Document Certificate EC-059

  • Project Manitoba-Minnesota Transmission Project
  • Document Category: Additional Information
  • Reference Number: 6
  • Updated: 2019-06-18
  • Document: 130521E.pdf
  • Relevance: 255.43
  • CERTIFICATE EC-059 IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and IN THE MATTER OF the Canadian Environmental Assessment Act, 2012 (CEAA 2012) and the regulations made thereunder; and, IN THE MATTER OF an application dated 16 December 2016 by Manitoba Hydro, for a permit pursuant to section 58.11 of the NEB Act (Application) to construct and operate the Manitoba-Minnesota Transmission Project (Project), which ...
1 alternate format found
French PDF
  • Relevance: 204.43
  • CERTIFICAT EC-059 RELATIVEMENT À la Loi sur l’Office national de l’énergie (la « Loi ») et à ses règlements d’application; RELATIVEMENT À la Loi canadienne sur l’évaluation environnementale (2012) (la « LCEE (2012) ») et à ses règlements d’application; RELATIVEMENT À une demande datée du 16 décembre 2016 que Manitoba Hydro a présentée à l’Office national de l’énergie aux termes de l’article 58.11 de la Loi en vue de la construction et de l’exploitation du projet de ...

Document Hearing Order

  • Project Manitoba-Minnesota Transmission Project
  • Document Category: For Public Participation
  • Reference Number: 4
  • Updated: 2018-01-23
  • Document: 121464E.html
  • Relevance: 230.13
  • The National Energy Board (NEB) will conduct a public hearing for Manitoba Hydro's Manitoba-Minnesota Transmission Project. Indigenous peoples, members of the public and other stakeholders who may be impacted by the project must apply to participate by 7 February 2018. Participant funding is available to cover expenses such as legal or expert fees and travel expenses.   Application to Participate ...
3 alternate formats found
English PDF
  • Relevance: 230.13
  • Manitoba Hydro Manitoba-Minnesota Transmission Project (MMTP) File OF-Fac-IPL-M180-2015-01 02 Hearing Order EH-001-2017 21 December 2017 Hearing Order EH-001-2017 Page 2 Table of Contents 1 This hearing ........................................................................................................................8 1.1 An overview ...
French HTML
  • Relevance: 179.13
  • L'Office national de l'énergie a convoqué une audience publique pour le projet de ligne de transmission d'électricité Manitoba-Minnesota de Manitoba Hydro. Les peuples autochtones, les membres du public et les autres parties prenantes susceptibles d'être touchées par le projet doivent faire une demande de participation au plus tard le 7 février 2018. Une aide ...
French PDF
  • Relevance: 179.13
  • Manitoba Hydro Projet de transport d’électricité Manitoba-Minnesota Dossier OF-Fac-IPL-M180-2015-01 02 Ordonnance d’audience EH-001-2017 21 décembre 2017 Ordonnance d’audience EH-001-2017 Page 2 Table des matières 1.1 Aperçu ......................................................................................................................8 1.2 En quoi consiste la demande présentée par Manitoba Hydro? ...

Document Hearing Order

  • Project Manitoba-Minnesota Transmission Project
  • Document Category: Hearing Documents
  • Reference Number: 3
  • Updated: 2017-12-21
  • Document: 121454E.pdf
  • Relevance: 228.77
  • Manitoba Hydro Manitoba-Minnesota Transmission Project (MMTP) File OF-Fac-IPL-M180-2015-01 02 Hearing Order EH-001-2017 21 December 2017 Hearing Order EH-001-2017 Page 2 Table of Contents 1 This hearing ........................................................................................................................8 1.1 An overview ...
1 alternate format found
French PDF
  • Relevance: 177.77
  • Manitoba Hydro Projet de transport d’électricité Manitoba-Minnesota Dossier OF-Fac-IPL-M180-2015-01 02 Ordonnance d’audience EH-001-2017 21 décembre 2017 Ordonnance d’audience EH-001-2017 Page 2 Table des matières 1.1 Aperçu ......................................................................................................................8 1.2 En quoi consiste la demande présentée par Manitoba Hydro? ...

