Marathon Palladium Project
Permits
The dashboard below shows the progress and status of individual permits needed for the project to start construction.
Permitting for this project started before the Cabinet Directive was released therefore progress is not displayed against the targets in the Directive.
Start date
May 1, 2023
Completed on
August 6, 2024
Status of permits
2 out of 2 completed
Status of permits
The table below is updated on a monthly basis.
| Permits | Authority | Status | Application date | Decision date |
|---|---|---|---|---|
| Metal and Diamond Mining Effluent Regulations Schedule 2 Amendment | Environment and Climate Change Canada | Approved | May 5, 2023 | July 18, 2024 |
| Fisheries Act Authorization | Fisheries and Oceans Canada | Approved | June 1, 2023 | August 6, 2024 |