Roberts Bank Terminal 2 Project

Registry Search Mobile

Registry Search

Skip to Filters

4791 results

Document Terms of Reference for the Independent Scientific Body Established by The Impact Assessment Agency of Canada

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 3571
  • Updated: 2024-01-30
  • Document: 155048E.pdf
  • Relevance: 394.53
  • Approved on January 29, 2024 by the Independent Scientific Body 1 TERMS OF REFERENCE FOR THE INDEPENDENT SCIENTIFIC BODY ESTABLISHED BY THE IMPACT ASSESSMENT AGENCY OF CANADA Introduction The Vancouver Fraser Port Authority (VFPA) has proposed the construction and operation of a new three-berth marine container terminal located at Roberts Bank in Delta, British Columbia (the Roberts Bank Terminal 2 Project). The Project underwent a review panel type environmental assessment ...
1 alternate format found
French PDF
  • Relevance: 343.53
  • Approuvé le 29 janvier 2024 par l’organisme scientifique indépendant 1 MANDAT DE L’ORGANISME SCIENTIFIQUE INDÉPENDANT ÉTABLI PAR L’AGENCE D’ÉVALUATION D’IMPACT DU CANADA Introduction L’Administration portuaire Vancouver Fraser a proposé la construction et l’exploitation d’un nouveau terminal maritime à conteneurs avec trois postes de mouillage à Roberts Bank, dans la ville de Delta, en Colombie-Britannique (le projet du Terminal 2 à Roberts Bank). Le projet a fait l’objet ...

Document Independent Scientific Body for the Roberts Bank Terminal 2 Project - Bios of Members

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 3572
  • Updated: 2024-01-19
  • Document: 155049E.pdf
  • Relevance: 393.34
  • Independent Scientific Body for the Roberts Bank Terminal 2 Project BIOS OF MEMBERS (as of Jan 19, 2024) Dr. Kelly Munkittrick CAIP Research Chair in Aquatic Ecosystem Health and Professor Department of Biological Sciences, University of Calgary Kelly Munkittrick is the CAIP Research Chair in Aquatic Ecosystem Health at the University of Calgary since 2019. Previously he was Executive Director of Cold Regions and Water Initiatives at Wilfrid Laurier University, was ...
1 alternate format found
French PDF
  • Relevance: 342.34
  • Organisme scientifique indépendant pour le projet du Terminal 2 à Roberts Bank BIOGRAPHIES DES MEMBRES (au 19 janvier 2024) Kelly Munkittrick Chaire de recherche en santé des écosystèmes aquatiques dans le cadre du Campus Alberta Innovation Program (CAIP) et professeur Département des sciences biologiques, Université de Calgary Kelly Munkittrick est titulaire de la chaire de recherche en santé des écosystèmes aquatiques dans le cadre du CAIP à l’Université de Calgary depuis ...

Document Government response to the Panel Recommendations

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 3561
  • Updated: 2023-04-20
  • Document: 147354E.pdf
  • Relevance: 365.02
  • 1 GOVERNMENT RESPONSE TO THE REVIEW PANEL RECOMMENDATIONS FOR THE PROPOSED ROBERTS BANK TERMINAL 2 PROJECT The Roberts Bank Terminal 2 Project (RBT2, the Project) was assessed by a Review Panel under the Canadian Environmental Assessment Act, 2012. In its final report, the Review Panel made 22 recommendations to the Government of Canada and the Government of British Columbia (BC) regarding the effects of the Project, as well as measures that could improve the conduct of ...
1 alternate format found
French PDF
  • Relevance: 314.02
  • Novembre 2022 1 RÉPONSE PANGOUVERNEMENTALE AUX RECOMMANDATIONS DE LA COMMISSION D’EXAMEN DU PROJET DU TERMINAL 2 À ROBERTS BANK (RBT2) Le projet du terminal 2 à Roberts Bank (RBT2, le projet) a été évalué par une commission d’examen en vertu de la Loi canadienne sur l’évaluation environnementale (2012). Dans son rapport définitif (en anglais seulement), la commission d’examen a fait 22 recommandations au gouvernement du Canada et au gouvernement de la Colombie-Britannique ...

Document Minister's Environmental Assessment Decision Statement

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 3563
  • Updated: 2023-04-20
  • Document: 147433E.html
  • Relevance: 365.02
  • Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 to Vancouver Fraser Port Authority c/o Robin Silvester, President and Chief Executive Officer 100 The Pointe, 999 Canada Place Vancouver, British Columbia V6C 3T4 for the Roberts Bank Terminal 2 Project Description of the Designated Project The Vancouver Fraser Port Authority proposes the construction and operation of a new three-berth marine container terminal located at Roberts Bank ...
3 alternate formats found
English PDF
  • Relevance: 365.02
  • Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 to Vancouver Fraser Port Authority c/o Robin Silvester, President and Chief Executive Officer 100 The Pointe, 999 Canada Place Vancouver, British Columbia V6C 3T4 for the Roberts Bank Terminal 2 Project Description of the Designated Project The Vancouver Fraser Port Authority proposes the construction and operation of a new three-berth marine container terminal ...
French HTML
  • Relevance: 314.02
  • Déclaration de décision Émise aux termes de l'article 54 de la Loi canadienne sur l'évaluation environnementale (2012) à Administration portuaire Vancouver Fraser a/s de Robin Silvester, Président et Chef de la direction 100 La Pointe, 999 place Canada Vancouver (Colombie-Britannique) V6C 3T4 pour le Projet du Terminal 2 à Roberts Bank Description du projet désigné L'Administration portuaire Vancouver Fraser propose la construction et l'exploitation d'un nouveau terminal à ...
French PDF
  • Relevance: 314.02
  • Déclaration de décision Émise aux termes de l’article 54 de la Loi canadienne sur l’évaluation environnementale (2012) à Administration portuaire Vancouver Fraser a/s de Robin Silvester, Président et Chef de la direction 100 La Pointe, 999 place Canada Vancouver (Colombie-Britannique) V6C 3T4 pour le Projet du Terminal 2 à Roberts Bank Description du projet désigné L'Administration portuaire Vancouver Fraser propose la construction et l'exploitation d'un nouveau ...

Document News Release: Environmental Assessment Decision Statement

  • Project Roberts Bank Terminal 2 Project
  • Document Category: News Releases
  • Reference Number: 3564
  • Updated: 2023-04-20
  • Document: 147357E.html
  • Relevance: 365.02
  • News Release Government of Canada Approves Key Roberts Bank Terminal 2 Project in British Columbia, subject to strict conditions to protect the local environment April 20, 2023 — Ottawa —Impact Assessment Agency of Canada Canadians have been clear that they want the Government of Canada to take decisions that protect the environment while building a strong economy, creating jobs and keeping everyday goods and services affordable. Following a robust and science-based environmental ...
1 alternate format found
French HTML
  • Relevance: 314.02
  • Communiqué de presse Le gouvernement du Canada approuve le projet clé du Terminal 2 à Roberts Bank, en Colombie-Britannique, sous réserve de conditions strictes visant à protéger l'environnement local Le 20 avril 2023 - Ottawa - Agence d'évaluation d'impact du Canada Les Canadiens ont clairement indiqué qu'ils souhaitent que le gouvernement du Canada prenne des décisions qui protègent l'environnement tout en bâtissant une économie forte, en créant de bons emplois et en maintenant le prix des ...

Document Crown Consultation and Accommodations Report - Executive Summary

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 3562
  • Updated: 2023-04-20
  • Document: 147355E.pdf
  • Relevance: 365.02
  • Consultation and Accommodation Report – Roberts Bank Terminal 2 February 2023 The Consultation and Accommodation Report (CAR) describes the Government of Canada and the Government of British Columbia’s efforts to consult and, where appropriate, accommodate potential adverse impacts on potential or established Aboriginal or Treaty rights protected under Section 35 of the Constitution Act, 1982, and to engage with Indigenous groups about ...
1 alternate format found
French PDF
  • Relevance: 314.02
  • Rapport sur la consultation et l’accommodement – Terminal 2 à Roberts Bank Février 2023 Le Rapport sur la consultation et l’accommodement décrit les efforts déployés par le gouvernement du Canada et le gouvernement de la Colombie-Britannique pour consulter et, s’il y a lieu, accommoder les effets négatifs potentiels sur les droits ancestraux ou issus de traités, potentiels ou établis, protégés en vertu de l’article 35 de la Loi ...

Document Draft Potential Conditions

  • Project Roberts Bank Terminal 2 Project
  • Document Category: For Public Participation
  • Reference Number: 2086
  • Updated: 2021-12-15
  • Document: 142133E.pdf
  • Relevance: 319.91
  • Potential conditions under the Canadian Environmental Assessment Act, 2012 The Impact Assessment Agency of Canada is contemplating the following potential conditions in relation to the Roberts Bank Terminal 2 Project (the Designated Project) located in British Columbia for recommendation to the Minister of Environment and Climate Change (the Minister) for inclusion in a Decision Statement issued under the Canadian Environmental Assessment Act, 2012. If the Minister decides that the ...
1 alternate format found
French PDF
  • Relevance: 268.91
  • Conditions potentielles en vertu de la Loi canadienne sur l’évaluation environnementale (2012) L’Agence d’évaluation d’impact du Canada envisage de recommander au ministre de l’Environnement et du Changement climatique (le ministre) les conditions potentielles suivantes portant sur le projet du Terminal 2 à Roberts Bank (le projet désigné) situé en Colombie-Britannique, en vue de leur inclusion dans une déclaration de décision rendue en vertu de la Loi canadienne sur l’évaluation ...

Document Public Notice - Public Comments Invited on Additional Information and Potential Conditions

  • Project Roberts Bank Terminal 2 Project
  • Document Category: For Public Participation
  • Reference Number: 2085
  • Updated: 2021-12-15
  • Document: 142782E.html
  • Relevance: 319.91
  • Public Notice Roberts Bank Terminal 2 Project Public Comments Invited on Additional Information and Potential Conditions   February 9, 2022 — The deadline to submit written comments has been extended from February 13, 2022, to March 15, 2022. What is happening? December 15, 2021 — The Impact Assessment Agency of Canada (the Agency) is holding a public comment period as part of the environmental assessment for the Roberts Bank Terminal 2 Project, a proposed three-berth marine ...
1 alternate format found
French HTML
  • Relevance: 268.91
  • Avis public Projet du Terminal 2 à Roberts Bank Période de consultation publique sur les renseignements supplémentaires et les conditions potentielles   9 février 2022 — La date limite pour présenter des commentaires écrits a été reportée du 13 février 2022 au 15 mars 2022. Que se passe-t-il ? 15 décembre 2021 — L'Agence d'évaluation d'impact du Canada (l'Agence) lance une période de consultation publique dans le cadre de l'évaluation environnementale du projet du Terminal 2 à ...

Document From Vancouver Fraser Port Authority to Impact Assessment Agency of Canada re: Response to Information Requests

  • Project Roberts Bank Terminal 2 Project
  • Document Category: Additional Information
  • Reference Number: 2083
  • Updated: 2021-09-24
  • Document: 142382E.html
  • Relevance: 313.08
  • From Vancouver Fraser Port Authority to Impact Assessment Agency of Canada re: Response to Information Requests Cover Letter (PDF - 150 KB) November 4, 2021 - Errata (PDF - 353 KB) Executive Summary (PDF - 497 KB) Concordance Table (PDF - 125 KB) IR 1.1 IR 1.1 (PDF - 2 MB) IR 1.1 Appendix A part 1 (PDF - 48 MB) IR 1.1 Appendix A part 2 (PDF - 82 MB) IR 1.1 Appendix A part 3 (PDF - 63 MB) IR 1.1 Appendix A part 4 (PDF - 94 MB) IR 1.1 Appendices B to D (PDF - 553 KB) IR ...
1 alternate format found
French HTML
  • Relevance: 262.08
  • De l'administration portuaire Vancouver-Fraser à l'agence d'évaluation d'impact du Canada concernant les réponses aux demandes d'informations Lettre d'accompagnement (PDF - 150 KB) (anglais seulement) 4 novembre 2021 - Errata (PDF - 353 KB) (anglais seulement) Résumé (PDF - 497 KB) Table de concordance (PDF - 125 KB) (anglais seulement) IR 1.1 IR 1.1 (PDF - 2 MB) (anglais seulement) IR 1.1 Appendix A part 1 (PDF - 48 MB) (anglais seulement) IR 1.1 Appendix A part 2 (PDF - 82 ...

Refine SearchDisplay Filters

Last UpdatedDisplay Filters

Filters

Date modified: