Permits

The Government of Canada is committed to ​improving the efficiency and predictability of regulatory processes ​and to expediting decisions on permits and other authorizations so that projects ​can get built faster while ​advancing reconciliation with Indigenous Peoples and maintaining strong environmental protections.

Below is a dashboard for the project displaying progress against the ​target​s set out in the Cabinet Directive on Regulatory and Permitting Efficiency for Clean Growth Projects, and the status of individual authorizations and permits​ needed for the project to start construction.

Permitting for this project started before the Cabinet Directive was released therefore progress is not displayed against the targets in the Directive.


Start date
September 15, 2021

Status of permits
1 out of 2 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Canadian Navigable Waters Authorization, Order in Council Exemption Transport Canada Approved September 15, 2021 October 25, 2023
Fisheries Act Authorization Fisheries and Oceans Canada In progress December 8, 2023 -

For questions or information, please contact:

Permit Coordination
Impact Assessment Agency of Canada
160 Elgin Street, 22nd floor
Ottawa, Ontario K1A 0H3
permit.coordination.permis@iaac-aeic.gc.ca
Date modified: