Document Executive summary

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 63
  • Document Date: 2026-09-20
  • Document: 168237E.html
  • Relevance: 395.1
  • Executive Summary Overview of the Assessment Report This Assessment Report (Report) summarizes the findings and recommendations of the environmental assessment (EA) for the Tilbury Phase 2 Liquefied Natural Gas (LNG) Expansion Project (Tilbury Phase 2 or the Project), an expansion of an existing LNG production and storage facility proposed by FortisBC Holdings Inc. (FortisBC or the Proponent), with its natural gas subsidiary FortisBC Energy Inc. (collectively referred to as FortisBC or ...
3 alternate formats found
English PDF
  • Relevance: 395.1
  • EXECUTIVE SUMMARY Overview of the Assessment Report This Assessment Report (Report) summarizes the findings and recommendations of the environmental assessment (EA) for the Tilbury Phase 2 Liquefied Natural Gas (LNG) Expansion Project (Tilbury Phase 2 or the Project), an expansion of an existing LNG production and storage facility proposed by FortisBC Holdings Inc. (FortisBC or the Proponent), with its natural gas subsidiary FortisBC Energy Inc. (collectively referred to as FortisBC or ...
French PDF
  • Relevance: 344.1
  • RÉSUMÉ EXÉCUTIF Aperçu du rapport d’évaluation Le présent rapport d’évaluation (le « rapport ») résume les constatations et les recommandations de l’évaluation environnementale (EE) du projet d’agrandissement de l’installation de gaz naturel liquéfié (GNL) Tilbury Phase 2 (« la Phase 2 de Tilbury » ou le « projet »), soit l’agrandissement d’une installation existante de production et d’entreposage de GNL proposée par FortisBC Holdings Inc. (« FortisBC » ou le « promoteur »), ainsi ...
French HTML
  • Relevance: 344.1
  • Résumé exécutif Aperçu du rapport d'évaluation Le présent rapport d'évaluation (le « rapport ») résume les constatations et les recommandations de l'évaluation environnementale (EE) du projet d'agrandissement de l'installation de gaz naturel liquéfié (GNL) Tilbury Phase 2 (« la Phase 2 de Tilbury » ou le « projet »), soit l'agrandissement d'une installation existante de production et d'entreposage de GNL proposée par FortisBC Holdings Inc. (« FortisBC » ou le « promoteur »), ainsi que ...

Document Impact assessment decision statement

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 65
  • Document Date: 2026-09-20
  • Document: 168079E.html
  • Relevance: 395.1
  • Decision Statement Issued under Section 65 of the Impact Assessment Act to FortisBC Holdings Inc. c/o Roger Dall'Antonia, President and Chief Executive Officer 16705 Fraser Highway Surrey, British Columbia V4N 0E8 for the Tilbury Phase 2 LNG Expansion Project FortisBC Holdings Inc. (the Proponent) is proposing the construction, operation and decommissioning of a liquefied natural gas (LNG) production facility, associated storage tank, and supporting infrastructure on ...
3 alternate formats found
English PDF
  • Relevance: 395.1
  • Page 1 of 17 Decision Statement Issued under Section 65 of the Impact Assessment Act to FortisBC Holdings Inc. c/o Roger Dall’Antonia, President and Chief Executive Officer 16705 Fraser Highway Surrey, British Columbia V4N 0E8 for the Tilbury Phase 2 LNG Expansion Project FortisBC Holdings Inc. (the Proponent) is proposing the construction, operation and decommissioning of a liquefied natural gas (LNG) production facility, associated storage tank, and supporting ...
French HTML
  • Relevance: 344.1
  • Déclaration de décision Émise aux termes de l'article 65 de la Loi sur l'évaluation d'impact à FortisBC Holdings Inc. a/s Roger Dall'Antonia, Président et chef de la direction 16705 Fraser Highway Surrey (Colombie-Britannique) V4N 0E8 pour le Projet d'agrandissement de l'installation de GNL Tilbury - phase 2 FortisBC Holdings Inc. (le promoteur) propose la construction, l'exploitation et la désaffectation d'une installation de production de gaz naturel liquéfié (GNL), ...
French PDF
  • Relevance: 344.1
  • Page 1 de 18 Déclaration de décision Émise aux termes de l’article 65 de la Loi sur l’évaluation d’impact à FortisBC Holdings Inc. a/s Roger Dall’Antonia, Président et chef de la direction 16705 Fraser Highway Surrey (Colombie-Britannique) V4N 0E8 pour le Projet d’agrandissement de l’installation de GNL Tilbury - phase 2 FortisBC Holdings Inc. (le promoteur) propose la construction, l’exploitation et la désaffectation d’une installation de production de gaz ...

Document News release – Major milestone completed

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: News Releases
  • Reference Number: 64
  • Document Date: 2026-09-20
  • Document: 168000E.html
  • Relevance: 395.1
  • News release Major milestone completed September 21, 2026 — Ottawa — Impact Assessment Agency of Canada Today, the Honourable Julie Dabrusin, Minister of the Environment, Climate Change and Nature, issued her decision statement for the Tilbury Phase 2 LNG Expansion Project (the project), determining that the project's potential adverse effects within federal jurisdiction are justified when taking into account the benefits it will provide. The project, proposed by FortisBC ...
1 alternate format found
French HTML
  • Relevance: 344.1
  • Communiqué de presse Une étape majeure a été franchie 21 septembre 2026 — Ottawa — Agence d'évaluation d'impact du Canada Aujourd'hui, l'honorable Julie Dabrusin, ministre de l'Environnement, du Changement climatique et de la Nature, a publié sa déclaration de décision concernant le projet d'agrandissement de l'installation de GNL Tilbury – phase 2 (le projet). La ministre a estimé dans sa déclaration que les effets négatifs potentiels du projet relevant d'un domaine de compétence ...

Document Notice of Substitution Approval under the Impact Assessment Act

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 60
  • Document Date: 2024-08-13
  • Document: 158529E.html
  • Relevance: 321.04
  • August 14, 2024: The Impact Assessment Agency of Canada is reposting this Notice of Substitution Approval under the Impact Assessment Act in accordance with the Notice of Transition. Notice of Substitution Approval under the Impact Assessment Act Ottawa — August 14, 2024 — On January 20, 2022, the Impact Assessment Agency of Canada (IAAC) determined that an impact assessment pursuant to the Impact Assessment Act (the IAA) is required for the Tilbury Phase 2 LNG Expansion Project ...
1 alternate format found
French HTML
  • Relevance: 270.04
  • Le 14 août 2024 : L'Agence d'évaluation d'impact du Canada a réaffiché la décision concernant la substitution conformément à l'avis de transition. Avis d'approbation de la substitution en vertu de la Loi sur l'évaluation d'impact Ottawa — Le 14 août 2024 — Le 20 janvier 2022, l'Agence d'évaluation d'impact du Canada (l'AEIC) a déterminé qu'une évaluation d'impact est requise en vertu de la Loi sur l'évaluation d'impact (la LEI) pour le projet d'agrandissement de l'installation de ...

