Hydro One D6 Line Relocation– Garrison Petawawa

Public Comment Period on Intent to Make a Determination
Hydro One D6 Line Relocation– Garrison Petawawa

August 11, 2026 — The Department of National Defence must decide whether the proposed project is likely to cause significant adverse environmental effects.

To help inform this decision, the Department of National Defence is inviting comments from the public on the project and its potential effects on the environment. All comments received will be considered public. For more information, individuals should consult the Privacy Notice on the Registry website.

Written comments must be submitted by August 30, 2026 to:
Joan Behnke, Realty Asset Manager
Mailing Address:  101 Menin Road, Garrison Petawawa
PO Box 9999, Stn Main
Petawawa, ON, Canada, K8H 2X3
E-mail:  Joan.Behnke@forces.gc.ca

or

Jeff Hankin, Environmental Planner
Mailing Address:  483 Bay Street, North Tower, 14th Floor
Toronto, ON, M5G 2P5
E-mail:  Jeff.hankin@hydroone.com

 

The Proposed Project

Hydro One's D6 transmission line requires relocation due to the existing transmission line corridor bisecting the increasingly active Ranges and Training Areas of Garrison Petawawa. The existing transmission line has also reached the end of its serviceability.

The project involves the preparations for, and installation of, single-circuit 115 kV wood or composite poled transmission line. Once completed, the new line transmission corridor will provide safe access to the line for maintenance, improve hydro reliability for the Ottawa Valley, support expanding Canada's Defence Operations and military residential housing development initiatives while minimizing impacts both to and by military activities.

Document reference number: 1

Date modified: