Permits

The dashboard below shows the progress and status of individual permits needed for the project to start construction.


Overview

Timeline

Start date: July 11, 2025 Target completion date: July 11, 2027
In progress 63%
Elapsed To be completed

Total days for process: 730
Total allocated width: 63%


Start date
July 11, 2025
Target completion date
July 11, 2027

Status of permits
0 out of 2 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Canadian Navigable Waters Authorization, Work Approvals Transport Canada In progress July 11, 2025 -
Fisheries Act Authorization Fisheries and Oceans Canada In progress July 22, 2025 -