Document Notice of Transition to the Amended Impact Assessment Act

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 61
  • Document Date: 2024-08-13
  • Document: 158460E.html
  • Relevance: 321.04
  • Notice of Transition to the Amended Impact Assessment Act   Ottawa — August 14, 2024 — On June 20, 2024, the Budget Implementation Act, 2024, No. 1 received Royal Assent and brought into force amendments to the Impact Assessment Act (the IAA). Transitional provision 305 of the Budget Implementation Act, 2024, No. 1 states that, in order to bring a designated project under the IAA, the Minister of Environment and Climate Change or the Impact Assessment Agency of Canada (IAAC) must take a ...
1 alternate format found
French HTML
  • Relevance: 270.04
  • Avis de transition à la Loi sur l'évaluation d'impact modifiée   Ottawa — Le 14 août 2024 — Le 20 juin 2024, la Loi no 1 d'exécution du budget de 2024 a reçu la sanction royale entraînant ainsi l'entrée en vigueur des modifications apportées à la Loi sur l'évaluation d'impact (la LEI). La disposition transitoire 305 de la Loi no 1 d'exécution du budget de 2024 stipule que, pour qu'un projet soit désigné en vertu de la LEI, le ministre de l'Environnement et du Changement climatique ou ...

Document Notice of Substitution Approval under the Impact Assessment Act

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 58
  • Document Date: 2022-01-19
  • Document: 142629E.html
  • Relevance: 254.67
  • Notice of Substitution Approval under the Impact Assessment Act The Impact Assessment Agency of Canada (the Agency) has determined that an impact assessment pursuant to the Impact Assessment Act (IAA) is required for the Tilbury Phase 2 LNG Expansion Project (the Project), located in Delta, British Columbia (B.C.). For this project, the Honourable Steven Guilbeault, Minister of Environment and Climate Change, has approved the substitution of the conduct of the impact assessment to B.C. ...
1 alternate format found
French HTML
  • Relevance: 203.67
  • Avis d'approbation de la substitution en vertu de la Loi sur l'évaluation d'impact L'Agence d'évaluation d'impact du Canada (l'Agence) a déterminé qu'une évaluation d'impact est requise en vertu de la Loi sur l'évaluation d'impact (LÉI) pour le projet d'agrandissement de l'installation de GNL Tilbury — phase 2, situé à Delta, en Colombie-Britannique. Pour ce projet, l'honorable Steven Guilbeault, ministre de l'Environnement et du Changement climatique, a approuvé la substitution de la ...

Document Notice of Impact Assessment Decision with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 53
  • Document Date: 2022-01-09
  • Document: 142500E.html
  • Relevance: 254.1
  • Notice of Impact Assessment Decision with Reasons Ottawa — January 10, 2022 — The Impact Assessment Agency of Canada (the Agency) has decided that an impact assessment is required for the Tilbury Phase 2 LNG Expansion Project (the Project), located in Delta, British Columbia. The Project is proposed by FortisBC Holdings Inc. (the Proponent). In accordance with subsection 16(2) of the Impact Assessment Act (IAA), the Agency has taken into account each of the following ...
1 alternate format found
French HTML
  • Relevance: 203.1
  • Avis de décision d'évaluation d'impact assortie de motifs Ottawa — le 10 janvier 2022 — L'Agence d'évaluation d'impact du Canada (l'Agence) a déterminé qu'une évaluation d'impact est requise pour le projet d'agrandissement de l'installation de GNL Tilbury – phase 2 (le projet) situé à Delta, en Colombie-Britannique. Le projet est proposé par Fortis Holdings Inc. (le promoteur). En vertu du paragraphe 16(2) de la Loi sur l'évaluation d'impact (LEI), l'Agence a pris en compte chacun des ...

Document Summary of the Detailed Project Description of a Designated Project

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 54
  • Document Date: 2022-01-09
  • Document: 142512E.pdf
  • Relevance: 254.1
  • Tilbury Phase 2 LNG Expansion Project Detailed Project Description Summary Rev 0 January 2022 Detailed Project Description Summary FES0517201718VBC iii Contents Glossary.............................................................................................................................................................................. vii Acronyms and Abbreviations ...
1 alternate format found
French PDF
  • Relevance: 203.1
  • Projet d’agrandissement de l’installation de GNL Tilbury- phase 2 Résumé de la description détaillée du Projet Rév. 0 Janvier 2022 Résumé de la description détaillée du Projet FES0517201718VBC iii Table des matières Glossaire ............................................................................................................................................................................ vii Acronymes et abréviations ...

Document Notice of Time Limit Resuming

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 52
  • Document Date: 2022-01-09
  • Document: 157891E.html
  • Relevance: 254.1
  • Notice of Time Limit Resuming Ottawa — January 10, 2022 — On January 4, 2022, FortisBC Holdings Inc. (the Proponent) provided its response to the Joint Summary of Issues and Engagement, and a detailed description of the Tilbury Phase 2 LNG Expansion Project to the Impact Assessment Agency of Canada (the Agency). On January 10, 2022, the Agency accepted these documents as it determined that they contained the information prescribed by the Information and Management of Time Limits ...
1 alternate format found
French HTML
  • Relevance: 203.1
  • Avis de reprise du délai Ottawa — le 10 janvier 2022 — Le 4 janvier 2022 FortisBC Holdings Inc. (le promoteur) a fourni sa réponse au sommaire des questions et une description détaillée du projet d'agrandissement de l'installation de GNL Tilbury – phase 2 à l'Agence d'évaluation d'impact du Canada (l'Agence). Le 10 janvier 2022, l'Agence a accepté ces documents car elle a déterminé qu'ils contenaient les renseignements prescrits par le Règlement sur les renseignements et la gestion des ...

Document Supporting Geospatial Data - Detailed Project Description

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Geospatial data files
  • Reference Number: 59
  • Document Date: 2021-12-21
  • Document: 146705E.html
  • Relevance: 253.04
  • Supporting Geospatial Data – Detailed Project Description FortisBC Holdings Inc. has provided electronic geospatial data files related to the Tilbury Phase 2 LNG Expansion Project. The dataset contains the following 25 layers for maps provided in the Detailed Project Description. These data files are available to the public under the terms of the Open Government Licence – Canada. Layer Name Projection (name) Page number Acoustic LAA UTM ...
1 alternate format found
French HTML
  • Relevance: 202.04
  • Données géospatiales connexes – Description détaillée du projet (angais seulement) FortisBC Holdings inc. a fourni des fichiers électroniques de données géospatiales liées au projet d'agrandissement de l'installation de GNL Tilbury - phase 2. L'ensemble de données contient 25 couches pour les cartes fournies dans la description détaillée du projet. Ces fichiers de données sont mis à la disposition du public selon les termes de la Licence du gouvernement ouvert – Canada. Nom ...

Document News Release - Participant Funding Available

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: News Releases
  • Reference Number: 48
  • Document Date: 2020-09-15
  • Document: 135996E.html
  • Relevance: 230.42
  • News Release Tilbury Phase 2 LNG Expansion Project — Participant Funding Available September 16, 2020 — Ottawa — Impact Assessment Agency of Canada The Impact Assessment Agency of Canada (the Agency) is making funding available to assist the participation of the public and Indigenous peoples in the federal impact assessment for the proposed Tilbury Phase 2 LNG Expansion Project, located on Tilbury Island, in Delta, British Columbia. Funding is available for eligible individuals ...
1 alternate format found
French HTML
  • Relevance: 179.42
  • Communiqué de presse Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Disponibilité d'une aide financière aux participants Le 16 septembre 2020 — Ottawa — Agence d'évaluation d'impact du Canada L'Agence d'évaluation d'impact du Canada (l'Agence) annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des peuples autochtones à l'évaluation d'impact fédérale du ...

