Permits

The dashboard below shows the progress and status of individual permits needed for the project to start construction.


Overview

Timeline

Start date: May 29, 2023 Target completion date: March 31, 2030
In progress 49%
Elapsed Paused To be completed

Total days for process: 2499
Total allocated width: 49%


Start date
May 29, 2023
Target completion date
March 31, 2030

Status of permits
0 out of 5 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Canadian Navigable Waters Authorization, Order in Council Exemption Transport Canada Potential - -
Canadian Navigable Waters Authorization, Work Approvals Transport Canada Potential - -
Fisheries Act Authorization Fisheries and Oceans Canada Potential - -
Metal and Diamond Mining Effluent Regulations Schedule 2 Amendment Environment and Climate Change Canada Potential - -
Project and Environmental Review Permit Saguenay Port Authority Potential - -

For questions or information, please contact:

Permit Coordination
Impact Assessment Agency of Canada
160 Elgin Street, 22nd floor
Ottawa, Ontario K1A 0H3
permit.coordination.permis@iaac-aeic.gc.ca
Date modified: