Marshdale Natural Gas Power Generation Facility Project

Registry Search Mobile

Registry Search

Skip to Filters

11 results

Document Notice of Early Decision with Reasons

  • Project Marshdale Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 35
  • Document Date: 2026-05-15
  • Document: 166495E.html
  • Relevance: 389.72
  • Notice of Early Decision with Reasons Ottawa – May 15, 2026 – The Impact Assessment Agency of Canada (IAAC) has conducted an assessment of the Marshdale Natural Gas Power Generation Facility Project (the project) and on May 14, 2026, decided at an early stage that no further assessment is required for the project proposed by IESO Nova Scotia, the province's Independent Energy System Operator (the proponent), located in Nova Scotia. In accordance with subsection 16(2) of the Impact ...
1 alternate format found
French HTML
  • Relevance: 338.72
  • Avis de décision avec motifs tôt dans le processus Ottawa – 15 mai 2026 – L'Agence d'évaluation d'impact du Canada (AEIC) a réalisé une évaluation d'impact du projet de centrale électrique au gaz naturel Marshdale (le projet) et le 14 mai 2026 a décidé, tôt dans le processus, qu'aucune évaluation supplémentaire n'est requise pour le projet proposé par IESO Nova Scotia, l'exploitant indépendant du système d'énergie de la province (le promoteur) situé en Nouvelle-Écosse. Conformément au ...

Document Notice of time limit resumption

  • Project Marshdale Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 34
  • Document Date: 2026-05-07
  • Document: 166412E.html
  • Relevance: 388.87
  • Notice of Time Limit Resumption Ottawa — May 7, 2026 — On May 5, 2026, IESO Nova Scotia, the province's Independent Energy System Operator (the proponent), provided its Response to the Summary of Issues for the Marshdale Natural Gas Power Generation Facility Project (the project) to the Impact Assessment Agency of Canada (IAAC). On May 6, 2026, IAAC determined that this document contains sufficient information to inform its decision under section 16 of the Impact Assessment Act regarding ...
1 alternate format found
French HTML
  • Relevance: 337.87
  • Avis de reprise du délai Ottawa — 7 mai 2026 — Le 5 mai 2026, IESO Nova Scotia, l'exploitant indépendant du système d'énergie de la province (le promoteur), a fourni sa réponse au sommaire des questions (en anglais seulement) pour le projet de centrale électrique au gaz naturel Marshdale (le projet) à l'Agence d'évaluation d'impact du Canada (AEIC). Le 6 mai 2026, l'AEIC a déterminé que ce document contient suffisamment de renseignements pour éclairer sa décision en vertu de l'article 16 de ...

Document Notice of time limit suspension with reasons

  • Project Marshdale Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 31
  • Document Date: 2026-03-13
  • Document: 165133E.html
  • Relevance: 383.07
  • Notice of time limit suspension with reasons Ottawa — March 13, 2026 — On March 11, 2026, the Impact Assessment Agency of Canada (IAAC) suspended the 180-day time limit for the planning phase under the Impact Assessment Act for the Marshdale Natural Gas Power Generation Facility Project proposed by IESO Nova Scotia, the province's Independent Energy System Operator (the proponent). IAAC has taken this action in consideration of a written request from the proponent that the time limit be ...
1 alternate format found
French HTML
  • Relevance: 332.07
  • Avis de suspension de délai avec motifs Ottawa — 13 mars 2026 — Le 11 mars 2026, l'Agence d'évaluation d'impact du Canada (AEIC) a suspendu le délai de 180 jours pour l'étape préparatoire en vertu de la Loi sur l'évaluation d'impact pour le projet de centrale électrique au gaz naturel Marshdale, proposé par IESO Nova Scotia, l'exploitant indépendant du système d'énergie de la province (le promoteur). L'AEIC a pris cette mesure à la suite d'une demande écrite du promoteur (anglais ...

Document Summary of Issues

  • Project Marshdale Natural Gas Power Generation Facility Project
  • Document Category: Additional Information
  • Reference Number: 30
  • Document Date: 2026-02-19
  • Document: 165065E.pdf
  • Relevance: 380.78
  • 1 Summary of Issues Marshdale Natural Gas Power Generation Facility Project The Summary of Issues outlines the key issues that the Impact Assessment Agency of Canada (IAAC) considers relevant for the federal impact assessment process for the Marshdale Natural Gas Power Generation Facility Project (the project). The proponent’s response to the Summary of Issues will support decision-making by IAAC on whether further assessment is required under section 16 of the Impact Assessment Act. ...
1 alternate format found
French PDF
  • Relevance: 329.78
  • 1 Sommaire des questions Projet de centrale électrique au gaz naturel Marshdale Le sommaire des questions décrit les enjeux clés que l'Agence d'évaluation d’impact du Canada (AEIC) juge pertinents pour le processus fédéral d'évaluation d’impact pour le projet de centrale électrique au gaz naturel Marshdale (le projet). La réponse du promoteur au sommaire des questions permettra d’éclairer la décision de l'AEIC quant à savoir si une évaluation d’impact approfondie est requise en ...

Document Summary of the Initial Project Description of a Designated Project

  • Project Marshdale Natural Gas Power Generation Facility Project
  • Document Category: For Public Participation
  • Reference Number: 2
  • Document Date: 2025-12-15
  • Document: 164293E.pdf
  • Relevance: 373.98
  • December 2025 ENVIRONMENTAL ASSESSMENT REGISTRATION DOCUMENT & INITIAL PROJECT DESCRIPTION Plain Language Summary Fast Acting Natural Gas Power Generation Facility – Marshdale (IAAC Project Title: Marshdale Natural Gas Power Generation Facility) Prepared for: IESO Nova Scotia Environmental Assessment Registration Document & Initial Project Description December 15, 2025 Plain Language Summary Fast Acting Natural Gas Power ...
1 alternate format found
French PDF
  • Relevance: 322.98
  • Décembre 2025 DOCUMENT D'ENREGISTREMENT À L'ÉVALUATION ENVIRONNEMENTALE & DESCRIPTION INITIALE DU PROJET Résumé en langage simple Installation de production d'énergie au gaz naturel à action rapide – Marshdale (Titre du projet IAAC : Installation de production d'énergie au gaz naturel de Marshdale) Préparé pour: IESO Nouvelle-Écosse Document d'enregistrement de l'évaluation environnementale et description initiale du projet 15 ...