Document Notice of Substitution Approval under the Impact Assessment Act

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 58
  • Updated: 2022-01-20
  • Document: 142629E.html
  • Relevance: 321.14
  • Notice of Substitution Approval under the Impact Assessment Act The Impact Assessment Agency of Canada (the Agency) has determined that an impact assessment pursuant to the Impact Assessment Act (IAA) is required for the Tilbury Phase 2 LNG Expansion Project (the Project), located in Delta, British Columbia (B.C.). For this project, the Honourable Steven Guilbeault, Minister of Environment and Climate Change, has approved the substitution of the conduct of the impact assessment to B.C. This ...
1 alternate format found
French HTML
  • Relevance: 270.14
  • Avis d'approbation de la substitution en vertu de la Loi sur l'évaluation d'impact L'Agence d'évaluation d'impact du Canada (l'Agence) a déterminé qu'une évaluation d'impact est requise en vertu de la Loi sur l'évaluation d'impact (LÉI) pour le projet d'agrandissement de l'installation de GNL Tilbury — phase 2, situé à Delta, en Colombie-Britannique. Pour ce projet, l'honorable Steven Guilbeault, ministre de l'Environnement et du Changement climatique, a approuvé la substitution de la ...

Document Notice of Impact Assessment Decision with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 53
  • Updated: 2022-01-10
  • Document: 142500E.html
  • Relevance: 320.3
  • Notice of Impact Assessment Decision with Reasons Ottawa — January 10, 2022 — The Impact Assessment Agency of Canada (the Agency) has decided that an impact assessment is required for the Tilbury Phase 2 LNG Expansion Project (the Project), located in Delta, British Columbia. The Project is proposed by FortisBC Holdings Inc. (the Proponent). In accordance with subsection 16(2) of the Impact Assessment Act (IAA), the Agency has taken into account each of the following factors: the ...
1 alternate format found
French HTML
  • Relevance: 269.3
  • Avis de décision d'évaluation d'impact assortie de motifs Ottawa — le 10 janvier 2022 — L'Agence d'évaluation d'impact du Canada (l'Agence) a déterminé qu'une évaluation d'impact est requise pour le projet d'agrandissement de l'installation de GNL Tilbury – phase 2 (le projet) situé à Delta, en Colombie-Britannique. Le projet est proposé par Fortis Holdings Inc. (le promoteur). En vertu du paragraphe 16(2) de la Loi sur l'évaluation d'impact (LEI), l'Agence a pris en compte chacun des ...

Document Summary of the Detailed Project Description of a Designated Project

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 54
  • Updated: 2022-01-10
  • Document: 142512E.pdf
  • Relevance: 320.3
  • Tilbury Phase 2 LNG Expansion Project Detailed Project Description Summary Rev 0 January 2022 Detailed Project Description Summary FES0517201718VBC iii Contents Glossary.............................................................................................................................................................................. vii Acronyms and Abbreviations ...
1 alternate format found
French PDF
  • Relevance: 269.3
  • Projet d’agrandissement de l’installation de GNL Tilbury- phase 2 Résumé de la description détaillée du Projet Rév. 0 Janvier 2022 Résumé de la description détaillée du Projet FES0517201718VBC iii Table des matières Glossaire ............................................................................................................................................................................ vii Acronymes et abréviations ...

Document Notice of Time Limit Resuming

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 52
  • Updated: 2022-01-10
  • Document: 142499E.html
  • Relevance: 320.3
  • Notice of Time Limit Resuming Ottawa — January 10, 2022 — On January 4, 2022, FortisBC Holdings Inc. (the Proponent) provided its response to the Joint Summary of Issues and Engagement, and a detailed description of the Tilbury Phase 2 LNG Expansion Project to the Impact Assessment Agency of Canada (the Agency). On January 10, 2022, the Agency accepted these documents as it determined that they contained the information prescribed by the Information and Management of Time Limits Regulations. ...
1 alternate format found
French HTML
  • Relevance: 269.3
  • Avis de reprise du délai Ottawa — le 10 janvier 2022 — Le 4 janvier 2022 FortisBC Holdings Inc. (le promoteur) a fourni sa réponse au sommaire des questions et une description détaillée du projet d'agrandissement de l'installation de GNL Tilbury – phase 2 à l'Agence d'évaluation d'impact du Canada (l'Agence). Le 10 janvier 2022, l'Agence a accepté ces documents car elle a déterminé qu'ils contenaient les renseignements prescrits par le Règlement sur les renseignements et la gestion des ...