Document Public Notice - Participant Funding Available

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: For Public Participation
  • Reference Number: 47
  • Document Date: 2020-09-15
  • Document: 135992E.html
  • Relevance: 230.42
  • Public Notice Tilbury Phase 2 LNG Expansion Project — Participant Funding Available September 16, 2020 — The Impact Assessment Agency of Canada (the Agency) is making funding available to assist the participation of the public and Indigenous peoples in the federal impact assessment for the proposed Tilbury Phase 2 LNG Expansion Project, located on Tilbury Island, in Delta, British Columbia. Funding is available for eligible individuals and groups to assist their participation in ...
1 alternate format found
French HTML
  • Relevance: 179.42
  • Avis public Projet d'agrandissement de l'installation de GNL Tilbury – phase 2 — Disponibilité d'une aide financière aux participants Le 16 septembre 2020 — L'Agence d'évaluation d'impact du Canada (l'Agence) annonce la disponibilité d'une aide financière offerte dans le cadre du Programme d'aide financière aux participants pour favoriser la participation du public et des peuples autochtones à l'évaluation d'impact fédérale du projet d'agrandissement de l'installation de GNL Tilbury – ...

Document Notice of Time Limit Suspension with Reasons

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 46
  • Document Date: 2020-09-14
  • Document: 135969E.html
  • Relevance: 230.37
  • Notice of Time Limit Suspension with Reasons Ottawa — September 15, 2020 — The Impact Assessment Agency of Canada (the Agency) has suspended the 180-day time limit for the Planning Phase under the Impact Assessment Act for FortisBC Holdings Inc.'s (the proponent) Tilbury Phase 2 LNG Expansion Project. The Agency has taken this action further to a written request from the proponent that the time limit be suspended in order that it may have sufficient time to provide the Agency ...
1 alternate format found
French HTML
  • Relevance: 179.37
  • Avis de suspension de délai avec motifs Ottawa, le 15 septembre 2020 — L'Agence d'évaluation d'impact du Canada (l'Agence) a suspendu le délai de 180 jours prévu pour l'étape préparatoire, en vertu de la Loi sur l'évaluation d'impact, du projet d'agrandissement de l'installation de GNL Tilbury — phase 2 de FortisBC Holdings Inc. (le promoteur). L'Agence a pris cette mesure à la suite d'une demande écrite du promoteur visant à suspendre le délai, afin qu'il ait suffisamment de temps pour ...

Document Joint Summary of Issues and Engagement

  • Project Tilbury Phase 2 LNG Expansion Project
  • Document Category: Additional Information
  • Reference Number: 44
  • Document Date: 2020-08-13
  • Document: 135764E.pdf
  • Relevance: 229.04
  • - 2 - The guidelines for completing a Detailed Project Description for the EAO are included in the Early Engagement Policy. Under Section 39(a) of the provincial Environmental Assessment Act (2018), FortisBC has up to one year to submit its Detailed Project Description from the issuance of the Joint Summary or the Chief Executive Assessment Officer may terminate the assessment of the Project. The EAO notes that the Detailed Project Description is a foundational document for ...
3 alternate formats found
English HTML
  • Relevance: 229.04
  • Joint Summary of Issues and Engagementt Impact Assessment Agency of Canada Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Agence d'evaluation d'impact du Canada Region du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 Environmental Assessment Office PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 Sent by Email Only   August 14, 2020 Todd Smith Business ...
French PDF
  • Relevance: 178.04
  • Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Région du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 14 août 2020 Envoi par courriel seulement Todd Smith Directeur de la prospection FortisBC Holdings Inc. todd.smith@fortisbc.com Numéro de dossier de l’Agence : 005724 Monsieur, Objet : Résumé conjoint des enjeux et ...
French HTML
  • Relevance: 178.04
  • Résumé conjoint des enjeux et activités de mobilisation Agence d'evaluation d'impact du Canada Region du Pacifique et du Yukon 757 rue Hastings Ouest bureau 210A Vancouver (C-B) V6C 3M2 Impact Assessment Agency of Canada Pacific and Yukon Region 757 West Hastings Street Suite 201A Vancouver BC V6C 3M2 Environmental Assessment Office PO Box 9426 Stn Prov Govt Victoria BC V8W 9V1 Envoi par courriel seulement 14 août 2020 Todd ...

Refine SearchDisplay Filters

Last ModifiedDisplay Filters

Filters

Key Document Display Filters

Date modified: