project phaseDisplay filters

Participation noticesDisplay filters