Document Supporting Geospatial Data - Detailed Project Description

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Geospatial data files
  • Reference Number: 59
  • Updated: 2021-12-22
  • Document: 146705E.html
  • Relevance: 318.69
  • Supporting Geospatial Data – Detailed Project Description FortisBC Holdings Inc. has provided electronic geospatial data files related to the Tilbury Phase 2 LNG Expansion Project. The dataset contains the following 25 layers for maps provided in the Detailed Project Description. These data files are available to the public under the terms of the Open Government Licence – Canada. Layer Name Projection (name) Page number Acoustic LAA UTM Zone 10 North. NAD 1983 314 Acoustic RAA UTM Zone ...
1 alternate format found
French HTML
  • Relevance: 267.69
  • Données géospatiales connexes – Description détaillée du projet (angais seulement) FortisBC Holdings inc. a fourni des fichiers électroniques de données géospatiales liées au projet d'agrandissement de l'installation de GNL Tilbury - phase 2. L'ensemble de données contient 25 couches pour les cartes fournies dans la description détaillée du projet. Ces fichiers de données sont mis à la disposition du public selon les termes de la Licence du gouvernement ouvert – Canada. Nom de la ...

Document News Release - Participant Funding Available

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: News Releases
  • Reference Number: 48
  • Updated: 2020-09-16
  • Document: 135996E.html
  • Relevance: 283.06
  • News Release Tilbury Phase 2 LNG Expansion Project — Participant Funding Available September 16, 2020 — Ottawa — Impact Assessment Agency of Canada The Impact Assessment Agency of Canada (the Agency) is making funding available to assist the participation of the public and Indigenous peoples in the federal impact assessment for the proposed Tilbury Phase 2 LNG Expansion Project, located on Tilbury Island, in Delta, British Columbia. Funding is available for eligible individuals and ...
1 alternate format found
French HTML
  • Relevance: 232.06
  • Communiqué de presse Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Disponibilité d'une aide financière aux participants Le 16 septembre 2020 — Ottawa — Agence d'évaluation d'impact du Canada L'Agence d'évaluation d'impact du Canada (l'Agence) annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des peuples autochtones à l'évaluation d'impact fédérale du projet ...

Document Public Notice - Participant Funding Available

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: For Public Participation
  • Reference Number: 47
  • Updated: 2020-09-16
  • Document: 135992E.html
  • Relevance: 283.06
  • Public Notice Tilbury Phase 2 LNG Expansion Project — Participant Funding Available September 16, 2020 — The Impact Assessment Agency of Canada (the Agency) is making funding available to assist the participation of the public and Indigenous peoples in the federal impact assessment for the proposed Tilbury Phase 2 LNG Expansion Project, located on Tilbury Island, in Delta, British Columbia. Funding is available for eligible individuals and groups to assist their participation in upcoming ...
1 alternate format found
French HTML
  • Relevance: 232.06
  • Avis public Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Disponibilité d'une aide financière aux participants Le 16 septembre 2020 — L'Agence d'évaluation d'impact du Canada (l'Agence) annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des peuples autochtones à l'évaluation d'impact fédérale du projet d'agrandissement de l'installation de GNL Tilbury – ...

Document Notice of Time Limit Suspension with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 46
  • Updated: 2020-09-15
  • Document: 135969E.html
  • Relevance: 282.99
  • Notice of Time Limit Suspension with Reasons Ottawa — September 15, 2020 — The Impact Assessment Agency of Canada (the Agency) has suspended the 180-day time limit for the Planning Phase under the Impact Assessment Act for FortisBC Holdings Inc.'s (the proponent) Tilbury Phase 2 LNG Expansion Project. The Agency has taken this action further to a written request from the proponent that the time limit be suspended in order that it may have sufficient time to provide the Agency with: a ...
1 alternate format found
French HTML
  • Relevance: 231.99
  • Avis de suspension de délai avec motifs Ottawa, le 15 septembre 2020 — L'Agence d'évaluation d'impact du Canada (l'Agence) a suspendu le délai de 180 jours prévu pour l'étape préparatoire, en vertu de la Loi sur l'évaluation d'impact, du projet d'agrandissement de l'installation de GNL Tilbury — phase 2 de FortisBC Holdings Inc. (le promoteur). L'Agence a pris cette mesure à la suite d'une demande écrite du promoteur visant à suspendre le délai, afin qu'il ait suffisamment de temps pour lui ...