Document Application to Participate Process

  • Project Manitoba-Minnesota Transmission Project
  • Document Category: News Releases
  • Reference Number: 2
  • Updated: 2017-08-09
  • Document: 119730E.pdf
  • Relevance: 223.57
  • File OF-Fac-IPL-M180-2015-01 02 27 June 2017 Ms. K. Jennifer Moroz Barrister & Solicitor, Law Division Manitoba Hydro 22nd Floor – 360 Portage Avenue Winnipeg, MB R3C 0G8 Facsimile 204-360-6147 Dear Ms. Moroz: Manitoba Hydro Application for Approval of Manitoba-Minnesota Transmission Project (MMTP, the Project) Application by Manitoba Hydro under subsection 58.11 of the National Energy Board Act (NEB Act), and under the Canadian Environmental Assessment Act, ...
3 alternate formats found
English HTML
  • Relevance: 223.57
  • Latest information 27 June 2017: The public can register to participate in the NEB environmental assessment process between 15 July and 15 August 2017. Register to participate – Deadline: 15 August 2017 [Filing A84661] Up to $250,000 is available for eligible participants through the NEB's Participant Funding Program. Apply for participant funding – Deadline: 18 August 2017 The indicated end date for funding applications is only approximate. When the Board sets out the ...
French PDF
  • Relevance: 172.57
  • Dossier OF-Fac-IPL-M180-2015-01 02 Le 27 juin 2017 Maître K. Jennifer Moroz Avocate-procureure à la division du contentieux Manitoba Hydro 360, avenue Portage, 22e étage Winnipeg (Manitoba) R3C 0G8 Télécopieur : 204-360-6147 Manitoba Hydro Demande d’approbation du projet de transport d’électricité Manitoba-Minnesota (le « projet ») présentée par Manitoba Hydro aux termes de l’article 58.11 de la Loi sur l’Office national de l’énergie (la « Loi ») et de la Loi ...
French HTML
  • Relevance: 172.57
  • Plus récentes informations 27 juin 2017 : Les membres du public peuvent déposer une demande de participation à l'évaluation environnementale de l'Office entre le 15 juillet et le 15 août 2017. Faire une demande de participation – date limite : 15 août 2017 [Dépôt A84661] Un montant total maximal de 250 000 $ est disponible pour les participants admissibles par l'entremise du Programme d'aide financière aux participants de l'Office. Faire une demande de fonds – date limite : 18 août ...

Document Decision on Process

  • Project Manitoba-Minnesota Transmission Project
  • Document Category: Additional Information
  • Reference Number: 1
  • Updated: 2017-04-17
  • Document: 118843E.pdf
  • Relevance: 219.57
  • File OF-Fac-IPL-M180-2015-01 02 19 April 2017 Ms. K. Jennifer Moroz Barrister & Solicitor, Law Division Manitoba Hydro 22nd Floor – 360 Portage Avenue Winnipeg, MB R3C 0G8 Facsimile 204-360-6147 Mr. Jason Madden Pape Salter Teillet, LLP 546 Euclid Avenue Toronto, ON M6G 2T2 Facsimile 416-916-3726 Dear Ms. Moroz and Mr. Madden: Manitoba Hydro Application for Approval of Manitoba-Minnesota Transmission Project (MMTP, the Project) Application by Manitoba ...
1 alternate format found
French PDF
  • Relevance: 168.57
  • Dossier OF-Fac-IPL-M180-2015-01 02 Le 19 avril 2017 Maître K. Jennifer Moroz Avocate-procureure à la division du contentieux Manitoba Hydro 360, avenue Portage, 22e étage Winnipeg (Manitoba) R3C 0G8 Télécopieur : 204-360-6147 Maître Jason Madden Pape Salter Teillet, LLP 546, avenue Eulid Toronto (Ontario) M6G 2T2 Télécopieur : 416-916-3726 Manitoba Hydro Demande d’approbation du projet de transport d’électricité Manitoba-Minnesota (le projet) ...