Heidelberg Materials Shoreline Repair
Public notice
Heidelberg Materials Shoreline Repair – Public comments invited
July 28, 2025 – As part of its Project and Environmental Review process, the Vancouver Fraser Port Authority must determine whether the proposed Heidelberg Materials Shoreline Repair – Surrey, located at 12366 Musqueam Drive, Surrey, are likely to cause significant adverse environmental effects.
To help inform this determination and a decision on whether or not to approve the proposed project, the Vancouver Fraser Port Authority is inviting comments from the public respecting that determination. All comments received will be considered public and may be posted online. For more information, individuals should consult the Privacy Notice on the Registry website. In addition, your contact information may be shared with third parties, e.g., the tenant, other relevant agencies, to help respond to your questions and inform possible mitigations.
Written comments must be submitted by August 27, 2025 to:
Vancouver Fraser Port Authority
Project and Environmental Review
100 The Pointe, 999 Canada Place
Vancouver, B.C. Canada V6C 3T4
per@portvancouver.com
The proposed project
Heidelberg Materials Canada Limited (Heidelberg) proposes to conduct works to stabilize an eroding stretch of shoreline along the south bank of the Fraser River Heidelberg's Surrey Depot generally located at 12366 Musqueam Drive, Surrey BC. The shoreline stabilization will require the removal of an existing creosote timber pile wall and eight mature trees along the Fraser River shoreline. The eroding shoreline will be regraded and armoured using filter rock overlaid with riprap. Eight cedar root wads will be installed along the project shoreline to provide habitat cover for fish.
The Project consists of the following:
- Mobilization and staging of equipment and machinery along the shore
- Removal of an existing creosote timber pile wall and eight cottonwood trees along the shoreline
- Localized excavation on the shoreline to a benched elevation for machinery work platform
- Slot cutting excavation and installation of filter rock and riprap during low tide windows
- Replacement of benched material and shoreline protection up to original grades
- Installation of eight tree root wads for fish habitat cover
- Installation of new drive barriers (lock block or no-post barriers)
- Site demobilisation and clean up.
The works are proposed to take place from the landside with no marine staging required. To the extent possible, works below the highwater mark would be carried out during the lowest tides, therefore tidally dependent work may be done outside of normal working hours. The Project works are proposed to take place in 2025 and be during the Fraser River least-risk timing window (June 16 to Feb 28).
Document reference number: 1