Document Joint Summary of Issues and Engagement

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 44
  • Updated: 2020-08-14
  • Document: 135764E.pdf
  • Relevance: 280.76
  • - 2 - The guidelines for completing a Detailed Project Description for the EAO are included in the Early Engagement Policy. Under Section 39(a) of the provincial Environmental Assessment Act (2018), FortisBC has up to one year to submit its Detailed Project Description from the issuance of the Joint Summary or the Chief Executive Assessment Officer may terminate the assessment of the Project. The EAO notes that the Detailed Project Description is a foundational document for ...
3 alternate formats found
English HTML
  • Relevance: 280.76
  • Joint Summary of Issues and Engagementt Impact Assessment Agency of Canada Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Agence d'evaluation d'impact du Canada Region du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 Environmental Assessment Office PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 Sent by Email Only   August 14, 2020 Todd Smith Business Development Manager FortisBC Holdings ...
French HTML
  • Relevance: 229.76
  • Résumé conjoint des enjeux et activités de mobilisation Agence d'evaluation d'impact du Canada Region du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 Impact Assessment Agency of Canada Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Environmental Assessment Office PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 Envoi par courriel seulement 14 août 2020 Todd Smith Directeur de la ...
French PDF
  • Relevance: 229.76
  • Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Région du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 14 août 2020 Envoi par courriel seulement Todd Smith Directeur de la prospection FortisBC Holdings Inc. todd.smith@fortisbc.com Numéro de dossier de l’Agence : 005724 Monsieur, Objet : Résumé conjoint des enjeux et ...

Document News Release - Public Comments Invited

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: News Releases
  • Reference Number: 9
  • Updated: 2020-06-01
  • Document: 134892E.html
  • Relevance: 275.72
  • News Release Tilbury Phase 2 LNG Expansion Project — Public Comments Invited June 1st, 2020 — Ottawa — Impact Assessment Agency of Canada The Impact Assessment Agency of Canada (the Agency) has accepted an initial project description for the proposed Tilbury Phase 2 LNG Expansion Project, located on Tilbury Island, in Delta, British Columbia. The unique circumstances arising from COVID-19 have presented challenges to the usual approaches of undertaking meaningful public engagement and ...
1 alternate format found
French HTML
  • Relevance: 224.72
  • Communiqué Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Période de consultation publique 1er juin 2020 — Ottawa — Agence d'évaluation d'impact du Canada L'Agence d'évaluation d'impact du Canada (l'Agence) a accepté une description initiale de projet pour le projet d'agrandissement de l'installation de GNL Tilbury – phase 2, situé sur l'île de Tilbury, à Delta, en Colombie-Britannique. Les circonstances uniques découlant de la crise de la COVID-19 ont présenté des ...

Document Public Notice - Public Comment Period & Virtual Open Houses

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: For Public Participation
  • Reference Number: 8
  • Updated: 2020-06-01
  • Document: 136255E.html
  • Relevance: 275.72
  • Public Notice Tilbury Phase 2 LNG Expansion Project — Public Comment Period & Virtual Open Houses FortisBC Holdings Inc. is proposing to expand its existing Tilbury LNG Project, a liquefied natural gas (LNG) storage and production facility located on Tilbury Island, in Delta, British Columbia. As proposed, the Tilbury Phase 2 LNG Expansion Project would increase the facility's LNG production capacity by more than 50%, up to 13,700 tonnes of LNG per day for an operational life of at least ...
1 alternate format found
French HTML
  • Relevance: 224.72
  • Avis public Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Période de consultation publique et portes ouvertes virtuelles FortisBC Holdings inc. propose l'agrandissement de son projet actuel de GNL Tilbury, une installation de stockage et de production de gaz naturel liquéfié (GNL) située sur l'île de Tilbury à Delta, en Colombie-Britannique. Tel qu'il est proposé, le projet d'agrandissement de l'installation de GNL Tilbury – phase 2 augmenterait la capacité de ...

Document Notice of Time Limit Resumption

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 7
  • Updated: 2020-05-29
  • Document: 134874E.html
  • Relevance: 275.52
  • Notice of Time Limit Resumption Ottawa — May 29, 2020 — On May 28, 2020, the Impact Assessment Agency of Canada (the Agency) resumed the 180-day time limit for the Planning Phase under the Impact Assessment Act for FortisBC Holdings Inc.'s (the proponent) Tilbury Phase 2 LNG Expansion Project. This action is being undertaken cooperatively with British Columbia's Environmental Assessment Office, in support of the Impact Assessment Cooperation Agreement Between Canada and British ...
1 alternate format found
French HTML
  • Relevance: 224.52
  • Avis de reprise du délai Ottawa — 29 mai 2020 — Le 28 mai 2020, l'Agence d'évaluation d'impact du Canada a repris l'échéancier de 180 jours prévu par la Loi sur l'évaluation d'impact, en ce qui a trait à l'étape préparatoire du projet d'agrandissement de l'installation de GNL Tilbury – phase 2 de FortisBC Holdings Inc. (le promoteur). Cette mesure est prise en collaboration avec le Bureau d'évaluation environnementale de la Colombie-Britannique, à l'appui de l'entente de collaboration ...

Document Notice of Time Limit Suspension with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 5
  • Updated: 2020-04-27
  • Document: 134649E.html
  • Relevance: 273.39
  • Notice of Time Limit Suspension with Reasons Ottawa — April 28, 2020 — On April 27, 2020, the Impact Assessment Agency of Canada (the Agency) suspended the 180-day time limit for the Planning Phase under the Impact Assessment Act for FortisBC Holdings Inc.'s (the proponent) Tilbury Phase 2 LNG Expansion Project by an additional 30 days. The timeline was previously suspended on March 27, 2020. The Agency has taken this action further to a written request from the proponent that the time ...
1 alternate format found
French HTML
  • Relevance: 222.39
  • Avis de suspension de délai avec motifs Ottawa — 28 avril 2020 — Le 27 avril 2020, l'Agence d'évaluation d'impact du Canada (l'Agence) a suspendu le délai de 180 jours prévu pour l'étape préparatoire, en vertu de la Loi sur l'évaluation d'impact, du projet d'agrandissement de l'installation de GNL Tilbury - phase 2 de FortisBC Holdings Inc. (le promoteur) pour une durée de 30 jours supplémentaires. Le délai avait préalablement été suspendu le 27 mars 2020. L'Agence a pris cette mesure à la ...

Document Notice of Time Limit Suspension with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 3
  • Updated: 2020-03-31
  • Document: 134501E.html
  • Relevance: 271.62
  • Notice of Time Limit Suspension with Reasons Ottawa — March 31, 2020 — On March 27, 2020, the Impact Assessment Agency of Canada (the Agency) suspended the 180-day time limit for the Planning Phase under the Impact Assessment Act for FortisBC Holdings Inc.'s (the proponent) Tilbury Phase 2 LNG Expansion Project. The Agency has taken this action further to a written request from the proponent that the time limit for the engagement period prior to the start of a public comment period be ...
1 alternate format found
French HTML
  • Relevance: 220.62
  • Avis de suspension de délai avec motifs Ottawa — 31 mars 2020 — Le 27 mars 2020, l'Agence d'évaluation d'impact du Canada (l'Agence) a suspendu le délai de 180 jours prévu pour l'étape préparatoire, en vertu de la Loi sur l'évaluation d'impact, du projet d'agrandissement de l'installation de GNL Tilbury - phase 2 de FortisBC Holdings Inc. (le promoteur). L'Agence a pris cette mesure à la suite d'une demande écrite du promoteur visant à suspendre le délai de la période de mobilisation ...

Document Summary of an Initial Project Description of a Designated Project

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 1
  • Updated: 2020-02-11
  • Document: 133941E.pdf
  • Relevance: 268.47
  • Tilbury Phase 2 LNG Expansion Project Initial Project Description Summary February 2020 Initial Project Description Summary i List of Contributors to the Project Description Contributors Credentials Section(s) Relevant Experience Todd Smith P.Eng. Section 2 (Project Overview) 20+ years experience in engineering, construction and business development for energy projects and utilities Ian Finke P.Eng., MBA Section 2 (Project Overview) 20+ years experience ...
1 alternate format found
French PDF
  • Relevance: 217.47
  • Projet d’agrandissement des installations GNL à Tilbury, phase 2 Description initiale du Projet – Synthèse Février 2020 Description initiale du Projet – Synthèse Février 2020 i Liste des contributeurs à la description du Projet Contributeurs Titres Chapitres Expérience pertinente Todd Smith Ingénieur Chapitre 2 (Aperçu du Projet) Plus de 20 ans d’expérience en ingénierie, construction et développement des affaires dans des projets relatifs aux ...

Refine SearchDisplay Filters