Permits

The dashboard below shows the progress and status of individual permits needed for the project to start construction.

Permitting for this project started before the Cabinet Directive was released therefore progress is not displayed against the targets in the Directive.


Start date
June 1, 2022
Completed on
August 9, 2024

Status of permits
2 out of 2 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Canadian Navigable Waters Authorization, Order in Council Exemption Transport Canada Approved June 1, 2022 June 5, 2024
Fisheries Act Authorization Fisheries and Oceans Canada Approved April 21, 2023 August 9, 2024

For questions or information, please contact:

Permit Coordination
Impact Assessment Agency of Canada
160 Elgin Street, 22nd floor
Ottawa, Ontario K1A 0H3
permit.coordination.permis@iaac-aeic.gc.ca
Date modified: