Document Notice of Impact Assessment Decision with Reasons

  • Project Cando Sturgeon Rail Terminal West Expansion Project
  • Document Category: Additional Information
  • Reference Number: 26
  • Document Date: 2024-08-02
  • Document: 158337E.html
  • Relevance: 328.75
  • Notice of Impact Assessment Decision with Reasons August 2, 2024: The Impact Assessment Agency of Canada is posting this Notice of Decision in accordance with the Notice of Transition. Ottawa — August 2, 2024 — The Impact Assessment Agency of Canada (IAAC) decided that an impact assessment is not required for the Cando Sturgeon Rail Terminal West Expansion Project (the project) located in Alberta, proposed by Cando Rail and Terminals Ltd. (the proponent). On June 14, 2024, ...
1 alternate format found
French HTML
  • Relevance: 277.75
  • Avis de décision relative à une évaluation d'impact avec motifs Le 2 août 2024 : L'Agence d'évaluation d'impact du Canada affiche cet avis de décision conformément à l'avis de transition. Ottawa — Le 2 août 2024 — L'Agence d'évaluation d'impact du Canada (l'AEIC) a décidé qu'une évaluation d'impact n'est pas requise pour le projet d'agrandissement ouest du terminal ferroviaire de Cando Sturgeon (le projet) situé en Alberta, proposé par Cando Rail and Terminals Ltd. (le ...

Document Notice of Agency's Opinion on Whether an Impact Assessment is Required

  • Project Cando Sturgeon Rail Terminal West Expansion Project
  • Document Category: Additional Information
  • Reference Number: 22
  • Document Date: 2024-06-14
  • Document: 157658E.html
  • Relevance: 324.49
  • Notice of Agency's Opinion on Whether an Impact Assessment is Required June 14, 2024 — The Impact Assessment Agency of Canada (the Agency) is of the opinion that an impact assessment is not required for the Cando Sturgeon Rail Terminal West Expansion Project (the project) proposed by Cando Rail and Terminals Ltd. (the proponent), located in Alberta. In applying the measures outlined in the Statement on the Interim Administration of the Impact Assessment Act Pending Legislative ...
1 alternate format found
French HTML
  • Relevance: 273.49
  • Avis d'opinion sur la nécessité d'une évaluation d'impact 14 juin 2024 — L'Agence d'évaluation d'impact du Canada (l'Agence) est d'avis qu'une évaluation d'impact n'est pas requise pour le projet d'agrandissement ouest du terminal ferroviaire de Cando Sturgeon (le projet) proposé par Cando Rail and Terminals Ltd. (le promoteur), situé en Alberta. En application des mesures décrites dans la Déclaration sur les dispositions provisoires relatives à l'administration de la Loi sur ...

Document Summary of the Detailed Project Description of a Designated Project

  • Project Cando Sturgeon Rail Terminal West Expansion Project
  • Document Category: Additional Information
  • Reference Number: 23
  • Document Date: 2024-05-24
  • Document: 157659E.pdf
  • Relevance: 322.69
  • File CG3821 Cando Rail & Terminals Cando Sturgeon Rail Terminal West Expansion Summary of the Detailed Project Description Under the Impact Assessment Act N ½ 34-55-22-W4M Sturgeon County, Alberta Clifton Engineering Group Inc. www.clifton.ca 10509 - 46 Street SE, Calgary, AB T2C 5C2 T (403) 263-2556 Document Cover Sheet – Form 01075-D01 24 May 2024 File CG3821 Cando Rail & Terminals Cando Sturgeon Rail Terminal West Expansion Summary of the Detailed ...
1 alternate format found
French PDF
  • Relevance: 271.69
  • Dossier CG3821 Cando Rail & Terminals Résumé de la description detailée du projet d’agrandissement à l’ouest du terminal ferroviaire de Cando Sturgeon en vertu de la Loi sur l’évaluation d’impact N ½ 34-55-22-W4M Comté de Sturgeon, Alberta Clifton Engineering Group Inc. www.clifton.ca 10509 - 46 Street SE, Calgary, AB T2C 5C2 Tél. : 403 263-2556 Page de couverture du document – Formulaire 01075-D01 24 mai 2024 Dossier CG3821 Cando Rail & Terminals ...

Document Summary of Issues

  • Project Cando Sturgeon Rail Terminal West Expansion Project
  • Document Category: Additional Information
  • Reference Number: 21
  • Document Date: 2024-04-12
  • Document: 157221E.pdf
  • Relevance: 319.13
  • April 12, 2024 — CANDO STURGEON RAIL TERMINAL WEST EXPANSION PROJECT — SUMMARY OF ISSUES – PAGE 1 OF 3 SUMMARY OF ISSUES – Cando Sturgeon Rail Terminal West Expansion This document provides a high-level summary of issues that were submitted to the Impact Assessment Agency of Canada (the Agency) about the Cando Sturgeon Rail Terminal West Expansion (the Project) during the public comment period on the Summary of the Initial Project Description (IPD), submitted by Cando Rail and ...
1 alternate format found
French PDF
  • Relevance: 268.13
  • 12 avril 2024 — PROJET D’AGRANDISSEMENT OUEST DU TERMINAL FERROVIAIRE DE CANDO STURGEON — SOMMAIRE DES QUESTIONSS – PAGE 1 DE 4 SOMMAIRE DES QUESTIONS – Agrandissement ouest du terminal ferroviaire de Cando Sturgeon Le présent document fournit un résumé général des questions qui ont été présentées à l’Agence d’évaluation d’impact du Canada (l’Agence) au sujet du projet d’agrandissement ouest du terminal ferroviaire de Cando Sturgeon (le projet) pendant la période de consultation ...

Document Summary of the Initial Project Description of a designated project

  • Project Cando Sturgeon Rail Terminal West Expansion Project
  • Document Category: For Public Participation
  • Reference Number: 2
  • Document Date: 2024-03-04
  • Document: 155805E.pdf
  • Relevance: 315.86
  • File CG3821 Cando Rail & Terminals Cando Sturgeon Rail Terminal West Expansion Summary Project Description Under the Impact Assessment Act N ½ 34-55-22-W4M Sturgeon County, Alberta Clifton Engineering Group Inc. www.clifton.ca 10509 - 46 Street SE, Calgary, AB T2C 5C2 T (403) 263-2556 Document Cover Sheet – Form 01075-D01 12 February 2024 File CG3821 Cando Rail & Terminals Cando Sturgeon Rail Terminal West Expansion Summary Initial Project ...
1 alternate format found
French PDF
  • Relevance: 264.86
  • Cando Rail & Terminals Description initiale du projet d’agrandissement àl’ouest du terminal ferroviaire de Cando Sturgeon en vertu de la Loi sur l’évaluation d’impact N ½ 34-55-22-W4M Comté de Sturgeon, Alberta Dossier CG3821 Clifton Engineering Group Inc. www.clifton.ca 10509 - 46 Street SE, Calgary, AB T2C 5C2 Tél. : 403 263-2556 Page de couverture du document – Formulaire 01075-D01 23 Février 2024 Dossier CG3821 Cando Rail & Terminals ...